7 of 20 ITEM NO: 009-60
FY-24
3.5.4.1 The weekly progress report must indicate the total hours, within
the 3.5.1 Manpower Loading Curve, which are attributed to work pending descope and pending
growth RCCs. This must not include unallocated LOE to completion.
3.6 Provide a representative whose function is to coordinate and schedule AIT,
Government-Contracted Third Party Maintenance Providers, S/F, CIS, and FMA work with
contractor work into the IPS.
3.6.1 The representative must meet with the SUPERVISOR, AIT, Government-
Contracted Third Party Maintenance Providers, S/F, CIS, and FMA between contract award and
A-0. Commencing at A-0, this engagement must occur daily to compare and coordinate
programmed AIT, Government-Contracted Third Party Maintenance Provider, S/F, CIS, and
FMA work with the IPS.
3.6.2 Coordinate AIT, Government-Contracted Third Party Maintenance Provider,
S/F, CIS, and FMA work integration into the IPS prior to setting the Schedule of Record (SOR).
(See 4.1.22).
3.6.2.1 The representative must develop a report identifying missing or
incomplete schedule integration data for known participants in the availability when the SOR is
submitted. Identification of missing or incomplete schedule integration data is required to
highlight areas of elevated IPS uncertainty, but must not be cause for delay in establishing the
SOR nor the delivery of reports required under this Standard Item.
3.6.3 Incorporate updated progress from AIT, Government-Contracted Third Party
Maintenance Providers, S/F, CIS, FMA, and other maintenance providers into the IPS.
3.6.3.1 Provide a common template in Microsoft Excel compatible
format to facilitate submission of progress updates of 3.6.3.
3.6.4 Identify, at the weekly progress meeting, schedule conflicts where
programmed AIT, Government-Contracted Third Party Maintenance Provider, S/F, CIS, and
FMA work interferes with previously scheduled contractor work.
3.6.5 Identify, at the weekly progress meeting, required AIT, Government-
Contracted Third Party Maintenance Provider, S/F, CIS, and FMA prerequisite actions necessary
to support contractor testing and equipment operation schedule.
3.7 Provide cognizant shipyard management representation to participate in the weekly
progress meeting at the time and location agreed to by the SUPERVISOR. The representative(s)
must be authorized to make management decisions relative to the routine requirements,
implementation of corrective actions for each schedule shortfall that, in good faith, commit the
contractor. Discussion will include the Schedule Analysis of 3.4 and each work item of concern.
3.8 Participate in review conferences at the 25, 50, and 75 percent points in the
availability. Data from the most recent submission in accordance with 3.9.3 will be used at the
review conferences. Review conferences will be held within 2 days of the Weekly progress
Meeting of 3.7 or, subject to SUPERVISOR approval, may be held simultaneously with the