Contents
Get Help ................................................................................................................................ i
1
Introduction
1
Overview of Oracle Project Portfolio Management Cloud Services ..................................................................................... 1
Workflows in Oracle Project Management ............................................................................................................................... 3
The Project Contract Invoice Approval Workflow .................................................................................................................. 10
The Financial Plan Version Approval Workflow ..................................................................................................................... 17
Oracle Fusion Cloud Project Management Profile Options ................................................................................................. 51
Where to Find Information About Scheduled Processes in Projects ................................................................................ 55
2
Implement Project Financial Management Applications
59
Overview of Project Financial Management and Grants Management Offerings ......................................................... 59
Organization Structures for Project Financial Management .............................................................................................. 63
Project Foundation ...................................................................................................................................................................... 69
Project Control .............................................................................................................................................................................. 82
Project Costing ............................................................................................................................................................................ 103
Project Billing ................................................................................................................................................................................ 113
Project Performance Reporting ................................................................................................................................................ 118
Project Templates ....................................................................................................................................................................... 124
3
Implement Project Execution Management Applications
127
Overview of Project Execution Management Offering Implementation ......................................................................... 127
Common Project Execution Options ...................................................................................................................................... 128
Project Management Configuration ....................................................................................................................................... 134
Project Resource Management Configuration ..................................................................................................................... 137
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Get Help
Get Help
There are a number of ways to learn more about your product and interact with Oracle and other users.
Get Help in the Applications
Use help icons to access help in the application. If you don't see any help icons on your page, click your user image
or name in the global header and select Show Help Icons.
Get Support
You can get support at My Oracle Support. For accessible support, visit Oracle Accessibility Learning and Support.
Get Training
Increase your knowledge of Oracle Cloud by taking courses at Oracle University.
Join Our Community
Use Cloud Customer Connect to get information from industry experts at Oracle and in the partner community. You
can join forums to connect with other customers, post questions, suggest ideas for product enhancements, and watch
events.
Learn About Accessibility
For information about Oracle's commitment to accessibility, visit the Oracle Accessibility Program. Videos included in
this guide are provided as a media alternative for text-based topics also available in this guide.
Share Your Feedback
We welcome your feedback about Oracle Applications user assistance. If you need clarification, find an error, or just
want to tell us what you found helpful, we'd like to hear from you.
You can email your feedback to oracle_fusion_applications_help_ww_grp@oracle.com.
Thanks for helping us improve our user assistance!
i
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Get Help
ii
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
1 Introduction
Overview of Oracle Project Portfolio Management Cloud
Services
Oracle Project Portfolio Management Cloud is a complete and integrated solution which dramatically improves the
way project-driven organizations work, enabling efficient and effective project management while ensuring smarter
business decisions based on a single source of project truth.
Oracle Project Portfolio Management Cloud Services include the following applications.
Project Financial Management Offering
Oracle Fusion Project Control Cloud Service
Oracle Fusion Project Costing Cloud Service
Oracle Fusion Project Billing Cloud Service
Oracle Fusion Project Contracts Cloud Service
Oracle Fusion Project Performance Reporting Cloud Service
Project Execution Management Offering
Oracle Fusion Project Management Cloud Service
Oracle Fusion Task Management Cloud Service
Oracle Fusion Project Resource Management Cloud Service
Applications in the Project Financial Management Offering
Project Financial Management applications in the Oracle Project Portfolio Management Cloud Service enable you to
plan, organize, and manage activities, resources, cost, billing, and revenue to bring about the successful completion of
specific project goals and objectives.
This table lists the Project Financial Management applications available on cloud.
Application Description
Project Foundation
Includes common components that are shared across Oracle Fusion Project Portfolio Management.
Includes the basic project plan structure and components such as resource breakdown structures, rate
schedules, pricing, burdening, and cross-charge processing.
Project Control
Provides full-function project planning, progress management, as well as budgeting and forecasting.
Project Costing
Captures and processes commitments and costs from Oracle Fusion Applications and third-party
applications.
1
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Application Description
Project Billing
Accelerates invoice processing while reducing billing errors through a functionally rich work area
offering visibility into formatted invoices with estimated taxes. Embedded analytics for contract
revenue, invoice, profitability and margin give insight into potential contract and payment problems.
Project Performance Reporting
Helps project-driven organizations keep pace through project performance insight. It allows project
stakeholders to receive answers to critical business questions and take action in real time, utilizing a
multidimensional model to deliver the right information at the right time.
Enhance contract management and reporting capabilities by subscribing to the following services:
Oracle Fusion Enterprise Contracts Management Base Cloud Service
Oracle Fusion Transactional Business Intelligence for Projects Cloud Service
Applications in the Project Execution Management Offering
Project Execution Management applications in the Oracle Project Portfolio Management Cloud Service enable you to
work together to plan and deliver projects, collaborate on project and non-project tasks all in one place, and find best-fit
project resources to staff projects.
This table lists the Project Execution Management applications available on cloud.
Application Description
Project Management
Extends project planning, management, and scheduling capabilities to all individuals within the
enterprise who are required to manage project-based work Project managers can engage with team
members to develop tasks, resolve issues, report progress, and monitor the status of the project to
ensure that objectives are met.
Task Management
Lets organizations manage all work and related interactions in a consolidated place. Team members,
challenged by the quantity of tasks they own, no longer have to track administrative and project work
in different places since all tasks are managed in a single view.
Resource Management
Enables organizations to optimize the allocation and utilization of their most precious resource: their
people. Innovative and intuitive tools let resource managers and project managers ensure that the
best-fit resource is identified and placed on each and every project assignment, to the benefit of
the organization, the project resource, and the end customer, for either internal or external billable
projects.
Project Portfolio Management Implementation Documentation
This guide contains procedures that enable you to quickly and efficiently configure Project Financial Management and
Project Execution Management applications to meet your business requirements.
For additional information before implementing the Project Portfolio Management applications, see the following
guides:
Oracle ERP Cloud Securing ERP
Oracle Applications Cloud Using Common Features
2
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Oracle Applications Cloud Using Functional Setup Manager
For additional information on implementing Project Portfolio Management applications, see the following guides:
Oracle Project Portfolio Management Cloud Implementing Project Financial Management
Oracle Project Portfolio Management Cloud Implementing Project Execution Management
Workflows in Oracle Project Management
This topic introduces workflows and explains how you can implement workflows in Oracle Project Portfolio
Management Cloud to simplify and optimize complex processes.
What's a workflow?
One of the chief goals of software is to simplify workflows. Coupled with automation and intelligent routing, software
becomes a powerful tool for simplifying lives.
But what's a workflow?
A workflow is a sequence of tasks, designed to accomplish a specific result.
Workflows simplify complex processes, breaking them down into smaller, simpler tasks that can be
accomplished with relative ease.
Some workflow tasks are one-person activities; others may require multiple persons working together, or in
parallel.
If team members in a workflow complete their assigned tasks at the right time, the workflow should reliably
deliver the expected result.
Workflows can be implemented as processes and procedures in teams, where they help streamline operation.
Implemented as software, however, workflows move faster, become more reliable, and handle a sizeable percentage of
tasks without human intervention.
For example:
If the user requesting a cost adjustment has the privilege required to approve cost adjustments, the application
can be configured to skip the entire workflow and automatically approve the adjustment.
On the other hand, if your organization mandates some oversight to cost adjustments, the same workflow can
be configured to skip all intermediate approval tasks and directly route the adjustment request to someone who
leads financial management for that project.
Project Portfolio Management Cloud Workflows
The following tables list out some of the key workflows in Oracle Project Portfolio Management Cloud.
The first table lists out those workflows that are available in Project Financial Management.
The second table lists out those workflows that are available in Project Execution Management.
The third table lists out those workflows that are available in both Project Financial Management and Project
Execution Management.
3
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
You can access all of these workflows using the Task Configuration page in BPM Worklist. For information on how
to access BPM Worklist and search for workflows, see Search for Workflow Tasks to Configure in the Implementing
Applications guide.
Note: Apart from the PPM workflows in the table below, there are project-related approval workflows, such as
approval of project-related AP invoices, project contracts (for billing), project time cards, and so on, in other subledger
applications. You can find guidance on these workflows in documentation associated with the application to which
they belong. The section below the table lists out these workflows and tells you where you can find them.
Workflows Available in Project Financial Management
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
Project Contract
Invoice Approval -
InvoiceApprovalHumantask
When an invoice
is submitted for
approval, this
workflow notifies the
administrator of the
contract associated
with the invoice, who
must approve or reject
the submitted invoice.
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
No Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: None
Yes
Generate Financial
Plan Amounts
Notification -
HumantaskNotification
When the Generate
Financial Plan
Amounts process is
run, this workflow
sends a non-action
notification to the
person who submitted
the process.
No No Workflow
Modifications: None
Notification
Customizations: None
N/A
Project Financial Plan
Approval (Budgets
and Forecasts) -
ApprovePlanVersion
When a financial plan
version is submitted
for approval, this
workflow notifies the
configured approvers,
who must approve
or reject the financial
plan version. It also
sends a non-action
notification to the
project manager of the
plan version and the
user who initiated the
workflow.
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
Yes. Use the Manage
Financial Plan Types
task in Setup and
Maintenance to
enable/disable a plan
type for workflow
approval.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: /
Shared Folders/
Projects/Workflow
Notifications/
Project Control/
FinancialPlanVersionApprovalTemplate
Yes
For workflows that are
in process, you can
use the Spectacles
icon on the Manage
Budget Version and
Manage Forecast
Versions pages. The
Approval History
popup shows you
to whom a workflow
has previously been
assigned, to whom it
is currently assigned,
and to whom it will be
assigned in the future.
Project Financial Plan
Approval (Budgets
and Forecasts) -
NotifyFinancialPlanApproved
When a financial plan
version is approved
by the configured
approver, this
workflow sends a non-
No Yes. Use the Manage
Financial Plan Types
task in Setup and
Maintenance to
enable/disable a plan
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Yes
4
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
action notification
to the configured
recipients indicating
that a plan version has
been approved by the
configured approver.
type for workflow
approval.
Modify
Participants and
Stages: Yes
Notification
Customizations: None.
Project Financial Plan
Approval (Budgets
and Forecasts) -
NotifyFinancialPlanRejected
When a financial plan
version is rejected
by the configured
approver, this
workflow sends a non-
action notification
to the configured
recipients indicating
that a plan version has
been rejected by the
configured approver.
No Yes. Use the Manage
Financial Plan Types
task in Setup and
Maintenance to
enable/disable a plan
type for workflow
approval.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: None.
Yes
Project Financial Plan
Approval (Budgets
and Forecasts) -
NotifyFinancialPlanReworked
When a financial plan
version is reworked
and submitted
for approval, this
workflow notifies the
configured approvers,
who must approve
or reject the financial
plan version. It also
sends a non-action
notification to the
project manager of the
plan version and the
user who initiated the
workflow.
No Yes. Use the Manage
Financial Plan Types
task in Setup and
Maintenance to
enable/disable a plan
type for workflow
approval.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: None.
Yes
Project Cost
Adjustment Approval -
ApproveAdjustment
When any of the
following project
cost adjustments
is attempted by a
user, this workflow
notifies the configured
approver, who must
approve or reject
the project cost
adjustment.
Transfer
Split
Split and transfer
Set to billable
Set to nonbillable
Set to
capitalizable
Set to
noncapitalizable
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
Yes. The workflow is
only initiated if the
user performing the
adjustment has not
been assigned the
duty role Project Cost
Adjustments Approval,
or one or more of the
privileges within it.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations Yes
/Shared Folders/
Projects/Workflow
Notifications/
Project Cost/Project
Cost Transactions
Adjustment Approval
Report
Yes. For workflows
that are in process,
you can use the
Spectacles icon on the
Adjustment History
tab of the Manage
Project Costs > Project
Cost Transaction page.
5
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
Hold invoice until
released
Hold invoice once
Release invoice
hold
Hold revenue
until released
Release revenue
hold
Change work
type
Project Cost
Adjustment Approval -
NotifyAdjustmentApproval
When a project
cost adjustment is
approved or rejected
by the configured
approver, this
workflow sends a non-
action notification
to the requestor and
approver of the project
cost adjustment
approval.
No Yes. The workflow is
only initiated if the
user performing the
adjustment has not
been assigned the
duty role Project Cost
Adjustments Approval,
or one or more of the
privileges within it.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: None.
No
Project Expenditure
Batch Approval -
ProjectExpenditureBatchApprovalTask
When a project
expenditure batch
is submitted for
approval, this
workflow notifies the
configured approver,
who must approve
or reject the project
expenditure batch.
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
Yes. Use the Manage
Project Transaction
Sources task in Setup
and Maintenance
to enable/disable
Requires expenditure
batch approval at the
document level.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: Yes
/Shared Folders/
Projects/Workflow
Notifications/
Project Cost/
ProjectExpenditureBatchApprovalReport
Yes. For workflows
that are in process,
use the Spectacles
icon on the Manage
Expenditure Batches
page to access the
Approval History
popup.
Project Expenditure
Batch Approval -
ProjectExpenditureBatchApprovalNotifyTask
When a project
expenditure batch is
approved or rejected
by the configured
approver, this
workflow sends a non-
action notification
to the configured
recipients of the
outcome of the project
expenditure batch
approval.
No Yes. Use the Manage
Project Transaction
Sources task in Setup
and Maintenance
to enable/disable
Requires expenditure
batch approval at the
document level.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: None.
Yes. For workflows
that are in process,
you can use the
spectacles icon on the
Manage Expenditure
Batches page. The
Approval History
popup shows you
to whom a workflow
has previously been
assigned, to whom it
is currently assigned,
and to whom it will be
assigned in the future.
6
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
Project Labor
Schedule Version
Status Change
Approval -
LaborScheduleVersionStatusApproval
When a labor schedule
version is set Active
status from New or
Inactive, this workflow
notifies configured
users that the labor
schedule version is
being set to active and
that costs will start to
be distributed through
it once it is approved
via this workflow.
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
The workflow is
only invoked if the
customer has created
the profile defined
here and set to Yes
This is to only fire the
workflow when set, to
reduce the amount of
technologies involved
if customer does not
want it at all. Auto-
approval workflows
still sometimes have
issues. This is to be
replaced with the
upcoming revamped
Projects Process
Configurator.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations Yes
/Shared Folders/
Projects/Workflow
Notifications/Project
Cost/Labor Schedule
Version Status
Approval Execution
Report
Yes, but only for the
user who created
the project labor
schedule version, and
the approver, in the
Notifications page.
Workflows Available in Project Execution Management
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
Task and Action
Item Notification -
TaskEmailNotificationHumantask
When any of the
following is true,
this workflow sends
notifications to the
task owner and
follower.
A follower is
added.
A followed task is
completed.
A task, action
item, to-do task
or milestone is
assigned.
Troubleshooting:
Yes
Configure Rules:
No
Bypass
Approvals: No
No Workflow
Modifications: None
Notification
Customizations: Yes
/Shared Folders/
Projects/Workflow
Notifications/
Project Management
Control/Task Details
Notifications
No
Project Manager
Daily Digest -
emailDigestHumantask
When it is time to send
regular notifications
containing status of
tasks, issues, action
items, deliverables,
change orders, and
task exceptions, this
workflow sends non-
action notifications
to project managers
No Yes. The Generate
Project Updates E-
Mail process can be
scheduled to pick
any new events that
occurred since the last
time the process was
run.
Workflow
Modifications: None
Notification
Customizations: None
No
7
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
about important
status changes for
tasks, issues, action
items, deliverables,
change orders, and
task exceptions.
The process sends
notifications to anyone
who's designated as
a project manager
and who has set their
email notification
preferences to receive
these notifications.
Change Orders
Notification -
ChangeManagementEventNotificationHumantask
When any of the
following events
occurs, this workflow
sends a notification
to the change order
creator, impact
assessors, reviewers,
approvers, and
implementers.
Change order
is created or
reassigned
to a different
resource.
Change order is
closed.
Change order is
canceled.
Change order
is approved or
rejected.
Work on
change order is
completed.
Participant is
removed from
change order.
Participant is
added to change
order
Note that approvers
only receive
notifications that
they need to approve;
they must go to
the application and
approve the change
order manually.
No No Workflow
Modifications: None
Notification
Customizations: Yes
/Shared Folders/
Projects/Workflow
Notifications/
Project Management
Control/Change
Order Participant
Notifications
(Notification that's
sent when participants
are assigned or
removed from a
change order)
/Shared Folders/
Projects/Workflow
Notifications/
Project Management
Control/Change Order
Stage Completion
Notifications
(Notification
that's sent when a
participant completes
a stage, approves
a change order, or
rejects a change order)
/Shared Folders/
Projects/Workflow
Notifications/Project
Management Control/
Change Order Stage
Change Notifications
(Notification that's
sent when a change
order is assigned,
closed, or canceled.)
No
Deliverable
Notification -
DeliverablesNotificationsHumanTask
When a deliverable
is completed, this
workflow sends a non-
action notification to
No No Workflow
Modifications: None
No
8
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
the creator, owner, and
project manager.
Notification
Customizations: None
Workflows Available in Both Project Financial Management and Project Execution Management
Workflow Name -
BPM Task Name
Workflow Trigger and
Description
Supported in
Transaction Console?
Dependent on
Configuration?
Workflow
Modifications
and Notification
Customizations
Supported
View History
Available?
Project Status
Change Approval -
ProjectStatusNotificationApproval
When a user updates
and saves a project
status, this workflow
notifies the project
manager named on
the project, who must
approve or reject the
changes made to the
project status.
Troubleshooting: Yes
Configure Rules: No
Bypass Approvals: No
Yes. Use the Manage
Project Statuses
task in Setup and
Maintenance to enable
or disable project
statuses for workflow
approval. Simply use
the Enable Workflow
checkbox for each
project status.
Workflow
Modifications
Modify Rules and
Rulesets: Yes
Modify
Participants and
Stages: Yes
Notification
Customizations: Yes
/Shared Folders/
Projects/Workflow
Notifications/
Project Foundation/
ProjectStatusChangeApprovalReport
Yes. You can use
the View History
button on the Manage
Financial Project
Settings page to
review historic project
status changes.
For workflows that
are in process, you
can use the spectacles
icon on the Manage
Financial Project
Settings page. The
Approval History
popup shows you
to whom a workflow
has previously been
assigned, to whom it
is currently assigned,
and to whom it will be
assigned in the future.
Project-Related Workflows in Other Oracle Cloud Applications
Here's a table listing out some of the key project-related workflows in the other Oracle Cloud applications. Review the
associated docs for more information.
Business Object(s) Parent Application
Timecard HCM
Supplier Invoice Payables
Requisitions, Purchase Order Procurement
Project Billing Contract Enterprise Contracts
Expense Report Expenses
9
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Related Topics
Overview of Notifications and Approval Workflows
Actions and Statuses for Workflow Tasks
Overview of Configurable Workflow Notifications in Project Management
The Project Contract Invoice Approval Workflow
Every time someone submits a project contract invoice for approval, the application triggers the Project Contract Invoice
Approval workflow. This workflow notifies configured assignees, who must approve or reject the submitted invoice, or
seek more information if required.
In the BPM Worklist tool, this workflow is called InvoiceApprovalHumantask, and the default recipient of this workflow
is the administrator of the contract for which the invoice was raised.
Note: To instruct the application to skip the approval workflow when someone submits a project contract invoice
using the UI or a REST call, create a profile option named PJB_NO_INV_APPR_WF and set its value to Y.
The Contract Invoice Approval Process
The Contract Approval Process
Agent Description Additional Information
Billing Specialist Uses the Manage Invoices, Invoice Overview,
or Edit Invoice page to submit an invoice for
approval.
For information on working with invoices, see
the Using Project Revenue and Billing guide.
The Contract Invoice Approval Workflow As soon as someone submits a project contract
invoice, the workflow sends notifications to
all configured assignees via email or in-app
notifications, as configured.
For detailed information on how you can
customize approval workflow notifications, see
Workflow Notifications in the Implementing
Common Applications guide.
Workflow Assignees Assignees review and approve or reject the
invoice, or seek more information.
If the workflow uses parallel approvers, then
the Voting Percentage rule is used to determine
final approval.
For detailed information on using BPM
Worklist to update approval workflows, see
Workflow Approvals and Notifications in the
Implementing Common Applications guide.
The Contract Invoice Approval Workflow The workflow updates the invoice status to
Approved or Rejected.
NA
The Contract Invoice Approval Workflow The workflow performs the following tasks once
the invoice status is updated.
If the invoice is approved, the workflow
sends notifications to configured
If the invoice is approved, the Billing Specialist
can release the invoice.
If the invoice is rejected, the submitter (Billing
Specialist) moves the invoice back to Draft
status, updates it as appropriate, and resubmits
it for approval if required. This action retriggers
10
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Agent Description Additional Information
recipients if configured. Otherwise, the
workflow exits.
If the invoice is rejected, the application
sends a notification indicating the result to
the submittor (Billing Specialist).
the workflow, and designated approvers receive
new notifications, as configured.
Configuring the Project Contract Invoice Approval Workflow
For information on how you can configure the Project Contract Invoice Approval workflow, review the following topics in
the Creating Analytics and Reports for Financials guide:
Configuring Payables Workflow Notifications
Example of Modifying Invoice Approval Workflow Notifications Using Oracle Business Intelligence (BI) Publisher
For generic guidance on customizing workflows and notifications, see the Workflow Approvals and Notifications section
in the Implementing Applications guide.
Configurable Attributes in the Project Contract Invoice Approval workflow
There are many attributes that you can use to configure the Project Contract Invoice Approval workflow's behavior.
These attributes are associated with:
The invoice that is being processed (See Invoice Attributes, below)
The project with which the invoice is associated (See Project Attributes, below)
The contract with which the project is associated (See Contract Attributes, below)
Invoice Attributes
Here's a table that lists out key project contract invoice attributes that you can use to customize the behavior of the
Project Contract Invoice Approval workflow.
Key Invoice Attributes Used to Modify the Project Contract Invoice Approval workflow
Attribute Description
InvoiceId The unique identifier of the invoice.
InvoiceNum The sequential number that identifies the draft invoice within a project.
ContractId The identifier of the contract that funds the invoice.
BillToCustAcctId The identifier of the customer id to which invoices are sent.
BillToDate The date through which to invoice the project. Expenditure items with the expenditure item date on
or before the bill to date and events with completion dates on or before the bill through date may be
included on an invoice.
11
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
InvoiceDate The invoice date passed to Oracle Receivables, which is used to calculate the invoice due date. Upon
release of the invoice, this date is defaulted from the released date. The user can override the invoice
date at the time of release.
InvoiceStatusCode The code associated with the invoice's payment status. Possible values are Y, N, or P.
InvoiceTypeCode The code associated with the type of Invoice, such as Standard, Credit Memo, Write-Off, Net Invoice,
Canceled.
ApprovedDate The date on which the draft invoice is approved.
ApprovedByPersonId The unique identifier of the employee who approved the invoice.
OrgId The unique identifier of the business unit associated with the invoice.
ContractNumber The contract number associated with the invoice.
MajorVersion The major version number of the contract for which the invoice is created.
InvCurrInvAmt Amount for which the invoice is created.
ContractAdminEmail The email address of the administrator of the contract.
BillToCustName The name of the customer to whom the invoice is sent.
InvoiceCurrencyCode The currency code associated with the amount for which the invoice is generated.
ContractAdminName The name of the administrator of the contract.
InvoiceTypeName The invoice type, such as Standard, Credit Memo, Write-Off, Net Invoice, Canceled, used for the invoice.
BillFromDate The date through which to invoice the project.
CustPoNumber The purchase order against which the invoice is issued.
ContractTypeId The unique ID of the contract type to which the contract associated with the invoice belongs.
InvoiceComment Free text comments that can be printed on an invoice. The invoice comment is defaulted from the
invoice comment defined for the project. This value can be overridden by a user for each draft invoice.
CreditMemoReasonCode The reason code for releasing credit invoices.
InvoiceInstructions Invoice instructions.
ContractStatusCode The code associated with the contract's fulfillment status.
CreditedInvoiceId The identifier of the invoice that can be fully reversed by a credit or debit memo.
BillingTypeCode The code associated with the billing type used in the project.
ContractType This is a temporary table used internally by Oracle.
BillingType The billing type used in the project. This can either be External, Inter-Company, or Inter-Project.
12
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
CreditedInvoiceNumber The number of the invoice that must be fully reversed by a Credit or Debit Memo.
BUName The name of the business unit associated with the invoice.
CreditMemoReason Codes provided by the government or central bank of a country. These codes provide the payment
system or bank with additional details about the reason for the payment and are used for regulatory
reporting purposes.
ContractStatus The status of the contract, such as Draft, Canceled, Pending Approval, and so on.
ProjMgrsUserNames The names of the project managers associated with the project associated with the invoice.
ParallelVotingPercentage The percentage of votes that an invoice must receive to be approved.
Invoice Header Flexfields General information, such as supplier, supplier site, invoice number, invoice date, as well as default
information, used to create invoice lines.
Key Project Attributes Used by the Project Contract Invoice Approval
Workflow
Here's a table that lists out key project attributes that you can use to customize the behavior of the Project Contract
Invoice Approval workflow.
Note: You can find some of the attributes listed here in folders in the Condition Explorer in the Task Configuration tab
in BPM Worklist. The name of the folder is added to every such attribute in this table. Thus, for example, the attribute
ProjectTeamMember > ProjectPartyId can be found in the ProjectTeamMember folder.
Key Project Attributes Used to Modify the Project Contract Invoice Approval workflow
Attribute Description
ProjectId The unique identifier of the project.
ProjectName The name of the project.
ProjectNumber The project number.
CarryingOutOrganizationId The unique identifier of the organization that is executing the project.
ProjectOrganizationName The name of the organization that is implementing the project.
ProjectUnitId The unique identifier of the project unit that is implementing the project associated with the invoice.
ProjectUnitName The name of the project unit that is implementing the project associated with the invoice.
ProjectTypeId The unique identifier of the project type.
ProjectTypeName The name of the project type.
BusinessUnitId The unique identifier of the business unit.
13
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
BusinessUnitName The name of the business unit.
LegalEntityId The unique identifier of the legal entity that is implementing the project.
LegalEntityName The name of the legal entity that is implementing the project.
WorkTypeId The unique identifier of the work type associated with task for which the invoice is created.
WorkTypeName The name of the work type associated with the task for which the invoice is created.
ProjectCurrencyCode The currency code used by default with amounts in the project.
ProjectLedgerCurrencyCode The currency code used by default with amounts in the project ledger.
SponsoredFlag A flag indicating whether the project is sponsored.
ProjectTeamMember > ProjectPartyId The unique identifier of a party assignment to the project for a project team member associated with
the task for which the invoice is created.
ProjectTeamMember >
TeamMemberRoleId
The unique identifier of the role assigned to a project team member associated with the task for which
the invoice is created.
ProjectTeamMember >
TeamMemberRoleName
The name of the role assigned to a project team member associated with the task for which the invoice
is created.
ProjectTeamMember >
TeamMemberPersonId
The unique ID of a project team member associated with the task for which the invoice is created.
ProjectTeamMember >
TeamMemberEmailAddress
The email address of a project team member associated with the task for which the invoice is created
ProjectTeamMember >
TeamMemberUserName
The name of a project team member associated with the task for which the invoice is created
ProjectTeamMember > StartDateActive The start date of a project team member associated with the task for which the invoice is created.
ProjectTeamMember > EndDateActive The end date of a project team member associated with the task for which the invoice is created.
Project Flexfields Custom project-related flexfields created for use in your organization.
ProjectClassification >
ProjectClassCategory
The project class category to which the project associated with the invoice belongs.
ProjectClassification > ProjectClassCode The project class code that belongs to the project class category, to which the project associated with
the invoice belongs.
Contract Attributes
Here's a table that lists out key contract attributes that you can use to customize the behavior of the Project Contract
Invoice Approval workflow.
Key Contract Attributes Used to Modify the Project Contract Invoice Approval workflow
Attribute Description
ContractId The unique identifier of the contract associated with the invoice.
14
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
Contract Header Flexfields Custom contract-related flexfields created for use in your organization.
Project Contract Invoice Approval Workflow Notifications
The Project Contract Invoice Approval workflow sends notifications when:
An invoice requires approval.
An invoice is approved or rejected.
An invoice requires more information.
Contents of a Project Contract Invoice Approval Workflow Notification
A Project Contract Invoice Approval Workflow notification contains the following details:
Header
Invoice Approval for <Contract Number>
Task Number: <Task number associated with the invoice.>
Approval options (if sent to an approver)
Approve
Reject
Request Info
Contents Section
Invoice Number
Contract Number
Bill-to Customer
Invoice Type
Date
Invoice Amount in Invoice Currency
Tax Amount in Invoice Currency
Bill from Date
Bill-Through Date
Invoice Lines
Line Number
Description
Amount in Invoice Currency
Approval options (if sent to an approver)
Approve
Reject
15
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Request Info
Approval History: One row per approver.
Approvers
- Assigned to / Approved by / Rejected by <Name of Approver>
- Date and Time of Assignment / Approval / Rejection
Submitter
- Submitted by <Name of Submitter>
- Date and Time of Submission
Link to invoice
Customizing Project Contract Invoice Approval Workflow Notifications
For details on customizing Project Contract Invoice Approval Workflow notifications, see Example of Modifying Invoice
Approval Workflow Notifications Using Oracle Analytics Publisher.
For guidance on how you can work with workflow notifications in BPM Worklist tool, see Workflow Notifications in the
Common Implementing Applications guide.
Customizing Notification Templates
You can find the templates and data models used in the Project Contract Invoice Approval workflow in the Shared
Folders > Projects > Workflow Notifications > Project Billing folder in the Oracle BI Publisher catalog. In this folder,
the ProjectContractInvoiceApprovalReport file contains the template used in the notification report. Expand the
Project Billing > Data Model folder to access the ProjectContractInvoiceApprovalDM file, which contains the data
model used in the notification report.
For information on how you can customize notification templates, see Configurable Notifications in the Common
Implementation guide. For detailed instructions on how to customize Project Contract Invoice Approval workflow
notifications, see Example of Modifying Invoice Approval Workflow Notifications Using Oracle Analytics Publisher.
How-to: Setting up Auto-Approval for Project Contract Invoices
In this use case, you set up auto-approval for project contract invoices. This means that instead of routing all invoices to
the default participants who must review and approve new invoices, you will configure the InvoiceApprovalHumantask
such that all new invoices will be automatically approved and forwarded for processing.
To set up auto-approval for project contract invoices:
1. Navigate to Setup and Maintenance > Manage Task Configurations for Project Financial Management.
The BPM Worklist tool appears.
2. Search and open InvoiceApprovalHumantask.
3. Click the Edit Task icon to open the task in Edit mode.
4. Click the Assignees tab in the Task Configuration page.
This tab displays the participants of the workflow. These are the users who must approve project invoices
before they can be processed. Click on each of these participants to review the workflow rules that apply to
their approval choices.
5. Click on Contract Invoice Single Approver Participant in the workflow, then click on the Go to Rule icon, and
then on the Go to Rule option that appears.
The list of rules associated with the participant you selected appears.
16
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
By default, the workflow sends project contract invoices to the contract administrator for approval. You want to
remove this requirement, so the approval request will not be routed.
6. Select the check box adjacent to the Top Participant field in the THEN section of the rule. This enables the
Delete Action icon above the rule. Click this icon to delete the action. You have now removed the default
approver for your project invoices and must configure the rule such that it automatically approves all new
invoices.
7. Click the Insert Action icon above the now empty rule and, from the drop-down options that appear, select
Add Approver > Supervisory.
8. Enter 1 in the Number of Levels field.
9. Perform the following steps to add the Starting Participant. This is the first participant–typically a manager–in
the approval process.
a. Click the Search icon adjacent to the Starting Participant.
The Add Hierarchy Participant dialog box appears.
b. Select the Get User radio button to indicate that you want to specify a user who must approve invoices.
c. Click the Expression Builder icon adjacent to the Reference User field.
The Expression Builder dialog box appears.
d. Click the Task > creator option in the expression builder and click Insert into Expression.
The value in the Expression field now reads Task.creator.
e. Click OK to exit the expression builder and add task.creator as the reference user for the approver. This
instructs the workflow to make the creator of the task the approver.
f. Enter "" in the Hierarchy Type field to indicate that the task creator can belong to any hierarchy type.
g. Click OK to populate these details into the Starting Participant field.
The value in this field must now read HierarchyBuilder.getPrincipal(Task.creator,-1,"","").
10. Populate the Top Participant field with the same value. The top participant is the last approver of a request.
11. Set Auto Action Enabled to True.
12. Specify the Auto Action as "APPROVE" (including the quotation marks) to instruct the application to
automatically approve all project contract invoice approval requests.
13. Save and Commit your updates, and enter Comments as appropriate. Click OK.
You have now configured the InvoiceApprovalHumantask workflow to automatically approve all new project contract
invoice approval requests using the name of the task creator as the approver.
The Financial Plan Version Approval Workflow
Every time someone submits a budget version for baseline or a forecast version for approval, the application triggers
the Financial Plan Version Approval workflow. This workflow notifies the configured approvers, who must approve or
reject the financial plan version. It also sends a non-action notification to the project manager of the plan version and
the user who initiated the workflow.
In the BPM Worklist tool, this workflow is named ApprovePlanVersion. The project manager is the default approver for
this workflow.
17
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
How to Enable the Financial Plan Version Approval Workflow
In the Setup and Maintenance work area, go to the Manage Financial Plan Types task and select the Use workflow for
status changes check box for the financial plan type to which the budget or forecast versions belong.
Key Components of Approval Workflow
Using approval workflow, you can define complex and multistage routing rules. The key components of approval
workflow are:
Component Description
Oracle SOA Suite Approval Management
Extensions
Approval management extensions of the human workflow services from Oracle SOA Suite are the
core of approval functionality in Oracle Cloud. With these components, you can perform many key
integrated tasks for the approval functionality. Here are the key functions of approval management
extensions:
Integrates with Oracle HCM Cloud to derive approvers based on the supervisory, job role, and
position-based hierarchies defined in Oracle HCM Cloud.
Provides the framework for defining approval rules for various business documents like financial
plan version and invoice approvals.
Provides the ability to select complex routing patterns based on your business processes, such as
whether to route documents to approvers in sequential or in parallel manner.
Oracle Business Process Management
(BPM)
Provides an interface named BPM Worklist for business users to perform the following key activities
related to approval management:
Provides an interface to work with various notifications tasks assigned to them. The BPM Worklist
is a web-based application that displays all worklist tasks that're assigned to business users and
they can perform various approval-related actions on the tasks assigned to them. Using this
application, users can drill down to the task assigned to them, for example, an approver can drill
down to the Financial Plan Approval Notification task to see the budget version details like version
amounts and a requester can perform the necessary approval action.
Provides an interface to set up and manage approval rules.
Oracle Human Capital Management Cloud
(Oracle HCM Cloud)
Used for defining various employee hierarchies like supervisory, job-based, or position-based.
Approval management extensions integrate with Oracle HCM Cloud to derive the required approvers if
approval rules are configured based on Oracle HCM Cloud hierarchies.
Human Task Workflow Concepts
To set up an approval hierarchy, you must define these as part of your workflow rules.
Concept Description
List Builders
Approval management determines the nature of the approvers required for a workflow approval using
list builders. Each approval rule is associated with a list builder for generating the list of approvers. The
Financial Plan Version Approval workflow supports the following list builders:
Supervisory
18
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Concept Description
Job Level
Position
Approval Group
Resource
Note: For more information about List Builders and how to define them, see Workflow Approval and
Notifications in the Implementing Applications guide.
Participants
A participant is a user or set of users who participate in the approval process. Each participant is
associated with a rule set. Approval rules are defined in the context of a rule set and you can create
many rules under one rule set. Based on your approval requirements, you must configure the approval
rules in the context of a participant. The different types of participants that can be configured are:
Serial
Parallel
Single
For Your Information (FYI)
Note: For more information about participants, see Workflow Approval and Notifications in the
Implementing Applications guide.
Participant Model Implemented in Financial Plan Version Approval
Workflow
The Financial Plan Version Approval workflow uses the ApprovePlanVersion human task. You must configure this task
for financial plan version approvals. This task is shared by the budget and forecast approval requests and includes the
same participants for both the budget and forecast requests.
For financial plan approvals, a total of 13 participants are predefined. Out of these 13, the two key participants are the
Approver and Requester. The Approver is an active participant to send approval notifications to the project manager
(default approver). The Requester is an FYI participant to send FYI notifications to the requester who submits the
budget for baseline or the forecast for approval.
The participant model that's implemented for the financial plan version approval supports both the parallel and
sequential mode of approvals:
Parallel Mode: The task is assigned and notifications go to all participants at once in parallel. For example,
participants 3 to 6 in the below figure are defined as parallel participants.
Sequential Mode: The task is assigned and notifications go in sequential mode, meaning one after another,
to each participant. All participants have to approve sequentially for the task to be approved. For example,
participants 7 to 13 in the below figure are defined as sequential participants.
19
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Some points to consider:
Only Approver and Requester participants are enabled by default. You must enable the other participants as
required.
The default approval rules in all the predefined rule sets are configured to send notifications to the project
manager for approvals. Review the predefined rules and modify them as required.
You can disable participants that you don’t want to use by enabling the Ignore Participant option or by defining
a rule to ignore the participant.
You can’t change the order of the predefined participants.
You can’t add participants.
The following figure indicates the predefined participant model for the ApprovePlanVersion task.
20
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
21
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Here are the details of the participants defined in the financial plan version approval workflow. Each participant is
associated with a predefined rule set.
Number Participant Name Rule Set Participant Type
1
Approver
BudgetForecastAMXRuleSet
Serial
2
Requester
NA
FYI
3
Financial Plan Approval Single Participant
1
ProjectBudgetsandForecastsApprovalSingleRuleSetOne
Single
4
Financial Plan Approval Parallel
Participant 1
ProjectBudgetsandForecastsApprovalParallelRuleSetOne
Parallel
5
Financial Plan Approval Serial Participant
1
ProjectBudgetsandForecastsApprovalSerialParticipantOne
Serial
6
Financial Plan Approval FYI Participant 1
ProjectBudgetsandForecastsApprovalFYIRuleSetOne
FYI
7
Financial Plan Approval Single Participant
2
ProjectBudgetsandForecastsApprovalSingleRuleSetTwo
Single
8
Financial Plan Approval Parallel
Participant 2
ProjectBudgetsandForecastsApprovalParallelRuleSetTwo
Parallel
9
Financial Plan Approval Serial Participant
2
ProjectBudgetsandForecastsApprovalSerialRuleSetTwo
Serial
10
Financial Plan Approval FYI Participant 2
ProjectBudgetsandForecastsApprovalFYIRuleSetTwo
FYI
11
Financial Plan Approval Single Participant
3
ProjectBudgetsandForecastsApprovalSingleRuleSetThree
Single
12
Financial Plan Approval Parallel
Participant 3
ProjectBudgetsandForecastsApprovalParallelRuleSetThree
Parallel
13
Financial Plan Approval Serial Participant
3
ProjectBudgetsandForecastsApprovalSerialRuleSetThree
Serial
The Financial Plan Version Approval Process
Here's how the Financial Plan Version Approval process works.
22
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Task Number Agent Description Comments
1
Project Administrator
Uses the Manage Budget Versions,
Edit Budget Version, Manage
Forecast Versions, or Edit Forecast
Version page to submit a budget or
a forecast for approval.
For information on working
with budgets or forecasts, see
Considerations for Creating
Budgets and Forecasts in the
Defining and Managing Financial
Projects guide.
2
ApprovePlanVersion
As soon as someone submits a
financial plan for approval, the
workflow sends notifications to
all configured assignees using
email or in-app notifications, as
configured.
When a budget or forecast version
for a project template is submitted,
the application skips the workflow
and the version is set to Baseline or
Approved status respectively.
For information on how you can
customize approval workflow
notifications, see Workflow
Notifications in the Implementing
Applications guide.
3
Workflow Assignees
Assignees review and approve or
reject the financial plan.
If the workflow uses parallel
approvers, then the Voting
Percentage rule is used to
determine the final approval.
For information on using BPM
Worklist to update approval
workflows, see Workflow
Approvals and Notifications in the
Implementing Applications guide.
Also, see the Use Cases section in
this topic.
4
ApprovePlanVersion
If the assignee rejects the financial
plan, then the workflow updates
the budget or forecast status to
Current Working. If the assignee
approves the financial plan, then
the budget status is set to Current
Baseline and the forecast status is
set to Approved.
NA
5
ApprovePlanVersion
The workflow performs the
following tasks once the financial
plan is submitted.
If the financial plan is
approved, the workflow sends
notifications to configured
recipients if configured.
Otherwise, the workflow exits.
If the financial plan is
rejected, the application
sends a notification indicating
the result to the submitter
(Project Administrator).
NA
23
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
You can withdraw the submitted budget while it’s still under approval. However, in the following error scenarios, you can
withdraw budget approvals only after two hours from the time the budget is submitted for approval:
Approval history doesn't exist.
Approvals are done but the budget is still in the Submitted status.
If the workflow is stuck due to an error, for example during rule evaluation, its indicated on the Approval History dialog
box and you can't withdraw the budget approval. The application administrator can review the status of the workflow in
the Transaction Console and either recover or withdraw the workflow.
Configure Financial Plan Version Approval Workflow
You can configure approval rules in the context of a rule set using BPM Worklist. To configure rules for this workflow,
you must have the Projects Application Administrator job role.
1. In the Setup and Maintenance work area, go to the Define Approval Management for Project Financial
Management task.
2. Click Manage Task Configurations for Project Financial Management.
3. In the Tasks to be configured pane, search for your human task workflow. Enter the name of your human task
workflow in the Search field and click Search task types. For example, to search for the Financial Plan Version
Approval workflow, enter ApprovePlanVersion and click Search task types.
4. Verify that the human task workflow appears underneath the Search.
5. Select the task and click Edit task on the panel header.
6. Click the Assignees tab on the right to view the predefined participants for the human task workflow.
7. Select the appropriate participant and click Go to rule to navigate to the relevant rule set.
The structure of a workflow approval rule is as follows:
1. Each rule consists of an IF and THEN component.
2. In the IF section of the rule, define the condition that determines if the rule should be applied. If needed, you
can define multiple conditions.
3. In the THEN section of the rule, define how approvals will be generated if the conditions are met. The THEN
component consists of a:
List builder and related attributes.
Response type that indicates if the assignees are required to respond or if they will receive an FYI
notification.
Automatic action setting that lets you set an automatic response. For example, automatically approve or
reject.
Some points to consider:
The default approval rules in all the predefined rule sets are configured to send notifications to the Project
application administrator for approvals. Review the predefined rules and modify them as required.
You can disable participants that you don’t want to use by enabling the Ignore Participant option or by
defining a rule to ignore the participant.
For generic guidance on customizing workflows and notifications, see Workflow Approval and Notifications in
the Implementing Applications guide.
24
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Supported Attributes
The attributes that can be used to modify the behavior of this workflow are as follows:
Plan Version Payload attributes - These attributes are associated with the version that's being processed.
Project Attributes - These attributes are associated with the project that's associated with the budget or
forecast.
Budget Attributes - These attributes are associated with the budget that's being processed.
Forecast Attributes - These attributes are associated with the forecast that's being processed.
Plan Version Payload Attributes
Attribute Description
projectName
The name of the project.
projectNumber
The unique identifier of the project.
awardNumber
The award number.
awardId
The unique identifier of the award.
businessUnit
The unique identifier of the business unit.
projectUnit
The name of the project unit that's implementing the project that's associated with the budget or
forecast.
planVersionName
The name of the budget or forecast version.
planVersionNumber
The unique identifier of the budget or forecast version.
requestorName
The name of the person requesting approval of the budget or forecast version.
approverName
The name of the person approving the budget or forecast version.
principalInvestigator
The name of the person acting as the principal investigator of the award budget.
SummaryAmounts --> peopleEffort
The labor effort amount of the budget or forecast version.
SummaryAmounts --> equipmentEffort
The equipment effort amount of the budget or forecast version.
SummaryAmounts --> pcRawCost
The raw cost amount of the budget or forecast version in project currency.
SummaryAmounts --> pcBurdenedCost
The burdened cost amount of the budget or forecast version in project currency.
25
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
SummaryAmounts --> pcRevenue
The revenue amount of the budget or forecast version in project currency.
SummaryAmounts --> pfcRawCost
The raw cost amount of the budget or forecast version in project ledger currency.
SummaryAmounts --> pfcBurdenedCost
The burdened cost amount of the budget or forecast version in project ledger currency.
SummaryAmounts --> pfcRevenue
The revenue amount of the budget or forecast version in project ledger currency.
SummaryAmounts --> margin
The margin amount of the budget or forecast version in project ledger currency.
SummaryAmounts --> marginPercent
The margin percentage of the budget or forecast version in project ledger currency.
planTypeName
The name of the financial plan type that's associated with the budget or forecast version.
planningAmount
The presence of cost amounts, revenue amounts, or both in a budget or forecast version.
projectNumAct
The system generated number of the project which starts at one and keeps incrementing.
versionNumAct
The system generated number of the budget or forecast version which starts at one and keeps
incrementing.
Project Attributes
Note: Some of the attributes listed here can be found in folders in the Condition Explorer. The name of the folder is
added to every such attribute in this table. Thus, for example, the attribute ProjectTeamMember > ProjectPartyId can
be found in the ProjectTeamMember folder.
Attribute Description
ProjectId
The unique identifier of the project.
ProjectName
The name of the project.
ProjectNumber
The project number.
CarryingOutOrganizationId
The unique identifier of the organization that's executing the project.
ProjectOrganizationName
The name of the organization that's implementing the project.
26
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
ProjectUnitId
The unique identifier of the project unit that's implementing the project that's associated with the
budget or forecast.
ProjectUnitName
The name of the project unit that's implementing the project that's associated with the budget or
forecast.
ProjectTypeId
The unique identifier of the project type.
ProjectTypeName
The name of the project type.
BusinessUnitId
The unique identifier of the business unit.
BusinessUnitName
The name of the business unit.
LegalEntityId
The unique identifier of the legal entity that's implementing the project.
LegalEntityName
The name of the legal entity that's implementing the project.
WorkTypeId
The unique identifier of the work type that's associated with task for which the budget or forecast is
created.
WorkTypeName The name of the work type that's associated with the task for which the budget or forecast is created.
ProjectCurrencyCode
The currency code used by default with amounts in the project.
ProjectLedgerCurrencyCode
The currency code used by default with amounts in the project ledger.
SponsoredFlag
Indicates whether the project is sponsored or not.
ProjectClassification
The classification of the project. The node comprises of ProjectClassCategory, ProjectClassCode, and
ClassCodePercentage attributes that help in classifying a project.
ProjectDff
Custom project-related flexfields created for use in your organization.
ProjectTeamMember --> projectPartyId
The unique identifier of a party assignment to the project for a project team member associated with
the budget or forecast version.
27
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
ProjectTeamMember -->
TeamMemberRoleId
The unique identifier of the role that's assigned to a project team member associated with the budget
or forecast version.
ProjectTeamMember -->
TeamMemberRoleName
The name of the role that's assigned to a project team member associated with the budget or forecast
version.
ProjectTeamMember -->
TeamMemberPersonId
The unique identifier of a project team member associated with the budget or forecast version.
ProjectTeamMember -->
TeamMemberEmailAddress
The email address of a project team member associated with the budget or forecast version.
ProjectTeamMember -->
TeamMemberUserName
The name of a project team member associated with the budget or forecast version.
ProjectTeamMember --> startDateActive
The start date of a project team member associated with the budget or forecast version.
ProjectTeamMember --> endDateActive
The end date of a project team member associated with the budget or forecast version.
Budget Attributes
Attribute Description
VersionName
The name of the budget version.
VersionNumber
The number of the budget version.
InternalVersionId
The unique identifier of the budget version.
ProjectName
The name of the project that's associated with the budget version.
ProjectNumber
The number of the project that's associated with the budget version.
InternalProjectId
The unique identifier of the project that's associated with the budget version.
FinancialPlanType
The name of the financial plan type that's associated with the budget version.
Status
The status of the budget version.
28
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
PlanningAmounts
The presence of cost amounts, revenue amounts, or both in a budget version.
BaselinedBy
The name of the person who set the budget version to baseline.
BaselinedDate
The date when the budget version is set to baseline.
ProjectCurrency
The currency in which the project that's associated with the budget is implemented.
TotalRevenue
The total revenue amounts taken into account the planning amounts from the previous budget version
plus any adjusted amounts.
TotalRawCost
The total raw cost amounts taken into account the planning amounts from the previous budget version
plus any adjusted amounts.
TotalBurdenedCost
The total burdened cost amounts taken into account the planning amounts from the previous budget
version plus any adjusted amounts.
Margin
The difference between the budgeted cost and revenue amounts.
MarginPercentage
The difference between the budgeted cost and revenue amounts, expressed as a percentage.
TotalEffortAtCompletion
The projected amount of work, in hours, for labor and equipment resource classes from the budget
version.
EquipmentEffortAtCompletion
The projected amount of work, in hours, for equipment resource class from the budget version.
PeopleEffortAtCompletion
The projected amount of work, in hours, for labor resource class from the budget version.
PlanningOptionDff
Custom budget planning options related flexfields created for use in your organization.
projectBudgetCurrentBaselinedVersions --
> ProjectId
The unique identifier of the project that's associated with the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> PlanVersionId
The unique identifier of the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> PlanTypeId
The unique identifier of the financial plan type that's associated with the current baseline budget
version.
projectBudgetCurrentBaselinedVersions --
> PlanningOptionId
The unique identifier of the financial planning options setup that's associated with the current baseline
budget version.
projectBudgetCurrentBaselinedVersions --
> ProjectNumber
The project number of the project that's associated with the current baseline budget version.
29
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
projectBudgetCurrentBaselinedVersions --
> ProjectName
The name of the project that's associated with the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> PlanVersionNumber
The version number of the project that's associated with the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> PlanVersionName
The name of the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> PlanTypeName
The name of the financial plan type that's associated with the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> BaselinedDate
The date when the current baseline budget version was set to baseline.
projectBudgetCurrentBaselinedVersions --
> PeopleQuantity
The amount of work, in hours, for labor resource class from the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> EquipmentQuantity
The amount of work, in hours, for equipment resource class from the current baseline budget version.
projectBudgetCurrentBaselinedVersions --
> TotalPcBrdndCost
The total of burdened cost amounts of the current baseline budget in project currency.
projectBudgetCurrentBaselinedVersions --
> TotalPcRawCost
The total of raw cost amounts of the current baseline budget in project currency.
projectBudgetCurrentBaselinedVersions --
> TotalPcRevenue
The total of revenue amounts of the current baseline budget in project currency.
projectBudgetCurrentBaselinedVersions --
> TotalPfcBrdndCost
The total of burdened cost amounts of the current baseline budget in project ledger currency.
projectBudgetCurrentBaselinedVersions --
> TotalPfcRawCost
The total of raw cost amounts of the current baseline budget in project ledger currency.
projectBudgetCurrentBaselinedVersions --
> TotalPfcRevenue
The total of revenue amounts of the current baseline budget in project ledger currency.
projectBudgetCurrentBaselinedVersions --
> ApprovedCostPlanTypeFlag
Indicates if the current baseline budget is of approved cost plan type or not.
projectBudgetCurrentBaselinedVersions --
> ApprovedRevPlanTypeFlag
Indicates if the current baseline budget is of approved revenue plan type or not.
projectBudgetCurrentBaselinedVersions --
> BudgetSourceReference
The reference of the source that's used for creating the current baseline budget version.
30
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attribute Description
Forecast Attributes
Attributes Description
InternalVersionId
The unique identifier of the forecast version.
VersionName
The name of the forecast version.
VersionNumber
The number of the forecast version.
ProjectName
The name of the project that's associated with the forecast version.
ProjectNumber
The number of the project that's associated with the forecast version.
InternalProjectId
The unique identifier of the project that's associated with the forecast version.
Status
The status of the forecast version.
PlanningAmounts
The presence of cost amounts, revenue amounts, or both in a forecast version.
ProjectCurrency
The currency in which the project that's associated with the forecast is implemented.
FinancialPlanType
The name of the financial plan type that's associated with the forecast version.
EtcStartDate
The date when the estimate-to-complete is intended to begin.
EACBurdenedCost
The estimated burdened cost amount at the completion of the project.
EACRawCost
The estimated raw cost amount at the completion of the project.
EACRevenue
The estimated revenue amount that will be recognized at the completion of the project.
Margin
The difference between the estimate-at-completion cost and revenue amounts.
MarginPercentage
The difference between estimate-at-completion cost and revenue amounts, expressed as a
percentage.
EACPeopleEffortAtCompletion
The projected amount of work, in hours, for labor resource class from the forecast version.
EACEquipmentEffortAtCompletion
The projected amount of work, in hours, for equipment resource class from the forecast version.
31
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attributes Description
EACTotalEffortAtCompletion
The projected amount of work, in hours, for labor and equipment resource classes from the forecast
version.
ETCBurdenedCost
The estimated burdened cost amount to complete the project.
ETCRawCost
The estimated raw cost amount to complete the project.
ETCRevenue
The estimated revenue amount to be recognized to complete the project.
ActualBurdenedCost
The actual burdened cost amount incurred on the project.
ActualRawCost
The actual raw cost amount incurred on the project.
PhysicalPercentComplete
The amount of physical work achieved, expressed as percentage.
TotalCommitments
The total planned quantity or amounts of commitments required to complete a project.
PlanningOptionDff
Custom forecast planning options related flexfields created for use in your organization.
projectForecastCurrentApprovedVersions
--> ProjectId
The unique identifier of the project that's associated with the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanVersionId
The unique identifier of the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanTypeId
The unique identifier of the financial plan type that's associated with the current approved forecast
version.
projectForecastCurrentApprovedVersions
--> ProjectNumber
The number of the project that's associated with the current approved forecast version.
projectForecastCurrentApprovedVersions
--> ProjectName
The name of the project that's associated with the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanVersionNumber
The version number of the project that's associated with the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanVersionName
The name of the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanTypeName
The name of the financial plan type that's associated with the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PlanningOptionId
The unique identifier of the financial planning options setup that's associated to the current approved
forecast version.
32
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Attributes Description
projectForecastCurrentApprovedVersions
--> BaselinedDate
The date when the current approved forecast version was set to baseline.
projectForecastCurrentApprovedVersions
--> EtcStartDate
The date when the estimate-to-complete is intended to begin in the current approved forecast version.
projectForecastCurrentApprovedVersions
--> PeopleQuantity
The amount of work, in hours, for labor resource class from the current approved forecast version.
projectForecastCurrentApprovedVersions
--> EquipmentQuantity
The amount of work, in hours, for equipment resource class from the current approved forecast
version.
projectForecastCurrentApprovedVersions
--> TotalPcBrdndCost
The total of burdened cost amounts of the current approved forecast in project currency.
projectForecastCurrentApprovedVersions
--> TotalPcRawCost
The total of raw cost amounts of the current approved forecast in project currency.
projectForecastCurrentApprovedVersions
--> TotalPcRevenue
The total of revenue amounts of the current approved forecast in project currency.
projectForecastCurrentApprovedVersions
--> TotalPfcBrdndCost
The total of burdened cost amounts of the current approved forecast in project ledger currency.
projectForecastCurrentApprovedVersions
--> TotalPfcRawCost
The total of raw cost amounts of the current approved forecast in project ledger currency.
projectForecastCurrentApprovedVersions
--> TotalPfcRevenue
The total of revenue amounts of the current approved forecast in project ledger currency.
projectForecastCurrentApprovedVersions
--> PrimaryCostForecastFlag
Indicates if the current approved forecast is of approved cost plan type or not.
projectForecastCurrentApprovedVersions
--> PrimaryRevForecastFlag
Indicates if the current approved forecast is of approved revenue plan type or not.
projectForecastCurrentApprovedVersions
--> ForecastSourceReference
The reference of the source that's used for creating the current approved forecast.
Financial Plan Version Approval Workflow Notifications
The Financial Plan Version Approval workflow sends notifications when:
A budget or forecast version requires approval.
A budget or forecast version is approved or rejected.
33
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
A budget or forecast version requires more information.
Note: For guidance on how you can work with workflow notifications in BPM Worklist, see Workflow Notifications in
the Common Implementing Applications guide.
Contents of a Financial Plan Version Approval Workflow Notification
A Financial Plan Version Approval Workflow notification contains the following details:
Note: Below are the details of a budget notification.
Header
Budget Version
Created On
Created By
Version Number
Version Description
Financial Plan Type
Summary Section
Project
Labor Effort (Hours)
Equipment Effort (Hours)
Burdened Cost in Project Currency
Raw Cost in Project Currency
Burdened Cost in Project Ledger Currency
Raw Cost in Project Ledger Currency
Approval History: One row per approver
Approvers
- Assigned to / Approved by / Rejected by <Name of Approver>
- Date and Time of Assignment / Approval / Rejection
Submitter
- Submitted by <Name of Submitter>
- Date and Time of Submission
Link to budget version
Approval options (if sent to an approver)
Approve
Reject
Request Info
Customizing Notification Templates
34
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
You can find the templates and data models used in the Financial Plan Version Approval workflow in the Shared Folders
> Projects > Workflow Notifications > Project Control folder in the Oracle BI Publisher catalog. In this folder, the
FinancialPlanVersionApprovalTemplate file contains the template used in the notification report. Expand the Project
Control > Data Model folder to access the FinancialPlanVersionApprovalDM file, which contains the data model used
in the notification report.
Note: For information on how you can customize notification templates, see Configure Workflow Approvals and
Notifications in the Implementing Applications guide.
Use Cases
Automatically Approve the Budget Version for Baseline in All Cases
To set up autoapproval for project budgets:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
7. Add the AutoApproval rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter AutoApproval in the Name field, add the description, verify that the
Active check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To specify that the rule is
applicable only for budget
versions.
35
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
To meet similar requirements
for forecasts, enter
"FORECAST".
d. In the THEN part of the rule, click the Advanced Add or Modify Options drop-down list and select the
Supervisory list builder by clicking Add Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
- Starting Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Top Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Auto Action Enabled: True
- Auto Action: “APPROVE” (Type this value including the quotation marks. Don't copy and paste this
value.)
- Rule Name: “AutoApproval”
Note: The rule name is auto-populated, its the name that you entered in Step 7.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
8. Click Validate on the top right corner to validate the newly defined rules.
9. Click the Save icon in the Tasks to be configured pane to save the rules.
10. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
11. Click OK to close the confirmation message window.
Simple Approval Rule Using Resource and Supervisory List Builders
Suppose that you want to approve the budget version for baseline based on the budget amount. Let's say, if the budget
burdened cost is less than or equal to $1000, then it should be auto-approved. Else, it should go to the project manager
for approvals. In such case, edit the predefined rule set to define two approval rules as follows:
Autoapproval rule for budget cost less than or equal to $1000 using the Supervisory list builder.
Project manager approval for budget cost greater than $1000 using the Resource list builder.
Follow these steps:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
36
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
7. Add the AutoApproval rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter AutoApproval in the Name field, add the description, verify that the
Active check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To meet similar requirements
for forecasts, enter
"FORECAST".
To specify that the rule is
applicable only for budget
versions.
ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost
isn't
null
To check if the burdened cost
amounts are available.
new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost)
same or less than
1000.00
To check if the burdened cost
is within the threshold limit.
d. In the THEN part of the rule, click the Advanced Add or Modify Options drop-down list and select the
Supervisory list builder by clicking Add Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
- Starting Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Top Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Auto Action Enabled: True
37
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
- Auto Action: “APPROVE” (Type this value including the quotation marks. Don't copy and paste this
value.)
- Rule Name: “AutoApproval”
Note: The rule name is auto-populated, its the name that you entered in Step 7.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
8. Add the Project manager approval rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options drop-down list and select General Rule.
b. Click the Properties link, enter ProjectManagerApproval in the Name field, add the description, verify
that the Active check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To meet similar requirements
for forecasts, enter
"FORECAST".
To specify that the rule is
applicable only for budget
versions.
ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost
isn't
null
To check if the burdened cost
amounts are available.
new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost)
more than
1000.00
To check if the burdened cost
is within the threshold limit.
38
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
d. In the THEN part of the rule, click the Advanced Add or Modify Options drop-down list and select the
the Resource list builder by clicking Add Approver > Resource. Then, enter the values as follows: :
- Response Type: Required
- Users: ApprovePlanVersionPayloadType.approvePlanPayload.approverName
- Groups: null
- Application Role:null
- Rule Name: “ProjectManagerApproval”
Note: The rule name is auto-populated, its the name that you entered in Step 8.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
9. Click Validate on the top right corner to validate the newly defined rules.
10. Click the Save icon in the Tasks to be configured pane to save the rules.
11. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
12. Click OK to close the confirmation message window.
Multilevel Approval Rule Using Supervisory List Builder
Suppose that you want to approve the budget version for baseline based on the budget cost. The higher the budget
cost, the more levels of approval needed for the budget. Let's say, if the budget cost is same or less than $5000, then
it should be approved only by the project manager. If the budget cost is between $5000 and $20000, then it should go
till the second level of approval to the manager of the project manager. If the budget cost is higher than $20000, then it
should go till the third level of approval to the manager of the manager of the project manager.
Budget Cost Greater Than Budget Cost Same or Less Than Levels of Approvals Required
0
5000
1
5000
20000
2
20000
No upper limit
3
In such case, edit the predefined rule set to route the budget version to a hierarchy using the Supervisory list builder
based on the budget cost.
First level approval rule to route approval to project manager for budget cost that’s same or less than $5000.
Second level approval rule to route approval to the project manager and the manager of project manager for
budget cost that’s between $5000 and $20000.
Third level approval rule to route approval till the manager of the manager of the project manager for budget
cost that’s greater than $20000.
You must also find out the highest position in the job hierarchy so that you can implement this approval for any number
of levels till the highest position in your hierarchy. In this example, we’ll consider the highest position in the hierarchy to
be CEO. See the implementation steps to define jobs in Oracle Fusion Cloud HCM documentation.
Pre-requisite: Define jobs in Oracle Fusion Cloud HCM.
39
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Follow these steps:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
7. Add the first level rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter FirstLevel in the Name field, add the description, verify that the Active
check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To meet similar requirements
for forecasts, enter
"FORECAST".
To specify that the rule is
applicable only for budget
versions.
ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost
isn't
null
To check if the burdened cost
amounts are available.
new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost)
same or less than
5000.00
To check if the burdened cost
is within the threshold limit.
40
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
d. In the THEN part of the rule, click the Advanced Add or Modify Options drop-down list and select the
Supervisory list builder by clicking Add Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
- Starting Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Top Participant: HierarchyBuilder.getPrincipal("john.doe",-1,"","")
Note: john.doe is the username of the CEO.
- Auto Action Enabled: False
- Auto Action: null
- Rule Name: “FirstLevel”
Note: The rule name is auto-populated, its the name that you entered in Step 7.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
8. Repeat Step 7 and make the following changes for the second and third levels of approval:
Enter the rule names as SecondLevel and ThirdLevel.
Enter the value in the IF condition as follows:
- Second level: new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost)
between 5000.00 and 20000.00
- Third level: new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost)
more than 20000.00
Enter the value in the THEN condition as follows:
- 2 for second level and 3 for third level in the Number of levels field.
9. Click Validate on the top right corner to validate the newly defined rules.
10. Click the Save icon in the Tasks to be configured pane to save the rules.
11. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
12. Click OK to close the confirmation message window.
Skip a Level Using Supervisory List Builder and Rule Priority
Suppose that you want to approve the budget version for baseline by following alternate level approvals. Let’s say we
have the following hierarchy defined in Oracle Fusion Cloud HCM.
Person Position Manager Approval Required
David
Project Manager
Henry
Yes
Henry
Senior Manager
Nick
No
Nick
Group Manager
Abraham
Yes
41
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
The budget version must first be approved by David. After David approves, the workflow should then skip Henry and
route the budget version approval to Nick. After Nick approves, the workflow should move into the approved state.
In such case, edit the predefined rule set to define an additional rule that uses rule priority and a try-catch action.
Follow these steps:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the rule priority to ensure that the workflow notification is sent to the project manager and only after
this approver approves, notifications are sent to the next approver.
a. Select the SoaOLabel.FinancialPlanApprovalRule.BudgetorForecastApprovalRule predefined rule.
b. Click the Properties link.
c. Select Highest from the Priority drop-down list, select the Advanced Mode check box, verify that the
Active check box is selected, and click OK.
7. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
8. Add the skip level rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter SkipLevel in the Name field, add the description, select Medium from the
Priority drop-down list, verify that the Active check box is selected, select the Advanced Mode check
box, and click OK.
c. Click the Insert Pattern link.
d. In the IF part of the rule, add the Task is a Task pattern by entering Task in both the text boxes. Then, click
the Advanced Add or Modify Options drop-down list and select simple test, and add the IF condition,
as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
Task.payload.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To specify that the rule is
applicable only for budget
versions.
42
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
Task.payload.planClassCode in
the Condition Browser dialog
box.
To meet similar requirements
for forecasts, enter
"FORECAST".
e. In the THEN part of the rule, click the Insert Action drop-down list and select try. Then, perform these
actions in the following order:
Where to Perform the
Action
Action to Perform Result
Under the try action
Click the Insert Action drop-down list and select catch.
The catch action is added.
Under the catch action
Click the Insert Action drop-down list and select Add Approver >
Supervisory.
The Supervisory list builder is
added.
Under the catch action
Select the check box against catch and click the Move down icon.
The Supervisory list builder
moves directly under the try
action.
Under the try action
Enter the values as follows:
-
Response Type: Required
-
Number of levels: 1
-
Starting Participant:
HierarchyBuilder.getManager("supervisory",HierarchyBuilder.getManager("supervisory",Task.payload.approvePlanPayload.approverName,-1,"","LINE_MANAGER").getId(),-1,"","LINE_MANAGER")
-
Top Participant:
HierarchyBuilder.getManager("supervisory",HierarchyBuilder.getManager("supervisory",Task.payload.approvePlanPayload.approverName,-1,"","LINE_MANAGER").getId(),-1,"","LINE_MANAGER")
Note: Replace “LINE_MANAGER” with the hierarchy type that
you define in Oracle HCM Cloud.
-
Auto Action Enabled: False
-
Auto Action: null
-
Rule Name: “SkipLevel”
Note: The rule name is autopopulated, its the name that you
entered in Step 8.
-
Dimension Id: null
Note: The dimension id is autopopulated as null.
NA
43
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Where to Perform the
Action
Action to Perform Result
In the catch action
Select the check box against catch and click the Delete Action
icon.
Note: Before you perform this action, ensure that only the
check box against catch is selected.
The catch action is deleted.
In the try action
Select the check box against try and click the Insert Action drop-
down list and select catch.
The catch action is added.
In the catch action
Enter Object as the target and e as the identifier value in the text
boxes.
NA
Under the catch action
Click the Insert Action drop-down list and select return.
NA
Note: If the try and catch actions are indented at the same level, it indicates that the rule is configured
correctly.
9. Click Validate on the top right corner to validate the newly defined rules.
10. Click the Save icon in the Tasks to be configured pane to save the rules.
11. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
12. Click OK to close the confirmation message window.
Multiple Approval Rules Based on Project Roles
Suppose that you want to define multiple approval rules based on project roles, as follows:
If the submitter has the project manager role on the project, then the budget version must be auto-approved.
If the submitter has the project administrator role (not project manger role) on the project, then the budget
version must be routed to the project manager for approval.
In such case, edit the predefined rule set to define a couple of additional rules that use advanced mode with pattern
matching.
Follow these steps:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
44
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
7. Add the approval rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter ProjectRoleBasedApproval in the Name field and add the description.
c. Select Medium from the Priority drop-down list, select the Advanced Mode check box, verify that the
Active check box is selected, and click OK.
d. In the IF part of the rule:
i. Click Insert Pattern, then enter Lists in the left box and select Lists from the drop-down list.
ii. Click the Add Pattern icon, then enter Task1 in the left box and select Task from the drop-down
list.
iii. Click the Add Pattern icon and select Surround from the Surround selected tests with
parenthesis drop-down list that's adjacent to the Add Pattern icon you just clicked.
iv. Select None from the drop-down list below and.
v. Enter ProjectTeamMember1 in the left box and choose ProjectTeamMember from the drop-down
list in the pattern.
vi. Click the Advanced Add or Modify Options drop-down list and select simple test, and add the IF
conditions within the same pattern as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF
Condition
Task1.payload.approvePlanPayload.requestorName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
Task1.payload.approvePlanPayload.requestorName
in the Condition Browser
dialog box.
is
ProjectTeamMember1.teamMemberUserName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ProjectTeamMember1.teamMemberUserName
in the Condition Browser
dialog box.
To specify that the requester
is a project team member.
ProjectTeamMember1.teamMemberRoleName
is
"Project Manager"
To check whether the
requester plays the Project
Manager role in the project.
e. In the THEN part of the rule, add a list builder of resource type by clicking Insert Action > Add Approver
> Resource. Then, enter the values as follows:
- Response Type: Required
- Users: Task1.payload.approvePlanPayload.approverName
- Groups: null
45
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
- Application Role: null
- Rule Name: “ProjectRoleBasedApproval”
Note: The rule name is auto-populated, its the name that you entered in Step 7.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
8. Add the auto-approval rule for project manager role, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options drop-down list and select General Rule.
b. Click the Properties link, enter AutoApproveForProjectManagerRole in the Name field, and add the
description.
c. Select Medium from the Priority drop-down list, select the Advanced Mode check box, verify that the
Active check box is selected, and click OK.
d. In the IF part of the rule:
i. Click Insert Pattern, then enter Lists in the left box, and select Lists from the drop-down list.
ii. Click the Add Pattern icon, then enter Task1 in the left box, and select Task from the drop-down
list.
iii. Click the Add Pattern icon and select Surround from the Surround selected tests with
parenthesis drop-down list that's adjacent to the Add Pattern icon you just clicked.
iv. Select None from the drop-down list below and.
v. Type ProjectTeamMember1 in the left box and choose ProjectTeamMember from the drop-down
list in the pattern.
vi. Click the Advanced Add or Modify Options drop-down list and select simple test, and add the IF
conditions within the same pattern as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF
Condition
Task1.payload.approvePlanPayload.requestorName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
Task1.payload.approvePlanPayload.requestorName
in the Condition Browser
dialog box.
is
ProjectTeamMember1.teamMemberUserName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ProjectTeamMember1.teamMemberUserName
in the Condition Browser
dialog box.
To specify that the requester
is a project team member.
ProjectTeamMember1.teamMemberRoleName
is
"Project Manager"
To check whether the
requester plays the Project
Manager role in the project.
e. In the THEN part of the rule, add a list builder of supervisory type by clicking Insert Action > Add
Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
46
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
- Starting Participant:
HierarchyBuilder.getPrincipal(Task1.payload.approvePlanPayload.approverName,-1,"","")
- Top Participant:
HierarchyBuilder.getPrincipal(Task1.payload.approvePlanPayload.approverName,-1,"","")
- Auto Action Enabled: True
- Auto Action: "APPROVE" (Type this value including the quotation marks. Don't copy and paste this
value.)
- Rule Name: “AutoApproveForProjectManagerRole”
Note: The rule name is auto-populated, its the name that you entered in Step 8.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
9. Click Validate on the top right corner to validate the newly defined rules.
10. Click the Save icon in the Tasks to be configured pane to save the rules.
11. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
12. Click OK to close the confirmation message window.
Approval Rule Comparing the Strategic Budget from EPM
Suppose that you want to approve the budget version for baseline based on the comparison with the strategic budget.
Let's say, if the detailed project budget created has a difference of amount that’s less than or equal to 5000 USD than
that of the strategic budget, then it’s approved by the project manager. If the detailed project budget created has a
difference of amount that’s greater than 5000 USD than that of the strategic budget, then it’s auto-rejected.
Follow these steps:
1. In the Setup and Maintenance work area, go to the Manage Task Configurations for Project Financial
Management task.
The BPM Worklist application is displayed.
2. In the Tasks to be configured pane, search for the ApprovePlanVersion task, and click the
ApprovePlanVersion link.
3. Click the Edit icon in the Tasks to be configured pane to modify the workflow.
4. Click the Assignees tab.
The participants who must approve project budgets or forecasts are displayed. Click on each of these
participants to review the workflow rules that apply to their approval choices.
5. Click the Approver participant in the workflow, click the Go to Rule (the diamond shaped) icon within the
Approver box, and then click the Go to Rule option that appears.
The list of rules associated with the Approver participant are displayed. Ensure that the
BudgetForecastAMXRuleSet rule is selected in the drop-down list.
6. Change the IF condition of the predefined rules from 1 is 1 to 1 is 2 to disable the predefined workflow from
sending project budget or forecast approvals to the project manager for approval.
7. Add the auto-approval rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options (the + icon) drop-down list and select
General Rule.
b. Click the Properties link, enter AutoApprovalLessThanStrategicBudgetBy5000 in the Name field and
add the description, verify that the Active check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions within the same pattern as follows:
47
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.approvePlanPayload.planTypeName
is
“Detailed Budget”
Replace this with the
appropriate FPT name that's
used for the detailed budget.
NA
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
-
To meet similar
requirements for
forecasts, enter
"FORECAST".
To specify that the rule is
applicable only for budget
versions.
new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost).subtract(ProjectBudgetCurrentBaselinedVersions.totalPcBrdndCost)
Same or less than
5000.00
NA
ProjectBudgetCurrentBaselinedVersions.planTypeName
is
"Strategic Budget"
Replace this with the
appropriate FPT name that's
used in EPM.
NA
ProjectBudgetCurrentBaselinedVersions.planTypeName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ProjectBudgetCurrentBaselinedVersions.planTypeName
in the Condition Browser
dialog box.
isn't
null
NA
48
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
d. In the THEN part of the rule, add a list builder of supervisory type by clicking Insert Action > Add
Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
- Starting Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Top Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Auto Action Enabled: True
- Auto Action: “APPROVE” (Type this value including the quotation marks. Don't copy and paste this
value.)
- Rule Name: “AutoApprovalLessThanStrategicBudgetBy5000"
Note: The rule name is auto-populated, its the name that you entered in Step 7.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
8. Add the auto-reject rule, as follows:
a. In the Rules pane, click the Advanced Add or Modify Options drop-down list and select General Rule.
b. Click the Properties link, enter AutoRejectMoreThanStrategicBudgetBy5000 in the Name field, add
the description, verify that the Active check box is selected, and click OK.
c. In the IF part of the rule, click the Advanced Add or Modify Options drop-down list and select simple
test, and add the IF conditions within the same pattern as follows:
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ApprovePlanVersionPayloadType.planClassCode
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ApprovePlanVersionPayloadType.planClassCode
in the Condition Browser
dialog box.
is
"BUDGET"
This value is case-sensitive.
Include the quotation marks.
Don't copy and paste this
value.
To meet similar requirements
for forecasts, enter
"FORECAST".
To specify that the rule is
applicable only for budget
versions.
ProjectBudgetCurrentBaselinedVersions.planTypeName
Note that you can also
select this value by
clicking the Left Value
search icon and selecting
ProjectBudgetCurrentBaselinedVersions.planTypeName
in the Condition Browser
dialog box.
isn't
null
NA
49
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Value to Enter in the Left
Text Box
Value to Select in the
Number Comparison Drop-
down List
Value to Enter in the Right
Text Box
Why to Add the IF Condition
ProjectBudgetCurrentBaselinedVersions.planTypeName
is
"Strategic Budget"
Replace this with the
appropriate FPT name that's
used in EPM.
NA
ApprovePlanVersionPayloadType.approvePlanPayload.planTypeName
is
“Detailed Budget”
Replace this with the
appropriate FPT name that's
used for the detailed budget.
NA
new
BigDecimal(ApprovePlanVersionPayloadType.approvePlanPayload.summaryAmounts.pcBurdenedCost).subtract(ProjectBudgetCurrentBaselinedVersions.totalPcBrdndCost)
more than
5000.00
NA
d. In the THEN part of the rule, add a list builder of supervisory type by clicking Insert Action > Add
Approver > Supervisory. Then, enter the values as follows:
- Response Type: Required
- Number of levels: 1
- Starting Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Top Participant:
HierarchyBuilder.getPrincipal(ApprovePlanVersionPayloadType.approvePlanPayload.approverName,-1,"","")
- Auto Action Enabled: True
- Auto Action: “APPROVE” (Type this value including the quotation marks. Don't copy and paste this
value.)
- Rule Name: “AutoRejectMoreThanStrategicBudgetBy5000"
Note: The rule name is auto-populated, its the name that you entered in Step 8.
- Dimension Id: null
Note: The dimension id is auto-populated as null.
9. Click Validate on the top right corner to validate the newly defined rules.
10. Click the Save icon in the Tasks to be configured pane to save the rules.
11. Click the Commit task icon in the Tasks to be configured pane to complete the rule configuration.
12. Click OK to close the confirmation message window.
50
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Oracle Fusion Cloud Project Management Profile Options
Project application administrators can use profile options to centrally manage UI settings and application behavior. You
can find the available profile options for your offering using the Manage Profile Options setup task from the Setup and
Maintenance work area.
You can use the Manage Administrator Profile Values setup task to view and update the values for the profile
options. Set profile options to configure certain features in the following Oracle Project Portfolio Management Cloud
applications:
Project Foundation
Project Billing
Project Costing
Project Control
Project Performance Reporting
Project Foundation Profile Options
The following table lists the name, description, and available values of the profile options that configure features in
Project Foundation, and the corresponding setup task name in Functional Setup Manager.
Profile Option Name Description Available Values Setup Task Name
Number of Days to Display People
with Terminated Assignments
Specify the number of days to
display an employee in assigned
projects after the employee
termination date.
0 (default)
Enter number of days
Specify Number of Days to
Display People with Terminated
Assignments
People with Future Effective Start
Dates as Project Members Allowed
Specify whether to assign people
with a future effective start dates
as project members.
Yes (default)
No
Allow People with Future Effective
Start Dates as Project Members
Task Managers Must Be Project
Team Members
Specify whether task managers
must be project team members.
No (default)
Yes
Require Task Managers to be
Project Team Members
Project Billing Profile Options
The following table lists the name, description, and available values of the profile option that configures a feature in
Project Billing, and the corresponding setup task name in Functional Setup Manager.
51
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Profile Option Name Description Available Values Setup Task Name
Unit of Measure for Invoice Lines
Sent to Receivables
Specify the unit of measure to
use when sending invoice lines to
Receivables.
Select a unit of measure defined in
Receivables
Specify Unit of Measure for Invoice
Lines Sent to Receivables
Credit Hold Prevents Revenue
Recognition
Specify whether customer credit
hold should prevent revenue
recognition.
No (default)
Yes
Manage Administrator Profile
Values
Net Credit Invoicing
Specify whether net credit
invoicing is enabled.
No (default)
Yes
Manage Administrator Profile
Values
Require Projects for Events Based
on Project Contract Lines
Specify whether project lines
on contracts require associated
projects and if related events
require the selection of a project.
Yes (default)
No
Manage Administrator Profile
Values
Number of Parallel Invoice
Generation Programs
Specify a value between 2 and 5
to create the number of instances
of the process that would run in
parallel to generate invoices more
quickly.
1 (default)
1 to 5
Manage Administrator Profile
Values
Allow Invoice Processing in any
SequenceDescription
Specify whether invoices can be
processed in any sequence.
Yes or No Manage Administrator Profile
Values
Project Costing Profile Options
The following table lists the name, description, and available values of the profile options that configure features in
Project Costing, and the corresponding setup task name in Functional Setup Manager.
Profile Option Name Description Available Values Setup Task Name
Account Updates Allowed on
Project-Related Distributions
Specify whether to update project-
related accounts when purchase
orders and invoice distributions
occur.
No (default)
Yes
Allow Account Updates on Project-
Related Distributions
Allocation Method for Zero-Basis
Amounts
Specify the allocations method if
the basis amount is zero.
Report as exception (default)
Spread evenly
Specify Allocation Method for
Zero-Basis Amounts
Default Expenditure Item Date for
Supplier Cost Transactions
Specify the expenditure item date
for the supplier cost transactions
that are matched to purchase
orders. This date is used on
purchase receipts, payments, and
discounts transferred to projects
and invoices.
Source document expenditure item
date (default)
Transaction accounting date
Transaction creation date
Transaction date
Specify Default Expenditure Item
Date for Supplier Cost Transactions
52
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Profile Option Name Description Available Values Setup Task Name
Number of Parallel Import Costs
Programs
Specify the maximum number,
between 1 and 10, of Import Costs
programs that are allowed to run at
the same time.
1 (default)
Enter a number between 1 and 10
Specify Number of Parallel Import
and Process Cost Programs
Work Type Derived for Expenditure
Item
Specify whether work types should
be derived for expenditure items.
No (default)
Yes
Derive Work Type for Project
Expenditure Items
Work Type Determines Billable
Status of Expenditure Item
Specify whether an expenditure
item is billable based on the
associated work type definition.
No (default)
Yes
Derive Billable Status of
Expenditure Items from Work Type
Burden Transactions Assigned with
Source Resources
Specify whether to assign both
burden costs and source raw costs
to the same resource class for
reporting purposes.
No (default)
Yes
Manage Project Types: Burdening
Options
Cost Transactions with 0 Quantity
Set as Nonbillable
Specify if cost transactions with 0
quantity are nonbillable.
No (default)
Yes
Allow Cost Transactions with Zero
Quantity as Nonbillable
Project Control Profile Options
The following table lists the name, description, and available values of the profile option that configures a feature in
Project Control, and the corresponding setup task name in Functional Setup Manager.
Profile Option Name Description Available Values Setup Task Name
PJO_GEN_ALLAMOUNTS
Specify whether amounts from
all periods should be considered
during financial plan creation.
Yes (default)
No
Amounts from all periods during
financial plan creation
Project Performance Reporting Profile Options
The following table lists the name, description, and available values of the profile options that configure features in
Project Performance Reporting, and the corresponding setup task name in Functional Setup Manager.
Profile Option Name Description Available Values Setup Task Name
Number of Parallel Summarization
Extraction Programs
Data summarization programs can
start helper programs to manage
the load on system resources.
Specify the maximum number of
helper programs that can exist at
one time.
3 (default)
Enter a number
Specify Number of Parallel
Summarization Extraction
Programs
53
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Profile Option Name Description Available Values Setup Task Name
Enable Project Performance Data
Process
Enable or disable Maintain Project
Performance Data process.
No (default)
Yes
NA
Display Format for Tasks in Smart
View
Specify the format in which tasks
appear in smart view.
Enable this profile option to
view task names, numbers, or a
combination of task number and
name in Oracle Smart View for
Office. You can then identify tasks
that have the same name distinctly
also by viewing the task number
along with the name.
Name (default)
Number
Number and Name
NA
Enable automatic pushing actual to
project plan after every online cost
summarization
Enable automatic updating of
actual in the project plan after
every online Update Project
Performance Data process for cost
processing.
No (default)
Yes
NA
Enable online summarization for
costing events
Enable automatic summarization
after every Import Costs process.
No (default)
Yes
NA
Enable automatic summarization
after every approved cost budget
baseline
Enable automatic summarization
after every approved cost budget
baseline event.
No (default)
Yes
NA
Enable online summarization for
revenue and invoice events
Enable automatic summarization
after every Generate Revenue
and Update Invoice Details from
Receivables process.
No (default)
Yes
NA
Display all Projects dashboards or
display project performance and
Project Management Dashboards.
Controls the listing of Project
Performance and Project Manager
Dashboards in the Navigator and
Home Page.
Yes (default)
No
NA
Number of projects summarized in
one batch by each parallel worker
Specify the number of projects
summarized in one batch by each
parallel worker.
50 (default)
NA
Threshold value for maximum
number of projects to enable batch
processing
Specify the threshold of the
number of projects after which all
projects in the helper processes will
be processed in a batch.
200 (default)
Specify Number of Parallel
Summarization Extraction
Programs
Related Topics
Hierarchy in Profile Levels
54
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Where to Find Information About Scheduled Processes
in Projects
Here are some scheduled processes that are available as part of Oracle Project Management Cloud.
Planning, Scheduling, and Forecasting
Maintain Project Organizations
See: Set Up Organizations
Change Project and Task Organizations
See: Options to Change Project and Task Organizations
Import Projects
See: Import Projects
Import Resource Breakdown Structures
See:Import Resource Breakdown Structures Process
Build New Organization Burden Multipliers
See: Burden Multipliers for New Organizations: How They Are Added to Burden Schedules
See:How Burden Schedule Components Work Together
Import Project Budgets
See: Import Project Budgets
Import Financial Project Plan
See:Import Financial Project Plans
Import Project Forecasts
See:Import Project Forecasts
Import Project Progress
See: Import Project Progress
Grant Management
Import Awards
See: Import Awards
55
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Cost Management and Control
Open Project Accounting Period
See: Options to Maintain Accounting Periods and Project Accounting Periods
Import Costs
See:Import Costs Process
Generate Burden Costs
See: How Burden Costs Are Calculated
Recalculate Burden Cost Amounts
See: Recalculate Burden Costs
Generate Capitalized Interest Transactions
See:Considerations for Managing Capitalized Interest
Identify Cross-Charge Transactions
See: Cross-Charge Options for Project Business Units
Import Unassigned Asset Lines
See: Import Unassigned Asset Lines
Release Allocation Transactions
See: Allocation Statuses
Reverse Allocation Transactions
See:When do I reverse an allocation?
Project Billing and Revenue
Import Project Billing Events
See: Import Project Billing Events
Performance Management
Generate KPI Values
See: How KPI Values Are Generated
Maintain Project Performance Data
See: Project Performance Data Summarization
Update Project Performance Data; Update Project Plan Data
See: Project Performance Data Summarization
56
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
Import Project Key Performance Indicators
See: Import Project Key Performance Indicators
Resource Management
Initiate Absence Records Transfer to Oracle Fusion Project Execution
See: Absence Management Integration
Project Enterprise Labor Resources
See: Project Enterprise Labor Resources Report
Import Project Enterprise Resources
See: Import Project Enterprise Resources
Import Project Resource Assignments
See: Import Project Resource Assignments Process
Import Project Resource Requests
See: Import Project Resource Requests Process
Import Resource Actual Hours
See: Import Resource Actual Hours
Import Resource Pools and Membership
See: Import Resource Pools and Memberships Process
Project Resource Search Index
See: Project Resource Search Index
Maintain Project Enterprise Labor Resources
Set up Conditions and Import HCM PersonSee:
57
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 1
Introduction
58
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
2 Implement Project Financial Management
Applications
Overview of Project Financial Management and Grants
Management Offerings
In the Project Financial Management and Grants Management business process areas, your enterprise can configure
how you manage projects, including how to plan, budget, or forecast, manage awards, collect costs, bill customers,
manage project templates and flexfields, and report performance.
Before you begin, use the Setup and Maintenance work area to access reports for each offering, including full lists of
setup tasks, the functional areas and features that you can select when you configure the offering, and business objects
and enterprise applications that are associated with the offering.
The first implementation step is to configure the offering in the Setup and Maintenance work area by selecting the
offering, functional areas, and features that you want to make available to implement.
This table describes the project-related functional areas for the Project Financial Management and Grants Management
offerings.
Functional Area Description
Project Organizations
Configure how you manage project units, project classifications, organization hierarchies, and business
unit options.
Project Foundation
Configure how you manage project organizations, create projects, plan project tasks, and review
project details. This common foundation is shared across the Project Financial Management
applications.
Burdening
Configure options used to calculate, group, and apply indirect costs to project expenditure items to
report and account for the total cost of a project.
Grants Management Foundation
Configure how you create and maintain awards, award funding, and award projects.
Project Control
Configure how you monitor project execution, progress, budgeting, and forecasting.
Project Billing
Configure how you invoice customers and recognize revenue for project contracts, including contract
management, intercompany billing, and the calculation of estimated taxes on invoices.
Project Costing
Configure how you collect, monitor and influence the costs associated with the delivery of the project
and management of capital assets.
Project Costing - Project Costing Base
Configure how you collect, monitor, and influence the costs associated with the delivery of the project.
59
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Functional Area Description
Project Costing - Capital Projects
Configure how you record asset costs, calculate capitalized interest, and create events to group costs
and assets.
Project Billing - Project Contracts
Configure the funding and billing relationships between the external parties who require the project
and the parties who deliver the project.
Project Billing - Project Billing Base
Configure how you invoice customers and recognize revenue for project contracts.
Project Billing - Internal Project Billing
Configure how you use internal invoices to share costs and revenue across projects and organizations.
Project Performance Reporting
Configure how you collect and review project performance data against defined performance areas.
Budgetary Control and Encumbrance
Accounting
This enterprise-level functional area option is typically used by public sector customers. Enable this
functional area if you plan to use budgetary control with or without encumbrance accounting in any
part of your organization.
Project Business Intelligence Analytics
Enable business intelligence reporting and analytics capabilities for project management data.
Project Revenue and Billing Business
Intelligence Analytics
Enable business intelligence reporting and analytics capabilities for project revenue and billing data.
Project Performance Business Intelligence
Analytics
Enable business intelligence reporting and analytics capabilities for project performance data.
Project Control and Costing Business
Intelligence Analytics
Enable business intelligence reporting and analytics capabilities for project control and costing data.
Project Accounting
Configure subledger accounting and set up subledger accounting rules for Project Financial
Management.
The following functional areas are also in the Project Financial Management and Grants Management offerings, but
aren't unique to these offerings:
Initial Users
Enterprise Profile
Legal Structures
Financial Reporting Structures
Organization Structures
Workforce Structures
Users and Security
Transaction Tax
Transactional Business Intelligence
60
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Optionally, create one or more implementation projects for the offerings, functional areas, and features that you want to
implement first, which generates task lists for each project. The application implementation manager can configure the
task list and assign and track each task.
This table lists the group of tasks that are available to you when you enable all functional areas and features.
Task List Description
Define Initial Users for Project Financial
Management
Populate the product tables with the users and roles held in LDAP and then create and provision job
and data roles for the initial users.
Verify Grants Management Offering
Implementation Status
Verify that the implementation status of the Grants Management offering is set to In Progress or
Implemented. The implementation status enables the grants functionality throughout Oracle Fusion
Project Portfolio Management applications.
Define Enterprise Profile for Project
Financial Management
Access your enterprise organization, such as legal entities, legal jurisdictions and authorities, and
business units, and specify their use in Project Financial Management applications.
Define Financial Reporting Structures for
Project Financial Management
Define the accounting configuration and chart of accounts that serve as a framework for how financial
records are maintained for an organization.
Define Organization Structures for Project
Financial Management
Configure business units for controlling transactions and workforce structures for managing the
enterprise.
Define Project Organizations
Manage the organizations that own, control, or contribute to projects, including the project units and
the project and business unit implementation options used by Project Financial Management.
Define Users and Security for Project
Financial Management
Define and assign security policies and data roles to enable users to perform functions related to their
job roles.
Define Project Foundation Configuration
Configure all foundation components for creating and maintaining projects in Oracle Fusion Project
Portfolio Management.
Define Project Control Configuration
Configure Oracle Fusion Project Control to monitor project execution, progress, budgeting, and
forecasting.
Define Project Costing Configuration
Configure Oracle Fusion Project Costing to collect, monitor, and influence the costs associated with the
delivery of the project.
Define Project Billing Configuration
Configure Oracle Fusion Project Billing to invoice customers and recognize revenue for project
contracts.
Define Project Performance Reporting
Configuration
Configure Oracle Fusion Project Performance Reporting to collect and review project data against
defined performance areas.
Manage Project Templates
Manage templates to quickly create projects that share common features, attributes, and options.
Define Budgetary Controls for Project
Financial Management
Configure the applicability of budgetary control on various business process flows, and set up the
business rules to enforce budgetary control.
61
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task List Description
Define Subledger Accounting Rules for
Project Financial Management
Configure subledger accounting and set up subledger accounting rules for Project Financial
Management.
Define Transactional Business Intelligence
Configuration
Define the configuration for Oracle Transactional Business Intelligence to enable business intelligence
reporting with the Oracle Fusion Applications.
Alternatively, you can use the rapid implementation feature to set up the Project Financial Management or Grants
Management offerings by populating and loading the Rapid Implementation for Project Financial Management
Applications macro-enabled Excel spreadsheet. This spreadsheet has a worksheet for key setup object or group
of setup objects. The setup includes key business objects and tasks such as, resources, burdening, and subledger
accounting. The Setup and Maintenance work area has a specific task list for rapid implementation. The Define
Project Financial Management Configuration for Rapid Implementation task list includes tasks to download a new
spreadsheet and to load the setup data. For more information on the rapid implementation feature, see the chapter
Rapid Implementation of Project Financial Management Applications in the Oracle Project Portfolio Management Cloud
Implementing Project Financial Management guide.
This table lists the Rapid Implementation tasks included in the Define Project Financial Management Configuration for
Rapid Implementation task list.
Task Description
Create Project Financial Management
Setup Data
Use this task to download the rapid implementation spreadsheet.
After downloading the rapid implementation spreadsheet you can start entering your setup data.
Load Project Financial Management Setup
Data
Use this task to load the setup data into the application.
After uploading the spreadsheet, the Project Financial Management or Grants Management application is fully
configured and ready for you to create project templates and to enter transactions. You can upload the spreadsheet
multiple times during the initial implementation until your setup is finalized.
Refer the following guides for more information:
Securing ERP
Implementing Common Features
Using Functional Setup Manager
62
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Related Topics
Organization Structures for Project Financial
Management
Overview of Organization Structures for Project Financial
Management
In the Define Organization Structures for Project Financial Management activity, you configure business units for
controlling transactions and workforce structures for managing the enterprise.
For business units, you perform setup steps such as creating and managing business units, generating data roles,
provisioning users with data roles, and assigning reference data to business units. For workforce structures, you
perform setup steps such as creating and managing organizations, assigning workers to organizations, creating and
managing hierarchies for the departments, and creating jobs.
This table lists the tasks and task lists that the setup tasks in the Define Organization Structures for Project Financial
Management activity are grouped into.
Task or Task List Description
Define Business Units for Project Financial
Management
Access your business units, and specify units and attributes relevant to Project Financial Management
applications. Create and maintain information on units of an enterprise to allow for flexible
implementation, to provide a consistent entity for controlling and reporting on transactions, and to be
an anchor for the sharing of sets of reference data across applications.
Manage Business Unit
Create and maintain information on units of an enterprise to allow for flexible implementation, to
provide a consistent entity for controlling and reporting on transactions, and to be an anchor for the
sharing of reference data sets across applications.
Verify Data Role Generation for Business
Unit
Generate data roles or verify the data roles if already generated.
Provision Roles to Implementation Users
for Business Unit
Provision implementation users with job or data roles, such as Application Implementation Consultant,
IT Security Manager, or Application Administrator for a product family.
Assign Business Unit Business Function
Assign business functions to be performed by a business unit, such as customer invoicing and order
capture.
Verify Data Role Generation for Business
Unit Business Function
Generate data roles or verify the data roles if already generated.
Provision Roles to Implementation Users
for Business Unit Business Function
Provision implementation users with job or data roles, such as Application Implementation Consultant,
IT Security Manager, or Application Administrator for a product family.
63
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task or Task List Description
Manage Business Unit Set Assignment
Assign reference data, which represents business rules and policies, to business units.
Define Workforce Structures for Project
Financial Management
Configure structures to represent the management and operating requirements of the enterprise.
Define the structures to support and represent workers using jobs, positions, and grades.
Manage Divisions
Create and manage the organizations that represent lines of business in the enterprise.
Manage Departments
Create and manage the organizations to which workers can be assigned.
Manage Department Trees
Create and manage hierarchies for departments to view the internal structures of the workforce.
Manage Job
Create and manage jobs.
Manage Organization Trees
Create and manage hierarchies of organizations to view the structures of the enterprise.
Create and Manage a Business Unit
A business unit is a unit of an enterprise that performs one or many business functions that can be rolled up in a
management hierarchy. A business unit can process transactions on behalf of many legal entities.
Verify that the implementation team set up the following in Oracle Human Capital Management:
Organizations
Organization hierarchies
Organization classifications
Creating a Business Unit
Follow these steps to create a business unit:
1. Click Navigator > Setup and Maintenance, and search for the Manage Business Unit task.
2. Click the Manage Business Unit link.
3. On the Manage Business Units page, click the Create icon.
4. In the Name field, enter the name for the business unit.
5. In the Default Set field, select a reference data set code.
Note: Click Create on the list to create a new reference data set.
6. Click Save and Close.
Assign Business Function to a Business Unit
Follow these steps to assign business functions to a business unit:
1. Click Navigator > Setup and Maintenance, and search for the Assign Business Unit Business Function task.
64
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
2. Click the Assign Business Unit Business Function link.
3. Enable the Billing and Revenue Management, Customer Contract Management, Expense Management,
Payables Invoicing, and Project Accounting business unit functions.
4. In the Select and Add: Business Unit page, search and select your business unit and click Save. The Assign
Business Functions page opens.
5. In the Financial Reporting section, enter primary ledger and default legal entity details.
6. Enable the Billing and Revenue Management, Customer Contract Management, Expense Management,
Payables Invoicing, and Project Accounting business unit functions.
7. Click Save and Close. The enabled business functions are now assigned to your business unit.
Managing Business Unit Data Access for Users
Follow these steps to manage business unit data access for users.
1. Click Navigator > Setup and Maintenance, and search for the Manage Business Unit Data Access for Users
task.
2. Click the Manage Business Unit Data Access for Users link.
3. Select the Users without Data Access option.
4. In the Search Results section, click the Create icon. Select user name , role, security context and security
context value.
5. Click Save and Close.
6. To search for Users with data access, select Users with Data Access option.
7. Select User name and role in the search region.
8. Click Search.
Note: To create a saved search click Save... In the Create Saved Search Window, type a name for your search.
You can also enable Set as Default to set the saved search as default and Run automatically to run the
search automatically later. You can get these values from Saved Search list later.
9. Click Save and Close.
10. Click Done.
Managing Business Unit Set Assignments
Follow these steps to manage business unit set assignments:
1. Click Navigator > Setup and Maintenance, and search for the Manage Business Unit Set Assignment task.
2. Click the Manage Business Unit Set Assignment link.
3. On the Manage Set Assignments page, change the assignment for each object as required.
Note: The default set of the business unit is assigned to each reference data object. You must perform
the Manage Business Unit Set Assignment task. Even if you don't change any of the sets assigned, the
assignment isn't complete until the record is saved.
4. Click Save and Close.
Related Topics
Classify Organizations to Own Projects and Tasks or Incur Costs on a Project
Options for Business Units to Work with Projects
Business Units
Reference Data Sets and Sharing Methods
Business Functions
65
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Create and Manage a Project Unit
To create a project unit, either enable an existing organization as a project unit or create a new organization as a project
unit in Oracle Human Capital Management.
After an organization is defined as a project unit, the project unit appears in searches on the Manage Project Units page.
Note: You must set up at least one project unit for your organization.
Creating Project Units
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Unit Organizations task.
2. Click the Manage Project Unit Organizations link.
3. On the Manage Project Unit Organizations page, click the Create icon.
4. Enable Create new and enter code and name for the project unit.
Note: You can select an existing organization to define as a project unit. Enable Select an existing
organization to define as a project unit and search for an existing organization. Select the organization and
enter a code.
5. Click Save and Close.
6. Click Done.
Manage Project Unit Options
Use the Manage Project Unit Options task to set up the general and reporting options for your project unit.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Unit Options task.
2. Click the Manage Project Unit Options link.
3. Click the project unit you want to edit.
4. On the Manage Project Units: General Properties page, in the Default Set section, select the default reference
data set that you want to use for the reference data objects within the project unit.
5. In the Project Numbering section, select the project numbering method and type.
6. Click Next.
7. On the Manage Project Units: Related Business Units page, associate the business units with the project unit.
Select the business units that are accountable for financial transactions of projects in each project unit.
8. Click Next.
9. On the Manage Project Units: Reporting Setup page, complete the reporting options as appropriate.
10. Click Save and Close.
11. Click Done.
Managing Project Unit Set Assignments
Determine how reference data is shared or partitioned across the different lines of business in your company.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Unit Set Assignments task.
2. Click the Manage Project Unit Set Assignments link.
66
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
3. On the Manage Project Unit: Set Assignments page, change the assignment for each object as required.
4. Click Save and Close.
5. Click Done.
Related Topics
Manage Project Unit Options
Project Unit Components
How can I associate a business unit with a project unit?
Create an Organization
A department is an organization to which you assign workers. It is an organization with one or more operational
objectives or responsibilities that exist independently of its manager. You track the department's financial performance
through one or more cost centers.
Examples of departments can be Sales, Human Resources, and Research and Development. You can report and keep
track of headcount by creating a department hierarchy.
Creating a Department
1. Click Navigator > Setup and Maintenance, and search for the Manage Departments task.
2. Click the Manage Departments link.
3. On the Manage Departments page, click Create.
4. On the Create Department Description page, enable Create new and enter the department description details.
5. Click Next.
6. On the Create Department: Department Details page, enter the department details as applicable.
7. Click Submit.
8. Confirm whether you want to submit the request. The application generates a request ID when you confirm.
9. Click Done.
Related Topics
Set Up Organizations
Department Classifications
Classify Organizations to Own Projects and Tasks or Incur Costs on
a Project
Specify organizations that can own projects and tasks, and incur project expenses. If an organizations can be a project
and task owning organization, then you also specify whether the organization allows indirect, capital, and contract
projects.
Classifying an Organization as Project Owning and Project Expenditure Organization
67
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Follow these steps to classify an organization as a project owning and project expenditure organization:
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Organization Classifications
task.
2. Click the Manage Project Organization Classifications link.
3. In the Search section, enter a name and effective date and click Search.
4. In the Search Results section, select an organization and click the Edit icon.
5. On the Edit Project Organization Classifications page, in the Change All Selected section, select the applicable
options.
6. Click Save and Close.
7. Click Done.
Selecting the Organization Hierarchy Type and Classifications
Select the organization hierarchy type that enables you to assign organization hierarchies, such as the project and task
owning organization hierarchy and project expenditure organization hierarchy, to project business units.
Follow these steps to selecting organization hierarchy type and classification:
1. Click Navigator > Setup and Maintenance, and search for the Manage Organization Hierarchies and
Classifications task.
2. Click the Manage Organization Hierarchies and Classifications link.
3. In the Organization Hierarchy Type list, select an organization hierarchy type, for example, HCM Organization
Hierarchy Tree Structure.
Note: A hierarchy must be set up in Oracle Human Capital Management for the selected hierarchy type.
4. In the Organization Classifications section, from the Available column, select Asset Organization, Business
Unit, Partner Organization, Project Expenditure Organization, Project Task Owning Organization, Project Unit
Classification.
Note: Generally the project expenditure organizations will also be departments.
5. Click the Move selected items to other list icon marked with a right arrow to move the items from the
Available column to the Selected column.
6. Click Save and Close.
Selecting Organization Hierarchies for the Business Unit
Associate project and task owning organizations to the business unit to restrict the project owning organizations in the
project creation flow.
The following conditions are required for an organization to be eligible to be a project and task owning organization:
You must assign the Project and Task Owning Organization classification to the organization.
The organization must belong to the hierarchy that you specify in the project implementation options for the
business unit.
The following conditions are required for an organization to be eligible to be a project expenditure organization:
You must assign the Project Expenditure Organization classification to the organization.
The organization must belong to the hierarchy that you specify in the project implementation options for the
business unit.
68
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Follow these steps to select organization hierarchies for a business unit:
1. Click Navigator > Setup and Maintenance, and search for the Configure Project Accounting Business
Function task.
2. Click the Configure Project Accounting Business Function link.
3. On the Configure Project Accounting Business Function page, in the Project Option section, enter the
mandatory information in the following tabs:
Project Setup
Expenditures
Costing
Project Units
Cross-Charge Options
4. Click Save and Close.
Associating Project Units with Business Units
Associate project units to business units to share a common approach to financial management across a set of project
units while maintaining independent setup data.
Follow these steps to associate a project unit with a business unit:
1. Click Navigator > Setup and Maintenance, and search for the Configure Project Accounting Business
Function task.
2. Click the Configure Project Accounting Business Function link.
3. On the Configure Project Accounting Business Function page, in the Project Options section, click the Project
Units tab and select the project units to associate with this business unit.
4. Click Save and Close.
Related Topics
Set Up Organizations
Project Foundation
Overview of Project Foundation Configuration
This table lists the setup task lists for Oracle Fusion Project Foundation.
Task or Task List Name Description
Define Project Calendars and Periods
Manage calendars, accounting period statuses, and project accounting period statuses used for
costing, budgeting, forecasting, billing, and project performance reporting.
Define Types and Categorizations
Manage various classifications used to describe and group projects, tasks, and transactions.
69
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task or Task List Name Description
Define Project Roles
Define project roles and the business rules that control how the roles are assigned.
Define Project Resources
Define job mapping, attributes, and rate schedules for project resources.
Define Rate Schedules and Costing Rules
Define rate schedules and costing rules used for costing, billing, work planning, and financial planning
purposes.
Define Project Resource Breakdown
Structures
Define resource breakdown structures used for project planning, billing, and reporting.
Define Burdening
Configure options used to calculate, group, and apply indirect costs to project expenditure items to
report and account the total cost of a project.
Manage Project Types
Create classifications for projects and configure basic options that are inherited by each project
associated with that project type.
Define Transfer Pricing
Define rules and schedules to determine the transfer price amount of cross-charge transactions that
require borrowed and lent or intercompany billing processing.
Define Action Controls
Define source products and configure action controls to determine which actions cannot be performed
in Oracle Fusion Projects on data imported from a particular third-party source.
Define System Administration and
Maintenance Options
Perform system administration functions including the definition of descriptive flexfields, distribution
of desktop integrator, and configuration of system options.
This chapter provides detailed setup steps for the following required tasks:
Manage Expenditure Types
Manage Nonlabor Resources
Manage Rate Schedules
Manage Planning and Billing Resource Breakdown Structures
Manage Project Types
Create Expenditure Types
Create expenditure types to classify the cost of each expenditure item.
Use expenditure types for processing requirements, such as calculating raw costs, to classify costs, and to plan, budget,
forecast, and report on projects.
The following sections describe how to create expenditure types.
70
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Note: After you save an expenditure type, you can't subsequently update the following attributes:
Expenditure and revenue categories
Unit of measure
Rate required option
Expenditure type class
If a change is required, you must enter a To Date to make the expenditure type unavailable and create another one.
Entering Basic Expenditure Type Information
To create an expenditure type:
1. Click Navigator > Setup and Maintenance, and search for the Manage Expenditure Types task.
2. Click the Manage Expenditure Types link.
Use the Manage Expenditure Types page to define expenditure types and to review or edit existing expenditure
types and the associated expenditure type classes, assigned sets, and tax classification codes.
3. Click the Add Row icon to create an expenditure type.
4. Enter a name in the Expenditure Type column. Optionally, enter a description.
5. The following table lists the decisions you need to take.
Option Name Decision
Expenditure Category
Determine the kind of costs, for example, labor or overhead, that you plan to capture using this
expenditure type.
Note:
Create expenditure categories using the Manage Expenditure Categories page before
creating expenditure types.
Revenue Category
Determine the source of revenue, for example, fees or other payments, you plan to capture
using this expenditure type.
Note:
Create revenue categories using the standard lookup PJF_REVENUE_CATEGORY before
creating expenditure types. You can update the lookup from the Manage Revenue Categories
page or the Manage Standard Lookups page.
Unit of Measure
Determine the default UOM for costing and planning transactions associated with this
expenditure type.
71
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision
Note:
Use Hours as the UOM for labor expenditure types.
Rate Required
Determine whether cost rates must be provided for expenditure items associated with this
expenditure type.
Proceeds of Sale
Determine whether cost rates must be provided for expenditure items associated with this
expenditure type. Indicate whether the expenditure type is used to track the proceeds of sale
for a capital project.
6. Select a date from which the expenditure type is available for use. Optionally, select a date to which the
expenditure type is available.
Selecting Expenditure Type Classes
Assign the expenditure type to one or more predefined expenditure type classes to determine how related expenditure
items are processed.
For example, an expenditure item with the expenditure type Materials can have the expenditure type class Supplier
Invoice if it originated in Oracle Fusion Payables or it can have the expenditure type class Inventory if it originated in
Oracle Fusion Inventory.
In other words, you can use the same expenditure type for expenditures with different origins that must be grouped for
costing, budgeting, or summarization purposes.
1. In the Expenditure Type Classes section, select an expenditure type class in the Name column.
2. Enter a date from which the expenditure type class is associated with the expenditure type. Optionally, specify a
date to which the expenditure type class is associated with the expenditure type.
3. Repeat the process for each expenditure type class that you want to associate with the expenditure type.
Assigning Sets
Use the Assigned Sets section to assign the expenditure type to one or more reference data sets so that only
expenditure types that are relevant to the project unit are available for the project.
To assign sets:
1. Click Add Row in the Assigned Sets section.
2. Select the Code of the desired set.
3. Repeat the process for each set to which the expenditure type is assigned.
For additional information about set assignments, see the Create Financial Plan Types section of this document.
72
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Selecting Tax Classification Codes
Optionally, select a default tax classification code to use for customer invoice lines for an expenditure type and business
unit. To select a tax classification code:
1. Click Add Row in the Tax Classification Codes section.
2. Select a business unit.
3. Select a tax classification code.
4. Repeat the process for each tax classification code and business unit combination you want to associate with
the expenditure type.
5. Click Save.
Create Nonlabor Resources
Create nonlabor resources to represent assets or pools of assets that project managers can use on projects.
As illustrated in the following figure, a nonlabor resource may be an equipment or resource with capacity that is
consumed, such as a training room, or equipment with physical output that is consumed, such as a copier.
To create a nonlabor resource:
1. Click Navigator > Setup and Maintenance, and search for the Manage Nonlabor Resources task.
2. Click the Manage Nonlabor Resources link.
Use the Manage Nonlabor Resources page to create, review, edit, or delete nonlabor resources.
3. Click the Add Row icon to create a nonlabor resource.
73
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
4. Enter a unique name, and optionally, a description for the nonlabor resource.
5. Select an Expenditure Type to determine the rates used to calculate cost and revenue for the nonlabor
resource.
Note: You can only select an expenditure type of Usage expenditure type class.
6. If you are creating a resource, such as a training room, whose capacity is consumed, then select the Equipment
Resource Class check box.
To indicate that the resource is equipment, the expenditure type you selected must use a UOM in Hours.
7. Enter a From Date to indicate the date from which the nonlabor resource is available for use. Optionally, specify
a To Date.
8. Specify the organizations to which a nonlabor resource is assigned. Click the Add Row icon in the Nonlabor
Resource Organizations section.
You can assign nonlabor resources to any organization from the organization hierarchy, regardless of whether
the organization has the Project Expenditure Organization classification, and regardless of the start and end
dates for the organization.
9. In the Name field, select an organization.
10. Enter a From Date to indicate the date from which the nonlabor resource is assigned to the organization.
Optionally, specify a To Date.
11. Repeat the process for each organization to which the nonlabor resource is assigned.
You can't assign a nonlabor resource to an organization multiple times, even for different date ranges.
12. Click Save.
Create Rate Schedules
Create rate schedules as a source for cost or bill rates for costing, billing, or planning purposes.
You can create schedules for the following types of rates:
Job
Person
Nonlabor
Resource class
The following sections describe how you create the different types of rate schedules.
Entering Basic Rate Schedule Information
To create a rate schedule:
1. Click Navigator > Setup and Maintenance, and search for the Manage Rate Schedules task.
2. Click the Manage Rate Schedules link.
Use the Manage Rate Schedules page to create, delete, and maintain rate schedules.
3. Click the Add Row icon to create a rate schedule.
4. Enter a unique name, and optionally, a description for the rate schedule.
5. Select a Project Rates Set.
74
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
6. Select a Schedule Type depending on whether you want to create a rate schedule for jobs, persons, nonlabor
resources, or resource classes.
7. Select the Currency in which you plan to enter rates.
Creating Nonlabor Rate Schedules
Define rates or percentage markups by nonlabor expenditure type or by a combination of nonlabor expenditure type,
nonlabor resource, and nonlabor resource organization.
The application uses the most detailed information available to determine the rate. For example, if a rate exists for the
expenditure type, nonlabor resource, and nonlabor resource organization combination, that rate is used. If that rate
does not exist, it uses the rate for the expenditure type and nonlabor resource combination. Otherwise, the rate for the
expenditure type is used.
Complete the following steps to create a nonlabor rate schedule:
1. Click Add Row in the Nonlabor Rates section.
2. Select the Expenditure Type for which you are entering rates.
3. Depending on the detail at which you want to enter rates, optionally select a Nonlabor Resource and a
Nonlabor Resource Organization.
4. Select the Rate Required check box if you want to enter a rate or a markup percentage for the expenditure
type. If you don't select this option, you must provide a markup percentage.
5. Enter either a Rate or a Markup Percentage that is used to calculate amounts for the resource.
6. Enter a From Date to indicate the date from which the rate is available for use. Optionally, select a To Date.
7. Repeat this process for each expenditure type or expenditure type, nonlabor resource, and nonlabor resource
organization for which you want to enter rates.
8. Click Save.
Creating Job Rate Schedules
Define rates for jobs included in a job set created in Oracle Fusion Human Capital Management.
Complete the following steps to create a job rate schedule:
1. In the Job Rates section, select a Job Set as a source for the jobs you are entering rates for.
2. Click Add Row.
3. Select the Job for which you are entering rates. Note that the Unit of Measure is always Hours.
4. Enter a rate for the job.
5. Enter a From Date to indicate the date from which the rate is available for use. Optionally, select a To Date.
6. Repeat this process for each job for which you want to enter rates.
7. Click Save.
Creating Person Rate Schedules
Define rates or percentage markups for person or for a combination of person, job, and organization.
The application uses the most detailed information available to determine the rate. For example, if there is a rate for
Person, Person Assignment Job, and Person Assignment Organization, that rate is used. Otherwise, the rate for the
person is used.
Complete the following steps to create a person rate schedule:
1. Click Add Row in the Person Rates section.
2. Select the person for whom you are entering rates. Note that the Unit of Measure is always Hours.
3. Depending on the detail at which you want to enter rates, optionally select a Person Assignment Job and a
Person Assignment Organization.
75
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Note: A default value is provided for the assignment organization when you select an assignment job. You
can select another organization if required.
4. Enter either a rate or a markup percentage.
5. Enter a From Date to indicate the date from which the rate is available for use. Optionally, select a To Date.
6. Repeat this process for each person or person, assignment, and organization combination for which you want
to enter rates.
7. Click Save.
Creating Resource Class Rate Schedules
Define rates or percentage markups by resource class or a combination of resource class and organization.
You can assign resource class rate schedules to project plan types or financial plan types. The selected resource class
rate schedule functions as a source of rates if the rates can't be determined elsewhere.
Complete the following steps to create a resource rate schedule:
1. Click Add Row in the Resource Class Rates section.
2. Select the resource class for which you are entering rates.
3. Depending on the detail at which you want to enter rates, optionally select an Organization.
4. Enter either a rate or a markup percentage.
5. Enter a From Date to indicate the date from which the rate is available for use. Optionally, select a To Date.
6. Repeat this process for each resource class, or resource class and organization combination for which you want
to enter rates.
7. Click Save.
Create Planning Resource Breakdown Structures
Create planning resource breakdown structures as a source for planning resources that are used for project planning,
budgeting, and forecasting.
A default planning resource breakdown structure with planning resources is created automatically for the Labor,
Equipment, Material Items, and Financial Resources resource classes for each project unit.
Note: When you create a project template, it's selected as the primary planning resource breakdown structure. You
can designate another planning resource breakdown structure as primary if required, but you can't remove the default
planning resource breakdown structure from the project or template.
Here's the three-step guided process for setting up planning resource breakdown structure.
1. Enter planning resource breakdown structure details.
2. Select resource formats.
3. Add planning resources.
Enter Planning Resource Breakdown Structure Details
To create a planning resource breakdown structure:
1. In the Setup and Maintenance work area, go to the Manage Planning and Billing Resource Breakdown
Structures task.
76
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
2. Use the Manage Planning and Billing Resource Breakdown Structures page to create planning resource
breakdown structures and to review existing planning and billing resource breakdown structures.
3. Click the Create icon in the Planning Resource Breakdown Structures section.
4. Use the Create Planning Resource Breakdown Structure: Basic Information page to provide the following details:
The name of the planning resource breakdown structure.
The date from which the planning resource breakdown structure is available for use.
Optionally, provide a description and a date to which the planning resource breakdown structure is
available for use.
The project unit. Only projects created for the selected project unit can use this planning resource
breakdown structure.
If you want to allow project managers to add planning resources at the project level, then select the Allow
resource changes at project level check box.
Tip: Changes at the project level don't move back to the parent planning resource breakdown
structure. Deselect this option to ensure that all projects using the planning resource breakdown
structure use the same resources.
As actual amounts are incurred for a project, if you want resources to be automatically added to the
primary planning resource breakdown structure when it allows changes at the project level, then select
the Automatically add resources on incurring actual amounts check box.
Tip: The Automatically add resources on incurring actual amounts option isn't applicable for
projects that are enabled for budgetary controls. Projects enabled for budgetary control need a
stringent control on resources incurring project costs.
Note: The resource is added to the planning resource breakdown structure as follows:
- If the resource format for the resource exists on the planning resource breakdown
structure, then the resource is directly added to the planning resource breakdown
structure.
- If the resource format for the resource doesn't exist on the planning resource
breakdown structure, then the application verifies if a higher level resource format
exists and then adds the resource directly to the planning resource breakdown
structure. If a higher level resource format doesn't exist, then the resource is
mapped to one of the generic resource classes.
Optionally, select a Job Set as a source of jobs for creating planning resources on your planning resource
breakdown structure.
5. Click Save.
Selecting Resource Formats
Resource formats are predefined resource types or hierarchies of resource types of up to three levels. The following
figure provides examples of resource format hierarchies up to three levels.
77
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
You create resources for planning or billing resource breakdown structures based on resource formats. For example, if
you want to plan for project-related expenses such as airfare, then you must select resource format hierarchies created
using the resource type Expenditure Type.
1. Click Next on the Create Planning Resource Breakdown Structure: Edit Details page to open the Create Planning
Resource Breakdown Structure: Select Resource Formats page.
Use the Create Planning Resource Breakdown Structure: Select Resource Formats page to select the resource
formats and resource format hierarchies to use for creating planning resources.
2. Click the Include check box for each resource format that you want to create planning resources for.
Tip: Click the Expand icon to expand the resource format hierarchy. You must select lower levels of a
hierarchy individually even if you have selected a format at a higher level.
3. Click Save.
Adding Planning Resources
Create planning resources based on the resource formats you selected for the planning resource breakdown structure.
1. Click Next on the Create Planning Resource Breakdown Structure: Select Resource Formats page to open the
Create Planning Resource Breakdown Structure: Add Planning Resources page.
Use the Create Planning Resource Breakdown Structure: Add Planning Resources page to create planning
resources based on the selected resource format hierarchies.
2. In the Resource Formats table, select a resource format for which you want to create planning resources.
Tip: Click the Expand icon to expand the resource format hierarchy if you want to create planning resources
at a more detailed level.
3. Click Add in the Planning Resources section.
4. Enter a name for the planning resource.
5. In the Resource Combination column, select values for each resource element that's part of the selected
resource format hierarchy. For example, if the selected resource format is Job: Supplier, then you must select
values for Job and Supplier.
78
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
6. Review the resource class and change if required.
Note: For each resource format, you can create planning resources based on certain resource classes. For
example, if the resource format contains Job, then the only available resource class is Labor. However, if the
resource format is Expenditure Category, then you can select any of the resource classes (Labor, Material
Items, Equipment, and Financial Resources) when you create a resource.
7. Review the spread curve and make changes if required.
Use predefined spread curves or create spread curves based on your requirements on the Manage Spread
Curves page. Spread curves determine how quantity, cost, and revenue amounts for planning resources are
distributed across periods in financial or project plans. The resource class associated with the planning resource
determines the default spread curve.
8. Repeat this step for each planning resource you want to create for each resource format.
9. Click Save.
Create Project Types
Create project types to control basic project configuration options for burdening, billing, capitalization, and project
categorization.
Project types are the primary classification for the projects your business manages. You must set up at least one project
type to create projects.
Note: After you create a project using a project type, you can't edit the project type.
The following sections describe how you create project types.
Entering Basic Project Type Information
To create a project type:
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Types task.
2. Click the Manage Project Types link.
Use the Manage Project Types page to view, create, and edit project types.
3. Click the Create icon to create a project type.
Use the Create Project Type page to specify basic project configuration options, such as burdening, billing, and
capitalization options, and class categories, that are inherited by each project associated with the project type.
4. Enter a project type name and select a date from which the project type is available for use. Optionally, select a
date to which the project type is available for use and enter a description.
5. Select the Set to which the project type is assigned.
Note: Project managers can use this project type only on project templates and projects created in business
units associated with the set you select here. For additional information about set assignments, see also the
Create Financial Plan Types section of this document.
79
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
6. Select a Work Type.
Create work types on the Manage Work Types page. Work types classify actual and scheduled work. Use work
types to determine whether expenditure items are billable, classify cross-charge amounts into cost and revenue
for cross-charge work, and calculate transfer price amounts.
7. To record burden costs on projects, select the Enable burdening check box.
8. To bill customers for project work, select the Enable billing check box.
9. To assign assets to projects, select the Enable capitalization check box.
Selecting Burdening Options
Control how burden transactions are created and accounted. If you enable burdening for a project type, you can choose
to account for the individual burden cost components or the total burdened cost amount.
1. Navigate to the Burdening Options tab.
2. Select the Default Cost Burden Schedule for projects that are defined with this project type. Project managers
can change this value at the project or task level.
3. Select the Allow cost burden schedule change for projects and tasks check box to allow a change of the
default cost burden schedule when creating and maintaining projects and tasks. Don't enable this option if you
want all projects of a project type to use the same schedule for internal costing.
4. The following table lists the decisions that you need to take for burden cost accounting.
Option Name Decision
Include burden cost on same
expenditure item
Decide if you want to include burden cost and raw cost amounts on the same expenditure item.
You can store the total burdened cost amount as a value with the raw cost on each expenditure
item.
Create expenditure items for burden
cost components
Decide if you want to include burden cost amounts on the same expenditure item, but want to
see the burden cost details. Expenditure items are created for each burden cost amount on an
indirect project and task.
Project Name and Task Name
Determine the project, and optionally the task, that receives the burden cost expenditure items.
Create separate expenditure item for
burden cost
Decide if you want to account for burden cost amounts as separate expenditure items on the
same project and task as the raw cost.
Create burden cost accounting journal
entries
Decide whether to create accounting entries for the burden costs.
Note:
If you select this setting, a separate journal line is created for the burden amount rather than
for the total burdened amount, which is the raw cost plus the burden cost. This journal line is
created independent of the raw cost journal line.
Deselect this check box if burden costs are calculated for reporting purposes only and you don't
want to export burdened costs to the general ledger.
80
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision
Create burdened cost accounting
journal entries
Decide whether you want to create a separate journal line for the total burdened cost.
CAUTION:
The raw cost may be accounted twice if separate journal lines are created for the raw cost
and for the total burdened cost.
You can use this option to track the total burdened cost amount in a cost asset or cost work-in-
progress account.
5. Click Save.
Selecting Capitalization Options
Configure capitalization options to determine the options that are inherited by each project associated with that project
type.
1. Navigate to the Capitalization Options tab.
2. The following table lists the decisions you need to take in the Construction in Progress section.
Option Name Decision
Cost Type
Decide whether to capitalize costs at the burdened or raw cost amount for projects with this
project type.
Asset Line Grouping Method
Decide how asset lines must be summarized. You can select All, which is the highest level of
summarization, or summarize by expenditure category or expenditure type.
Asset Cost Allocation Method
Decide if you want to automatically distribute indirect and common costs across multiple
assets.
Event Processing Method
Decide how assets and costs are grouped over time. You can choose to use either periodic or
manual events, or no events.
Require complete asset definition
Decide if a complete asset definition is required before sending costs to Oracle Fusion Assets.
You won't need to enter information for the imported asset line in Oracle Fusion Assets. The
Transfer Assets to Oracle Fusion Assets process places asset lines with complete definitions
directly into the Post queue in Oracle Fusion Assets.
Group supplier invoices
Decide if you want to consolidate the expenditure items on a supplier invoice into one asset line
according to the asset line grouping method.
81
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
3. If you aren't grouping supplier invoices, select one of the following options in the Supplier Invoices section.
As new additions: Sends each expenditure item on a supplier invoice line to Oracle Fusion Assets as a
separate addition line with a status of New.
As merged additions: Sends each supplier invoice line to Oracle Fusion Assets as a separate addition line
with the status of Merged.
4. In the Capitalized Interest section, optionally specify a Default Capitalized Interest Rate Schedule that is
inherited by projects using this project type.
5. Select the Allow override check box if project managers can change the capitalized interest rate schedule at
the project level.
6. Click Save.
Selecting Classifications
Assign project classifications to group your projects according to categories and codes that you define on the Manage
Class Categories page.
1. Navigate to the Classifications tab.
2. Click the Add Row icon.
3. Select a Class Category.
4. Select the Assign to all projects check box to automatically add the classification to the project definition for
all new projects using this project type.
5. Repeat the process for each class category you want to add to the project type.
6. Click Save.
Project Control
Overview of Oracle Project Control Configuration
The Oracle Project Control functional area lets you manage the financial and budgeting aspects of projects.
Using Project Control, you can configure your enterprise on how you monitor project execution, budget, forecast, and
track progress. You can configure period profiles, spread curves, project plan types, and financial plan types and use
Business Process Engineering Language (BPEL) workflows to manage budget and forecast approvals.
The preliminary step is to use the Setup and Maintenance work area to select the features and settings that you want to
implement for your enterprise.
This table describes the setup tasks for Project Control.
Task Name Description
Manage Period Profiles
Specify how time periods are grouped and displayed when editing budgets, forecasts, and project plan
costs.
Manage Spread Curves
Specify how quantity, cost, and revenue amounts are automatically distributed across a range of
accounting or project accounting periods.
Manage Resource Classes: Spread Curves Review and update resource classes to specify the spread curve to be used.
82
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task Name Description
Manage Financial Plan Types
Specify options used to control planning scenarios for budget and forecast versions.
Manage Project Plan Types
Specify default planning options that cascade down to the template and project levels.
Create Financial Plan Types
Create financial plan types to define default information and planning options for creating different types of budgets or
forecasts.
While creating a financial plan type, you can associate one or more sets, specify plan, currency, rate, and budgetary
control settings, and select generation, export, and reporting options.
Create any number of financial plan types based on company requirements as illustrated in the following figure. For
example, if your organization has stringent financial planning and oversight requirements, you can create separate
financial plan types for each planning scenario. Alternatively, you may create only a few financial plan types, for
example, for approved budgets and primary forecasts.
The following graphic illustrates how you can have multiple financial plan types for your projects. The financial plan
types can be approved cost budget, primary revenue forecast, estimate, and so on. The versions can be working,
submitted, approved, baseline and so on.
83
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Here's how you create financial plan types.
Enter Basic Information and Setup Options
To create a financial plan type:
1. In the Setup and Maintenance work area, go to the Manage Financial Plan Types task.
2. Use the Manage Financial Plan Types page to create, review, edit, or delete existing financial plan types.
3. Click the Create icon to open the Create Financial Plan Type page.
Use the Create Financial Plan Type page to enter basic financial plan type information, and setup and planning
options that determine how associated financial plan versions are created.
4. Enter a unique financial plan type name and select a date from which the financial plan type is available for use.
5. Optionally, provide a description and a date to which the financial plan type is available for use.
6. Use the Plan Class list to determine whether project managers will use the financial plan type to create budget
versions or forecast versions.
7. Use the Planning Amounts list to determine whether associated financial plan versions will contain cost
amounts, revenue amounts, or both.
84
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
If you want to create a financial plan type to plan for both cost and revenue, indicate whether one version will
contain both amounts, or if project managers must select to include either cost or revenue amounts when
creating a budget or forecast version.
8. Select setup options depending on whether you're creating a financial plan type of the Budget or Forecast plan
class.
If you're creating a financial plan type of the Budget plan class, make decisions as listed in the following table.
Option Name Decision Notes
Designate as approved cost budget
Designate as approved revenue budget
Is the financial plan type an approved
budget?
Decide whether the financial plan type will
create cost and revenue versions used for
plan comparison or project performance
reporting.
Designate as award budget
Will you use the financial plan type to create
budgets for sponsored projects?
Select this option if the financial plan type
will create control budgets for sponsored
projects.
Use workflow for status changes
Will you use an approval workflow?
Use workflow to trigger notifications when
project managers change the version status
or submit a request to change the version
status.
Set as default financial plan type
Set as default award financial plan type
Do you want the financial plan type to be
the default selection?
Set the financial plan type as the default,
if for example, you anticipate it to be the
most commonly used for creating budget
versions.
Enable planning in multiple transaction
currencies
Will project managers enter amounts in
multiple currencies?
Decide whether project managers can
enter amounts in currencies other than the
project currency.
Note:
To use transaction currencies, you
must define currency attributes on the
Currency Settings tab.
When the financial plan type allows
transactions in multiple currencies, the
Assign Resource in Single Currency
for a Task check box is displayed
under the Currency Settings tab. Select
this check box to assign resources in
a single currency for a task to create a
budget or forecast line. Project costs
that are incurred in another currency
are mapped to the existing budget or
forecast line. For example, this check
85
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
box is selected on a forecast version
with a forecast line in USD. If project
costs are incurred in EUR for the same
forecast line, then the project cost is
mapped to the existing forecast line in
USD instead of creating a new forecast
line in EUR.
Enable budgetary controls
Will you create control budgets with the
financial plan type?
Decide whether the financial plan type will
create cost budget versions that create
control budgets in Oracle Budgetary
Control.
Note: In the Manage Budgetary Control
and Encumbrance Accounting setup
page, if the Control Budget Filter
option is set to Ledger only, then you
can’t create a budget using a financial
plan type that’s enabled for budgetary
controls.
If you're creating a financial plan type of the Forecast plan class, make parallel decisions for the following
attributes:
Designate as primary cost forecast
Designate as primary revenue forecast
Use workflow for status changes
Set as default financial plan type
The following table lists a few more decisions that you need to take when creating a financial plan type of the
Forecast plan class.
Option Name Decision Notes
Automatically submit forecasts for approval
Can forecasts be automatically submitted
for approval?
Automatic submission for approval applies
only to primary forecasts. When the project
manager creates the first baseline version
for the approved budget, the application
creates the primary forecast version and
submits it for approval.
Automatically approve forecasts
Can project managers directly approve
forecasts?
If you don't use workflow for forecast
approvals, decide if project managers can
approve forecast versions directly (without
first submitting them to an approver).
86
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Tip:
The automatically approve forecasts
option applies even if project managers
aren't entitled to approve forecasts. So,
use it to enable automatic approval
for certain financial plan types while
controlling the forecast approval
entitlement for others.
Assign Sets
You associate one or more sets with financial or project plan types so that project managers can use them to create
financial plans (budget or forecast versions) for projects or project templates. Financial plan types are available for
selection only when projects or project templates are created for project units linked to selected sets.
The following figure illustrates an example of set assignments. The Consulting Services set is associated only with the
Consulting Services project unit. You associate the Consulting Bid financial plan type only with the Consulting Services
set. In this case, only project managers who create projects for Consulting Services can create versions of the Consulting
Bid financial plan type.
87
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
If you associate the Internal Services Set to the Consulting Bid financial plan type, then project managers from the
Internal Services project unit can also access that financial plan type.
Tip: To make financial plan types available more widely across your organization, you can assign them to a common
set.
To assign sets:
1. Navigate to the Set Assignments tab.
2. Click the Add Row icon to add a set assignment.
3. Select the Code of the desired set.
4. Repeat the process for each set to which the financial plan type is assigned.
5. Click Save.
Specify Plan Settings
Use the Plan Settings tab to specify the cost and revenue amounts to include in budget or forecast versions, level of
detail for planning, calendar and period options, and rate derivation options.
Navigate to the Plan Settings tab and make the following decisions related to the amount types that are available for
editing on budget and forecast versions and how they're edited and displayed.
88
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Amount Types
What measures can project managers plan for
on a budget or forecast?
Decide whether to plan for quantities, amounts,
and rates.
When selected, corresponding fields are
editable on the Edit Budget and Edit Forecast
pages. For example, when creating a financial
plan type for internal projects that don't track
cost amounts, project managers can select
quantity and deselect cost and rates.
Tip:
If you're planning for cost and revenue,
select the Use cost plan options for
revenue check box to replicate your cost
selections to revenue. Note that this check
box applies to current changes only. If you
update cost options later, you must select
the check box again to copy.
Planning Level
What measures can project managers plan for
on a budget or forecast?
At what level of the task hierarchy will project
managers plan?
Determine the level of the task structure at
which project managers will enter budget or
forecast amounts.
For example, create one financial plan type for
capturing detail cost amounts at the lowest
task level, another to capture summary cost
amounts at the top task level, and a third to
capture total revenue amounts at the project
level.
Calendar Type
Will project managers plan by period or for
duration of plan lines?
Decide whether to plan for the duration of
budget or forecast lines or to plan for specific
periods in the accounting calendar or project
accounting calendar.
Calendar Type
Will you use the financial plan type to create
control budgets for sponsored projects?
Select the Award Calendar calendar type if you
will use the financial plan type to create control
budgets for sponsored projects.
This calendar type creates the calendar for
control budgets based on the budget periods
defined for the award.
Calendar Type
Will you use the financial plan type to create
control budgets for nonsponsored projects?
Select either the Accounting Calendar or
Project Accounting Calendar, or None as
the calendar type if you will use the financial
plan type to create control budgets for
nonsponsored projects.
These calendar types create calendars for
control budgets by using the accounting period
or project accounting period.
If you select None as the calendar type, then
either the project duration or the maximum
89
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
task assignment duration is used to create
calendars for control budgets.
Cost Rate Derivation Date Type
How will cost rates be determined?
If project managers won't plan based on a
calendar, determine whether cost rates are
derived based on the start or end date of plan
lines, system date, a fixed date, or on effective
resource rate dates.
If project managers plan based on the
accounting calendar or project accounting
calendar, then determine whether cost rates are
derived based on the start date of plan lines or
on effective resource rate dates.
Period Profile
How will period amounts be displayed?
If project managers enter planning amounts
by period, select how the periods are grouped
for display when editing budget or forecast
versions.
Use predefined period profiles or create period
profiles based on your requirements on the
Manage Period Profiles page.
Maintain manual spread on date changes
Do you want to retain manual periodic spread
on date changes?
Decide whether to retain manual periodic
spread even if the duration changes due to a
scope change.
The period-level adjustments previously made
to the forecast or budget line aren't lost when
you modify the line dates in the user interface.
Note:
The Maintain manual spread on date
changes option doesn't apply to non-
periodic calendar versions.
Associate project costs or revenue to summary
tasks (if you're planning in both cost and
revenue planning amounts)
Associate project costs to summary tasks (if
you're planning in cost only planning amounts)
Associate project revenue to summary tasks
(if you're planning in revenue only planning
amounts)
Do you want to associate cost and revenue
to planned resource assignments in the task
hierarchy?
Decide whether to associate the incurred costs
or revenue for resources on the task hierarchy
at the level planned.
Note: This check box is available for
selection only when the Plan Class is set to
Forecast and the Planning Level is set to
Project and all tasks.
90
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Select Currency Settings and Rate Settings
Use the Currency Settings tab to select transaction currencies in which to enter financial plan amounts, and the rates for
converting those amounts to project currency, project ledger currency, or planning currency.
1. Navigate to the Currency Settings tab.
If you selected the Enable planning in multiple transaction currencies check box, then the following options
are displayed:
Assign Resource in Single Currency for a Task check box - Select this check box to assign resources in
a single currency for a task to create a budget or forecast line. Project costs that are incurred in another
currency are mapped to the existing budget or forecast line. For example, this check box is selected on a
forecast version with a forecast line in USD. If project costs are incurred in EUR for the same forecast line,
then the project cost is mapped to the existing forecast line in USD instead of creating a new forecast line
in EUR.
Edit icon - Click this icon and set the planning currency.
2. Select the following currency conversion attributes to define how the application must convert transaction
currency amounts to project currency, project ledger currency, and planning currency. If the financial plan type
supports planning for cost and revenue, then you must provide currency conversion attributes separately for
cost and revenue.
Rate Type as a source of conversion rates.
Date Type to determine whether conversion rates are derived based on the start or end date of plan
lines, or a fixed date.
If you selected Fixed date as the Date Type, then enter the date from which conversion rates will be used
in the Fixed Date field.
Note:
When the Use same conversion attribute for all currency conversions check box is selected
the same currency conversion attributes are used for all currencies. If you clear this check box,
then you must repeat this step for each transaction currency that project managers can use.
If the Enable planning in multiple transaction currencies check box is selected and you
clear the Use same conversion attribute for all currency conversions check box, then you
must select the Rate Type, Date Type, and Fixed Date for the project currency, project ledger
currency, and planning currency.
3. Click Save and Close.
Use the Rate Settings tab to specify the actual or planning rates used to calculate cost and revenue amounts on
associated budget or forecast versions.
Note: If the financial plan type supports planning for cost and revenue, you specify rate settings separately for cost
and revenue.
Add required project roles to the project and directly create work plan or financial plan by project roles and perform
high-level planning. In either of these cases, the application derives cost rates for these project role resources from the
project role rate schedules associated with the project, and bill rates from the project role overrides setup at the contract
91
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
level. Further, create project budget and forecast from the financial project plan containing the project role assignments
or directly from project resources, thus accurately determining projections for cost and revenue.
1. Navigate to the Rate Settings tab.
2. Click Add Row in the Rate Schedules section to specify rate settings for a business unit. You must specify rate
settings separately for each business unit.
3. Determine if project managers will use the same rate schedules defined for the project to calculate actual costs,
or use separate rate schedules for planning purposes.
4. To use actual rates, deselect the Use planning rates check box. In the Details section, optionally select rate
schedules for Resource Class Raw Cost Rate and Resource Class Bill Rate.
If the application is unable to determine cost or bill rates for a planning resource, then it uses the resource class
rates schedules you specify here.
5. To use planning rates, select the Use planning rates check box. In the Details section, select separate rates for
Person, Job, Project Role, Nonlabor Resource, and Resource Class, as required. You can also select a burden
schedule to use for calculating burdened costs for all planning resources (including those that aren't rate-
based).
6. Repeat the process for each business unit for which you want to select rates.
7. Click Save.
Select Budgetary Control Settings
Use the Budgetary Control Settings tab to define the control budgets that you can create. Control budgets are
automatically created in Oracle Budgetary Control when you create the baseline version of a project budget that's
enabled for budgetary control.
CAUTION: The financial plan type must be enabled for budgetary controls for the Budgetary Control Settings tab to
be available.
Navigate to the Budgetary Control Settings tab and make the following decisions related to the project and top resource
control budgets.
Option Name Decision Notes
Control Budget
How will you define the control budget, using
which project-related segments?
Decide whether to control amounts in the
budget version at the project or top resource
level for non sponsored projects or at the
project, award, top resource, or funding source
level for sponsored projects. These amounts
are passed to the control budget, and Oracle
Budgetary Control uses the project and top
resource level budget data to create control
budget account segments.
Control Level
How strictly do you want to control the funds
that are reserved for expenditures that impact
the control budget?
Select a control level for the project and top
resource control budgets. The options are:
Absolute
Advisory
Track
Do Not Create Control Budget
92
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Default Rate Type
Which rate type will convert the transaction
amount to the control budget currency prior to
the funds check?
Select a default rate type to use on control
budgets that are created from this financial plan
type. You can change the rate type on individual
budget versions.
If transactions fail processing due to missing
currency conversion attributes, then ensure
that you specify this rate type and that the
conversion rate is setup using this rate type for
the currency in the Manage Conversion Rate
Types page.
Tolerance Percentage
By what percentage can transactions exceed
the budgeted amount without generating a
warning or exception?
Transactions that impact the control budget can
exceed the budgeted amount by the percentage
that you enter. After transactions meet or
exceed the tolerance level, a notification is
issued or the funds reservation process fails.
Select Generation Options
Use the Generation Options tab to indicate how cost and revenue are calculated when you generate a budget or forecast
version from another financial plan or from the project plan.
Perform the following actions if you're creating a financial plan type of the Budget plan class.
1. Navigate to the Generation Options tab.
2. Select a Generation Source to determine whether budget versions must be generated from another financial
plan or from the project plan.
3. If you selected Financial plan type as the generation source, select a Source Plan Type to indicate which
financial plan type the source plan must belong to.
4. Select a Source Plan Version.
If your generation source is Project plan type, then you can select either Working or Baseline.
If your generation source is Financial plan type and your source plan type is a budget financial plan type,
then you can select Current baseline, Original baseline, or Current working.
If your generation source is Financial plan type and your source plan type is a forecast financial plan
type, then you can select Current approved, Original approved, or Current working.
5. If the financial plan type supports planning for revenue, select a Revenue Generation Method. The following
table describes the options.
Option Name Description
Manual entry
Revenue amounts aren't generated. Project managers can enter amounts manually. Manually
entered revenue amounts are retained even if any changes are made to quantity, raw cost, or
burdened cost of an individual plan line; at the periodic level or version level.
Also, when you refresh rates, the revenue isn't recalculated based on the rate derivation logic to
fetch rates from the rate schedules defined in plan settings.
93
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Description
Planning rate based
Revenue amounts are generated based on the planning rates you specify in the Rate Settings
tab of the financial plan type.
Contract revenue classification method
Revenue is generated line by line, using the revenue method classification on the revenue
plan that’s associated with the contract line. The contract line revenue method classifications
determines if revenue rates, bill rates, or contract line funding amounts are used to derive
revenue.
If you're using the Contract revenue classification method for determining revenue amounts
for financial plans, then the expected revenue for the project is reflected based on the
parameters known at that time.
For projects or tasks that are associated to contract lines with Amount Based revenue
plans, the best estimate is the funding amount that's assigned to that project or task on
the contract line.
For projects or tasks that are associated to contract lines with Rate Based revenue plans,
for example, As Incurred, the best estimate is based on the planned resources and the
rates that they will eventually use when billing and recognizing revenue.
For financial resources, the rate is determined using the Resource Class Bill Rate schedule
that’s assigned to the financial plan. If the assigned Resource Class Cost and Bill Rate
schedules are the same, then the planned cost and revenue are also the same.
6. Select the Retain manually added budget lines check box if plan lines added by project managers must be
retained when an existing version is generated again.
7. Select the Retain override rates from source check box if override rates entered in the source plan version
must be used to generate amounts in the new budget version.
8. Click Save.
If you're creating a financial plan type of the Forecast plan class, in addition to the decisions listed for budget financial
plan types, you must also determine the following:
1. The following table lists the Forecast ETC Method that you can use to determine how ETC amounts are
calculated. Select one of the options.
Option Name Resulting Calculation
Remaining plan
ETC = Plan - Actual
Plan to complete
ETC = Plan - Actual ETC = Plan * (1 - Physical Percent Complete from latest Published Progress)
Cost performance index based
ETC = (1 - Physical Percent Complete) / Physical Percent Complete * Actual
Actual amounts are from summarized project plan data and physical percent complete from
latest published progress.
94
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Resulting Calculation
Note:
If either the physical percent complete or actual amounts are zero, then the Plan to
complete method is used.
Manual entry
ETC amounts not calculated
2. If you're using the Remaining plan ETC method, then select the Carry forward unused amounts from past
periods check box to carry over unused source plan amounts from periods prior to the actual amounts through
period.
3. Select one of the following options for the Actual Amounts Through Period field to determine the period
through which to obtain actual amounts when generating forecast amounts:
Current period
Prior period
Last closed period
4. Select the Allow negative ETC calculation check box if you don't want negative results of ETC calculation to be
set to zero.
5. Select the Open commitments check box to include commitments such as purchase orders and supplier
invoices in the project forecast.
6. Click Save.
Select Reporting Options, Export Options, and Additional Information
Use the Reporting Options tab to indicate how to roll up amounts for planning resources, report quantity when planning
for cost and revenue in separate financial plan versions, calculate margins, and display amounts.
The following table lists the decisions you need to take while setting up reporting options for your project.
Option Name Decision Notes
Report Quantity
What quantity will be used for reporting?
If the financial plan type supports planning for
cost and revenue in separate plan versions,
decide whether cost or revenue quantity is used
for reporting.
Report Cost
How will margin be calculated?
Decide whether to calculate margins based on
raw cost or burdened cost.
Amount Scale
How will large amounts be displayed?
Decide how you want whole number amounts
to display when project managers view
quantities and amounts when reviewing and
finalizing budgets or forecast versions. For
example, select a rounding factor of 100 and a
value of 25,000 is displayed as 250.
95
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Currency Type
What currency will cost and revenue be
displayed in?
Decide whether you want amounts to be
displayed in project currency or project ledger
currency.
Use the Export Options tab to determine the amounts, rates, and quantities that you can export to Excel. The following
table lists the decisions you need to take:
Option Name Decision
Use task planned dates as task assignment
dates
Select the check box to display currency conversion attributes and costs and revenue in project
currency and project ledger currency when you edit financial plan versions in Excel.
Note:
This option is enabled if you select the Enable planning in multiple transaction currencies check
box in the Budget or Forecast Options section.
Display commitments
Select the check box to display commitment amounts in Excel.
Selected Measures
Use the Available Measures-Selected Measures select shuttle to determine what financial plan
information you can review and edit in Excel.
Use the Additional Information tab to capture information specific to your organization. To enable data entry, configure
the PJO_PLANNING_OPTIONS_DFF descriptive flexfield.
Related Topics
Example of Set Association with Financial Plan Types
How Financial Plan Types and Project Budget Versions Work With Budgetary Control
How do I define the financial plan type to create an award project budget?
Considerations for Selecting Rate Schedules for Project and Financial Planning
Invoice and Revenue Method Components
Invoice and Revenue Method Classifications
Considerations for Changing a Revenue Method
Create Project Plan Types
Create project plan types to define default information used for creating a project plan and capturing progress.
While creating a project plan type, you can associate one or more sets, specify plan, task, currency, rate, and progress
settings, and select budget generation options.
96
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Associate one project plan type to a project template. Projects created using the template inherit setup and planning
option values. You can revise setup or planning options at each level to match specific planning requirements. The
following figure shows how you can edit the setup or planning options at the project template or project level.
The following sections describe how to create project plan types.
Enter Basic Information and Setup Options
To create a project plan type:
1. In the Setup and Maintenance work area, go to the Manage Project Plan Types task.
2. Use the Manage Project Plan Types page to create, review, edit, or delete existing project plan types.
3. Click the Create icon to open the Create Project Plan Type page.
Use the Create Project Plan Type page to provide basic project plan type information and specify setup and
planning options that determine how associated project plans and progress are created.
4. Enter a unique project plan type name and select a date from which the project plan type is available for use.
5. Optionally, provide a description and a date to which the project plan type is available for use.
97
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
6. Use the options in the Setup Options section to indicate whether:
Project managers can use Microsoft Project for scheduling.
Project managers can enter amounts in currencies other than the project currency.
Note: When you select this option, you must provide currency conversion attributes in the Currency Settings
tab.
Assign Sets and Specify Plan Settings
To assign sets and specify plan settings:
1. Navigate to the Set Assignments tab.
Use the Set Assignments tab to associate sets with project plan types so that project managers can use them to
create project plans for projects or project templates. For more information, see the Create Financial Plan Types
section of this document.
2. Navigate to the Plan Settings tab.
Use the Plan Settings tab to indicate whether you will track costs in the project plan and whether you will plan
for the project duration or by periods.
3. The following table lists the decisions you need to take when assigning sets to your project.
Option Name Decision Notes
Enable project plan costs
Will project managers plan for costs on the
project?
Enable project plan costs if project
managers must plan for costs on tasks and
task assignments and monitor actual costs
through the project lifecycle.
Note:
If you don't enable planning for costs,
then physical percent complete values are
calculated based only on effort.
Set unplanned assignments as planned
assignments
Can a resource with actuals get added
directly as a planned resource to the
financial project plan?
When this option is selected, as project
costs are incurred, the resource is added as
a planned resource to the financial project
plan instead of being marked as unplanned.
When assigning a resource as a planned
resource, the application:
Defaults the dates from the task dates.
You can edit these dates unless the
Use task planned dates as task
assignment dates check box is
selected at project plan type level.
Defaults the currency to the actual
currency if the project plan type allows
planning in multiple currencies, else it
always assigns in the project currency.
98
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Periodic spread for planned resource
happens from the planned start date
of the task or the actual period.
Associate project costs to summary task
assignments
Do you want to associate cost to planned
resource assignments in the task hierarchy?
Decide whether to associate the incurred
costs for resources on the task hierarchy at
the level planned.
Note: This check isn't available
for selection if the Set unplanned
assignments as planned assignments
or Use third-party software for
scheduling check box is selected.
Calendar Type
Will project managers plan by period or for
duration of plan lines?
Decide whether project managers will
plan for the task assignment duration or
if they can plan for specific periods in the
accounting calendar or project accounting
calendar.
Rate Derivation Date Type
How will cost rates be determined?
If project managers won't plan based on a
calendar, then determine whether cost rates
are derived based on the start or end date
of plan lines, system date, a fixed date, or on
effective resource rate dates.
If project managers plan based on the
accounting calendar or project accounting
calendar, then determine whether cost rates
are derived based on the start date of plan
lines or on effective resource rate dates.
Fixed Date
How will cost rates be determined?
If the rate derivation date type is Fixed
Date, then select the date from which rates
will be used for calculating costs.
Period Profile
How will period amounts be displayed?
If project managers will enter planning
amounts by period, then select how
periods will be grouped for display when
project managers view amounts for task
assignments.
Maintain manual spread on date changes Do you want to retain manual periodic
spread on date changes?
Decide whether to retain manual periodic
spread even if the duration changes due to
a scope change.
99
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
The period-level adjustments previously
made to the forecast or budget line aren't
lost when you modify the line dates in the
user interface.
Note: The Maintain manual spread on
date changes option doesn't apply to
non-periodic calendar versions.
Specify Task Settings
Use the Task Settings tab to specify task and task assignment date settings.
1. Navigate to the Task Settings tab.
2. The following table lists the ways in which you can enter and calculate the planned dates for tasks and task
assignments.
Option Name Decision
Use task planned dates as task
assignment dates
Must task assignment dates match corresponding task planned dates?
If yes, then project managers can't edit task assignment dates.
Automatically roll up task planned
dates
Must planned dates for lowest-level tasks roll up to summary tasks?
If yes, then project managers can't edit summary task dates.
CAUTION: The Use task planned dates as task assignment dates check box and the Automatically roll
up task planned dates check box are disabled if you enable use of Microsoft Project as the scheduling
application.
3. The following table lists the options that you can use to enter transaction dates.
Option Name Decision
Synchronize task transaction dates with
planned dates
Decide whether transaction dates must match the planned dates for tasks, plus or minus the
date adjustment buffer.
If you don't select this check box, then transaction dates for summary tasks are blank by
default. Transaction dates for subtasks are set to summary task transaction dates.
Date Adjustment Buffer in Days
Optionally, specify a date adjustment buffer to determine the maximum lag (positive) or lead
(negative) time between task planned dates and task transaction dates.
100
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision
4. Click Save.
Specify Currency Settings and Rate Settings
Use the Currency Settings tab to select transaction currencies in which to enter project plan amounts, and the rates for
converting those amounts to project currency or project ledger currency.
Use the Rate Settings tab to specify the actual or planning rates used to calculate cost and revenue amounts on the
project plan.
For more information on both tabs, see the Create Financial Plan Types section of this document.
Specify Progress Settings
Use the Progress Settings tab to define how progress values are calculated and roll up the task hierarchy. These options
indicate default values that you can modify at the project level.
1. Navigate to the Progress Settings tab.
2. The following table lists the decisions you need to take on how the application should calculate physical percent
complete values and rolls up task hierarchy.
Option Name Decision Notes
Physical Percent Complete Calculation
Method
How is physical percent complete calculated
for lowest-level tasks?
Decide whether project managers must
enter physical percent complete or if the
application calculates the value based on
either cost or effort.
Calculation is based on the following
formula, where amount can be cost or
effort, as appropriate:
Actual Amount / Estimate at Completion
(EAC) Amount * 100
Primary Physical Percent Complete Method
How does physical percent complete roll up
the task hierarchy?
Decide whether the rolled-up physical
percent complete for summary tasks is
based on cost or effort.
Calculation is based on the following
formula, where amount can be cost or
effort, as appropriate:
Sum of Earned Value Amount from
Subtasks / Sum of Baseline Project Plan
Amount * 100
101
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
Note:
The rolled up physical percent complete
value is used in project forecasting,
reporting, and revenue generation.
3. Decide how ETC amounts are calculated as listed in the following table. The following table lists the ways in
which you can calculate ETC amounts.
Option Name Decision Notes
ETC Method
How are ETC amounts calculated?
Use one of the following methods to
calculation ETC values:
Remaining plan: For all progress
calculations (initial and subsequent)
ETC cost is calculated as:
Current Planned Cost - Actual Cost
Manual entry: For first progress as-of
date, ETC cost is calculated as:
Current Planned Cost - Actual Cost
For all subsequent progress as-of
dates, ETC cost equals ETC cost from
the previous published progress.
Allow negative ETC calculation
Can ETC values be negative or should they
be set to zero?
If you're using the Remaining plan ETC
method and actual amounts are greater
than the plan, then you can select to display
negative ETC amounts that result.
4. The following table lists the ways in which you can update the project plan information and generate a forecast
version when publishing progress.
Option Name Decision
Update planned quantity with EAC
quantity
Decide whether planned quantity in the project plan is updated with EAC quantity from
progress.
Automatically generate forecast version
Decide whether a forecast version is created when the project manager publishes progress.
Financial Plan Type
Select the financial plan type for use in forecast creation.
102
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
5. Click Save.
Select Budget Generation Options
Use the Budget Generation Options tab to decide whether a budget version is generated when you set a baseline for
your project plan and to specify how the budget version is generated. These options indicate default values that you can
modify at the project level.
1. Navigate to the Budget Generation Options tab.
2. The following table lists the decisions you need to take when choosing to generate a budget version while
setting a baseline for a project plan.
Option Name Decision
Generate budget version
Decide whether a budget version is created when the project managers sets a baseline for the
project plan.
Financial Plan Type
Select the financial plan type for use in budget creation.
Automatically designate budget version
as baseline
Decide whether the budget version must be set as the current baseline version.
Note:
If an existing current baseline budget version exists, then the existing version becomes
a standard baseline version and the newly created baseline version becomes the current
baseline version.
3. Click Save.
Provide Additional Information
Capture information specific to your organization using the descriptive flexfield PJO_PLANNING_OPTIONS_DFF.
Project Costing
Overview of Project Costing Configuration
This table lists setup tasks for Oracle Fusion Project Costing, grouping them into task lists. These tasks include setup
configurations for descriptive PPM flexfields and profile options, project cost capitalization options, project cost
distribution across organizations, and options to integrate Costing with other Oracle applications.
103
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task List Name Description
Define General Costing Setup
Configure transaction sources, documents, profile options, and descriptive flexfields related to Oracle
Fusion Project Costing functionality.
Define Capital Projects
Configure options used to capitalize project costs and place assets in service.
Define Borrowed and Lent Accounting
Configure borrowed and lent accounting to distribute project costs across organizations.
Define Project Costing Integrations
Configure options used to integrate Oracle Fusion Project Costing with other Oracle Fusion
applications.
This chapter provides detailed setup steps for defining an additional segment for the cost collection flexfield.
See the Implementing Subledger Accounting guide for more details.
Related Topics
Set Up Default Budget Account
As a project application administrator, you must set up a default budget account for cost transactions before you enable
an account based control budget for budgetary control.
You can create a default budget account for transactions from various sources by:
1. Creating a transaction account definition
2. Associating the transaction account definition to your ledger
Create a Transaction Account Definition
When you import costs for a project that's enabled for budgetary control, the application derives the budget account
using the account rule assignments that you define for the Project Costing Budget Account transaction type in the
transaction account definition.
1. In the Setup and Maintenance work area, go to the Define Transaction Accounting for Project Financial
Management task.
2. Click the Manage Transaction Account Definitions link. Set the scope to Project Costing if not already set.
The application provides the PPM Default Account Generation Definition predefined transaction account
definition, which is selected by default. You can create a copy of this transaction account definition and
configure it. To copy the definition, select Duplicate from the Actions menu.
3. Enter a name and short name for your transaction account definition. You can optionally select a chart of
accounts.
4. Edit the account combination and segment rules according to your business needs. You can create an account
combination rule and segment rules or segment rules and then associate them with the Project Costing Budget
Account transaction account type.
5. Click Activate to activate your transaction account definition. Verify that the status changes from Incomplete to
Active.
6. Click OK to close the confirmation message window.
7. Click Done.
104
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Associate a Transaction Account Definition to a Ledger
Budgetary control uses the budget account to derive the budget amount for validating the transaction cost for your
ledger.
1. In the Setup and Maintenance work area, go to the Define Transaction Accounting for Project Financial
Management task.
2. Click the Manage Subledger Accounting Options link. Set the scope to Project Costing if not already set.
3. Search for your ledger.
4. In the search results, select the row that corresponds to the Project Costing application name for the selected
ledger.
5. Click Edit Accounting Options for Project Costing.
6. Select your transaction account definition from the list of values in the Transaction Account Definition field.
7. Click Save.
Note: If a transaction fails indicating that the account derived by account rules can't be created or accessed, then
identify if the failure is in the project control budget or the General Ledger control budget. If the failure is in the
General Ledger control budget and the account generated for the budget transaction is incorrect, then review the
Transaction Account Definition to verify if the rules were defined correctly to derive an account and update the rules
accordingly.
Related Topics
Account Rules
Transaction Account Builder
Define an Additional Segment in the Cost Collection Flexfield
The Cost Collection flexfield helps you to capture product-specific attributes on actual cost and commitment
transactions.
The Project Costing descriptive flexfield captures a complete set of transaction attributes in source applications and
displays them in Oracle Fusion Project Costing. The Cost Collection flexfield is available for use on pages such as the
Manage Unprocessed Costs page from where you can create transactions, and on the various Create Costs ADFdi
Excel spreadsheets. It is also displayed on purchase orders, supplier invoice distributions, and expense reports in source
applications.
To define an additional segment in the Cost Collection flexfield:
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Standard Cost Collection
Flexfield task.
2. Click the Manage Project Standard Cost Collection Flexfield link.
3. Use the Manage Project Standard Cost Collection Flexfield page to manage context sensitive segments. Select
the Project Costing Details flexfield row.
4. Click the Edit icon.
5. In the Context Sensitive Segments section, expand the Context list.
6. Select the context for which you want to add the additional segment in the flexfield and view the context
sensitive segments. To view this newly added segment in Project Costing you must also add this segment to the
PJC: All context.
7. Select a user-defined attribute row, such as USER_DEF_ATTRIBUTE1, to define the context sensitive segment.
105
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Note: You must define context sensitive segments by using only the user-defined attributes and not
reserved or other attributes, such as RESERVED_ATTRIBUTE1, EXPENDITURE_ITEM_DATE and so on.
8. Click Edit.
9. Use the Edit Segment page to specify the segment name, and define how it must be displayed and validated.
Note: User-defined attributes for this flexfield support only character data type, which includes alphabets
and numbers. However, you cannot use negative numbers or numbers with decimal values.
10. Optionally specify a description.
11. Select the Enabled check box to enable this segment.
12. Depending on how the segment must appear, for example as a list, associate an existing value set or create a
value set for Oracle Fusion Project Costing and associate the value set to the segment.
13. In the Validation section select a value set.
14. Optionally make this a required field by selecting the Required check box.
Note: To ensure that project attributes are entered for your transactions, you can mark the Project Number
segment as a required field. This automatically makes the Task Number, Expenditure Type, Expenditure
Organization, and Expenditure Item Date segments required for the context.
15. In the Initial Default section, specify the format of the default value for the segment, and the entity attribute
from which the segment is derived.
16. In the Display Properties section, enter a value for Prompt which appears as the field label.
17. The Display Type field specifies how the segment appears. For example, you can specify the expense locations
in a drop-down list.
Select a value for Display Type such as Check Box, List of Values, or Text Area.
18. On the Edit Segment page, click Save and Close.
19. On the Edit Context page, note the created segment name so you can identify it in the transactional pages.
20. Repeat steps 7 through 19 for every additional context in which the new segment must appear.
21. After you define all the flexfields, click Save and Close.
22. You must deploy the Cost Collection flexfield to make it available for users while entering transactions. Click the
Deploy Flexfield button on the Manage Project Standard Cost Collection Flexfield page.
23. You can now verify the segment you defined using the Cost Collection flexfield by creating a transaction from
either the Manage Unprocessed Costs page or the various Create Costs ADFdi Excel spreadsheets.
Configure the Project Costing Details Flexfield
You can configure the Project Costing Details flexfield by using the Manage Project Standard Cost Collection Flexfield
setup task to cater to your business needs.
For example, you can restrict expenditure types for specific expenditure organizations, derive project expenditure type
based on purchase category, make the project-owning organization as your default expenditure organization, and so
on.
Creating New Value Sets
1. Click Navigator > Setup and Maintenance, and search for the Manage Value Sets task.
2. Click the Manage Value Sets link.
3. Click Create in the Search Results section to create a new value set.
106
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
4. On the Create Value Set page, enter the Value Set Code, select Cost Collection as the Module, select Table as the
Validation Type, and select Value Data Type as required.
5. In the Definition section, enter the table or view name in the FROM Clause field.
6. Enter the column you want to add in the Value Column Name field.
7. Enter your query criteria in the WHERE Clause field. To refer to an existing segment value, use the format :
{SEGMENT.<segment column>}. For example, :{SEGMENT.EXPENDITURE_ITEM_DATE}. To refer to a parameter value,
use the format :{PARAMETER.<parameter name>}. For example, :{PARAMETER.PurchaseCategory}.
8. Click Save and Close.
Using Value Sets in Existing Segments
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Standard Cost Collection
Flexfield task.
2. Click the Manage Project Standard Cost Collection Flexfield link.
3. On the Manage Project Standard Cost Collection Flexfield page, verify that the Project Costing Details flexfield
row is selected in the Search Results table, and click Edit.
4. On the Manage Project Standard Cost Collection Flexfield page, click Manage Contexts.
5. On the Manage Contexts page, select your context code in the Context Code field and click Search. For
example, EXM: Expense Report Line, POR: Requisition, and so on.
6. Select your context in the Search Results table and click Edit.
7. On the Edit Context page, select the segment row in the Context Sensitive Segments section for which you
want to use the new value set and click Edit.
8. On the Edit Segment page, select the new value set for the Value Set field in the Validation section.
9. If your value set returns only a single value then that value is used as the default value for that segment. If your
value set returns multiple values then you must explicitly set a default value using the Initial Default section.
10. Click Save and Close.
11. Click Save and Close.
12. Click Save and Close.
13. Click Save and Close.
14. On the Manage Project Standard Cost Collection Flexfield page, select the Project Costing Details row in the
Search Results section.
15. Click Deploy Flexfield.
16. Monitor the deployment and click OK to dismiss the confirmation window after the deployment is complete.
17. Verify that the Deployment Status changes to Deployed.
18. Sign out of the application and sign in to activate the changes.
Configuring Segments to Limit List of Values
To conditionally control the list of values returned by a field based on the value selected for a previous field, you
can change the order of the segments in the flexfield to create a master-child relationship between two segments.
For example, if you want the tasks list of values to be controlled by the expenditure item date, then move the
EXPENDITURE_ITEM_DATE segment immediately before the TASK_ID segment, edit the query criteria for the value set
of the TASK_ID segment, and redeploy the flexfield.
Set Project-Owning Organization as the Default Expenditure
Organization on Payables Invoices
This example demonstrates how project application administrators can set the project-owning organization of a project
to be the default expenditure organization on an invoice line.
107
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
The following table summarizes key decisions for this scenario.
Decisions to Consider In This Example
For which expenditure organizations can I
create invoice lines?
Only those expenditure organizations that are also project-owning organizations.
Can I set a default value for the
expenditure organization of my cost
transaction?
Yes, by using the project-owning organization to be the default expenditure organization.
Summary of Tasks
To set the project-owning organization as the default expenditure organization on invoices, project application
administrators must:
1. Create a value set.
2. Use the value set in the invoice line.
3. Use the value set in the invoice distribution.
4. Deploy the updated Project Costing Details flexfield.
Creating a Value Set
1. Click Navigator > Setup and Maintenance, and search for the Manage Value Sets task.
2. Click the Manage Value Sets link.
3. On the Manage Value Sets page, click Create in the Search Results section to create a new value set.
4. On the Create Value Set page, enter the following values. The following table lists the values that you need to
enter on the Create Value Set page.
Field Value
Value Set Code
PJC_DEFAULT_EXP_ORGANIZATION
Description
Project-owning organizations that are the default expenditure organizations.
Module
Cost Collection
Validation Type
Table
Value Data Type
Character
5. In the Definition section, enter the following values.
Field Value
FROM Clause PJF_ORGANIZATIONS_EXPEND_V
108
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Field Value
Value Column Name
NAME
ID Column Name
ORGANIZATION_ID
WHERE Clause
org_id = :{PARAMETER.BusinessUnit} and nvl(:{SEGMENT.EXPENDITURE_
ITEM_DATE}, trunc(sysdate)) between nvl(EFFECTIVE_START_DATE, nvl(:
{SEGMENT.EXPENDITURE_ITEM_DATE}, trunc(sysdate))) and nvl(EFFECTIVE_
END_DATE, nvl(:{SEGMENT.EXPENDITURE_ITEM_DATE}, trunc(sysdate)))
and organization_id = (select carrying_out_organization_id from pjf_
projects_all_b where project_id = :{SEGMENT.PROJECT_ID})
6. Click Save and Close.
Using the Value Set in the Invoice Line
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Standard Cost Collection
Flexfield task.
2. Click the Manage Project Standard Cost Collection Flexfield link.
3. On the Manage Project Standard Cost Collection Flexfield page, verify that the Project Costing Details flexfield
row is selected in the Search Results table, and click Edit.
4. On the Manage Project Standard Cost Collection Flexfield page, in the Context Sensitive Segments section
select AP: Invoice Line as the context.
5. Select the ORGANIZATION_ID row and click Edit.
6. On the Edit Segment page, select PJC_DEFAULT_EXP_ORGANIZATION as the value set in the Validation section.
7. Since the value set PJC_DEFAULT_EXP_ORGANIZATION returns a single value, that value is used as the default value
of the expenditure organization. You don't have to specify a default value using the Initial Default section on the
Edit Segment page.
8. Click Save and Close.
Allow Employees to Enter Expenses for Active Tasks Only
This example demonstrates how project application administrators can limit the list of values for Task Number field on
an expense item to allow employees to enter expenses for only those project tasks which are currently active.
That is, the expenditure item date is within the task start and finish dates.
The following table summarizes key decisions for this scenario.
Decisions to Consider In This Example
For which project tasks can I enter time?
Only those project tasks for which the expenditure item date lies within the task start and finish dates.
How can I select the project tasks for which
I want to enter time?
Using the Task Number list of values field on the Create Expense Item page.
109
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Decisions to Consider In This Example
Summary of Tasks
To limit the number of tasks in the Task Number list of values on an expense item, project application administrators
must:
1. Create a value set.
2. Use the value set in the expense report line.
3. Deploy the updated Project Costing Details flexfield.
Creating a Value Set
1. Click Navigator > Setup and Maintenance, and search for the Manage Value Sets task.
2. Click the Manage Value Sets link.
3. Click Create in the Search Results section to create a new value set.
4. The following table lists the values you need to enter on the Create Value Set page.
Field Value
Value Set Code
MY_PROJECT_TASK_EXPENSE
Description
Value set to display only active tasks.
Module
Cost Collection
Validation Type
Table
Value Data Type
Character
5. The following table lists the values you need to enter in the Definition section.
Field Value
FROM Clause
PJC_TASKS_CCW_V
Value Column Name
TASK_NUMBER
Description Column Name
TASK_NAME
ID Column Name
TASK_ID
110
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Field Value
WHERE Clause
expenditure_org_id = :{PARAMETER.BusinessUnit} and project_id = :
{SEGMENT.PROJECT_ID} AND NVL(START_DATE,(:{PARAMETER.EIDate})) <= (:
{PARAMETER.EIDate}) AND NVL(COMPLETION_DATE,(:{PARAMETER.EIDate})) >=
(:{PARAMETER.EIDate})
ORDER BY Clause
TASK_NUMBER
6. Click Save and Close.
Enable Team Members to Enter Project Time
Use delivered objects to enable the team members of financial projects to enter project time. Alternatively, you can
create your own objects.
Your Time and Labor manager or administrator must set up the following to enable the project team members to enter
time:
User group
Time entry profile
Time processing profile
Creating a User Group
You can either use the delivered Projects Usage user group or use the following process to create your own group:
1. Click Navigator > Setup and Maintenance, and search for the Manage HCM Groups task.
2. Click the Manage HCM Groups link.
3. Click the Create icon on the toolbar of the Search Results table.
4. On the Create Group page, enter the group name and other details.
5. Click Save and Close.
Updating a User Group
Update an existing user group so that new project team members can enter time for their assigned projects.
1. Click Navigator > Setup and Maintenance, and search for the Manage HCM Groups task.
2. Click the Manage HCM Groups link
3. Search for the user group that you want to update.
4. Select the user group in the Search Results table and click Refresh Group Membership on the table toolbar.
5. Click Submit on the Refresh Group Membership process page.
6. Note the process ID in the confirmation message and click OK to close the confirmation window.
7. On the Manage HCM Groups page, select your user group and click View Evaluation Status.
8. Search for the process ID of the process you submitted and verify that the Processing Status of your process
is Completed Successfully. If the processing status is different, then click Search again to refresh the Search
Results table.
111
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Creating a Time Entry Profile
You create a time entry profile for project team members so that they can enter time only for the projects to which
they're assigned.
1. Click Navigator > Setup and Maintenance, and search for the Manage Worker Time Entry Profiles task.
2. Click the Manage Worker Time Entry Profiles link.
3. Click the Create icon on the toolbar of the Search Results table.
4. On the Create Worker Time Entry Setup Profile: Profile Values page, enter the profile name, description, and
effective start date.
5. Select the layout set Projects Layout Set Filtered by Project Team Members.
6. Enable the entry actions as required in the Time Entry Actions Allowed table and enter appropriate values for
the Days Before and Days After fields for these actions.
7. Click Next.
8. Click the Add icon on the toolbar of the Group Assignments section on the Create Worker Time Entry Setup
Profile: Group Assignments page.
9. Select the user group for which you want to use this time entry profile in the Group Name field.
10. Click Next.
11. Click Move to Top in the Priority Order section on the Create Worker Time Entry Setup Profile: Profile
Priority page to move your user group to the top.
12. Click Next.
13. Click Save and Close.
Creating a Time Processing Profile
You create a time processing profile for project team members so that they can enter time for only the projects to which
they're assigned.
1. Click Navigator > Setup and Maintenance, and search for the Manage Worker Time Entry Profiles task.
2. Click the Manage Worker Time Entry Profiles link.
3. Open the Setup and Maintenance work area, and go to the Manage Worker Time Processing Profiles task.
4. Click Create on the toolbar of the Search Results table.
5. On the Create Worker Time Processing Setup Profile: Profile Values page, enter the profile name,
description, and effective start date.
6. In the Time Card Period field, select the value Projects and Payroll Weekly Starting Monday from the list.
7. In the Time Consumer Set field, select the value Projects and Payroll from the list.
8. Click Next.
9. Click Add on the toolbar of the Group Assignments section on the Create Worker Time Processing Setup
Profile: Group Assignments page.
10. Select the user group for which you want to use this time processing profile in the Group Name field.
11. Click Next.
12. Click Move to Top in the Priority Order section on the Create Worker Time Processing Setup Profile: Profile
Priority page to move your user group to the top.
13. Click Next.
14. Click Save and Close.
112
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Project Billing
Overview of Project Billing Configuration
This table lists the setup task lists and tasks for Oracle Fusion Project Billing.
Task or Task List Name Description
Define Contracts Configuration for Project
Billing
Define and manage setup related to project contracts including contract types and content that can be
used consistently across contracts.
Define General Project Billing Setup
Enable project billing, manage the general project billing setup, and configure the project billing
business unit options.
Define Internal Project Billing
Manage the project billing general setup, options, processing rules, transfer pricing, and extensions
used for interproject and intercompany project billing.
Define Customer Billing Configuration for
Project Billing
Define the configuration for processing transactions and related billing functions.
Define Transaction Taxes for Rapid
Implementation
Configure tax setup according to local and international tax requirements.
This chapter provides detailed setup steps for the following required tasks:
Manage Event Types
Manage Revenue Methods
Manage Invoice Methods
Manage Invoice Formats
Create Event Types
Create event types to control whether events are used to invoice, recognize revenue, or perform both functions
for contract lines. For example, you can create event types for invoice fees or to recognize revenue associated with
milestones.
Event types can be used to derive the accounting in Oracle Fusion Subledger Accounting for event-based invoice and
revenue accounting entries.
Optionally, you can add a tax classification code to an event type. Oracle Fusion Project Billing calculates the
approximate tax amounts for events of this type on contract invoice lines.
113
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
The following section describes how you create event types.
Entering Basic Event Type Information
To create an event type:
1. Click Navigator > Setup and Maintenance, and search for the Manage Event Types task.
2. Click the Manage Event Types link.
Use the Manage Event Types page to create event types and to review, edit, or delete existing event types.
3. Click Add Row to create an event type.
4. Enter a unique name in the Event Type column. Optionally, provide a meaningful description.
5. Select a Revenue Category for reporting event-related revenue.
Note: Create revenue categories using the standard lookup PJF_REVENUE_CATEGORY before creating
event types. You can update the lookup from the Manage Revenue Categories page or the Manage Standard
Lookups page.
6. Select the Revenue check box if the current event type will be used for recognizing revenue.
7. Select the Invoice check box if the current event type will be used for invoicing.
8. Click Save.
Specifying Tax Classification Codes
Associate tax classification codes with event types to enable calculation and display of approximate tax amounts in
Oracle Fusion Project Billing before final tax figures are available in Oracle Fusion Receivables.
1. Click Add Row in the Tax Classification Code section.
2. Select a Business Unit.
3. Select a Tax Classification Code.
4. Click Save.
Create Revenue Methods
Create revenue methods to determine how revenue amounts are calculated for contracts.
The following sections describe how you create revenue methods.
Entering Basic Revenue Method Information
To create a revenue method:
1. Click Navigator > Setup and Maintenance, and search for the Manage Revenue Methods task.
2. Click the Manage Revenue Methods link.
Use the Manage Revenue Methods page to create revenue methods and to review, edit, or delete revenue
methods.
3. Click the Create icon to create a revenue method.
4. On the Create Revenue Method page, enter a revenue method name.
5. Specify a status. Select Active to make the revenue method available for use.
6. The following table lists the revenue method classifications from which you can select one to determine the
basis for calculating revenue amounts for transactions on contracts or contract lines.
114
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Revenue Method Classification Description
Amount Based
Recognize revenue as billing events are completed.
As Billed
Recognize revenue as customers are invoiced, using a common set of bill rates, a burden
schedule, or transfer pricing for both invoicing and revenue.
As Incurred
Recognize revenue as costs are incurred, using a revenue-specific set of bill rates, a burden
schedule, or transfer pricing for both invoicing and revenue.
Percent Complete
Recognize revenue based on project progress of a contract line or associated project.
When you select the Percent Complete revenue method classification, the Percent Complete
billing extension is automatically added to the revenue method. The extension automatically
creates a billing event with the percent spent revenue amount for a contract line, or for the
project associated to the contract line.
Percent Spent
Recognize revenue as progress is calculated, based on actual cost to date over budget cost.
When you select the Percent Spent revenue method classification, the Percent Spent billing
extension is automatically assigned to the revenue method. The extension automatically
creates a billing event with the percent spent revenue amount for a contract line.
Rate Based
Recognize revenue as costs are incurred, using a revenue-specific set of bill rates, a burden
schedule, or transfer price rates.
Use this revenue method classification if you are using a fixed price for invoices, or if you
require different burden schedules for invoices and revenue. You can also use this revenue
method classification if the invoice method classification for a bill plan on the same contract
line is percent complete or percent spent.
Note: You can use a revenue method with the As Billed or As Incurred revenue method classification
only when combined with an invoice method that has the Rate Based invoice method classification. In this
situation, the bill rate, burden, or transfer price schedule type selected for that invoice method is used for
both invoicing and revenue recognition.
7. To enable a revenue method for intercompany billing only, select the Use Revenue Method for Intercompany
Billing check box. Use revenue methods with this option to track internal business activity between legal
entities within your enterprise. Deselect the check box if the revenue method is used for billing external parties.
115
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Defining Rate Sources
If the revenue method classification is Rate Based, then you must select one of the following schedule types on the
revenue method for both labor and nonlabor rates.
Bill rate
Burden rate
Cost reimbursable
Transfer price (available if you are using the revenue method for intercompany billing)
Assigning Billing Extensions
Use the Billing Extension Assignment section to add a billing extension to a revenue method. In such a situation,
contract lines that use revenue plans associated with the revenue method use the billing extension to calculate revenue
amounts.
Note: You can't assign client extensions to revenue or invoice methods when using the Oracle Fusion Project Billing
Cloud Service.
Create Invoice Methods
Create invoice methods to determine how invoice amounts are calculated on contracts.
The following sections describe how you create invoice methods.
Entering Basic Invoice Method Information
To create an invoice method:
1. Click Navigator > Setup and Maintenance, and search for the Manage Invoice Methods task.
2. Click the Manage Invoice Methods link.
Use the Manage Invoice Methods page to create invoice methods and to review, edit, or delete invoice methods.
3. Click Create to create an invoice method.
4. On the Create Invoice Method page, enter an invoice method name.
5. Specify a status. Select Active to make the invoice method available for use.
6. The following table lists the invoice method classification from which you can choose one to determine the
sources for invoice amount calculations on contracts or contract lines.
Invoice Method Classification Description
Amount Based
Generate invoices as billing events are completed.
Percent Complete
Generate invoices based on project progress of a contract line or associated project.
Percent Spent Generate invoices as progress is calculated, based on actual cost to date over budget cost.
116
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Invoice Method Classification Description
Rate Based
Generate invoices as costs are incurred, using an invoice-specific set of bill rates, a burden
schedule, or transfer price rates.
7. To enable an invoice method for intercompany billing only, select the Use Invoice Method for Intercompany
Billing check box. Use invoice methods with this option to track internal business activity between legal entities
within your enterprise. Deselect the check box if the invoice method is used for billing external parties.
Defining Rate Sources
If the invoice method classification is Rate Based, then you must select one of the following schedule types on the
invoice method for the source of both labor and nonlabor rates.
Bill rate
Burden rate
Cost reimbursable
Transfer price (available if you are using the invoice method for intercompany billing)
Create Invoice Formats
Create invoice formats to determine how Oracle Fusion Project Billing creates invoice lines.
Configure different invoice formats for labor, nonlabor, and event invoice line items, and specify if you want to use the
format for customer invoices, internal invoices, or both.
Specify how to summarize expenditure items, and the fields you want an invoice line to display. You can configure the
invoice formats to include free-form text on invoice lines.
The following sections describe how you create invoice formats.
Entering Invoice Format Header Information
To create an invoice format:
1. Click Navigator > Setup and Maintenance, and search for the Manage Invoice Formats task.
2. Click the Manage Invoice Formats link.
Use the Manage Invoice Formats page to create new invoice formats and to review, edit, or delete existing
invoice formats.
3. In the Invoice Format Header section, click the Add Row icon.
4. Enter a unique name for the invoice format.
5. Select a Format Type to determine whether the invoice format is used for labor, nonlabor, or events.
6. Select a date from which the information format is available for use. Optionally, select a date to which the
invoice format is available.
7. Select a grouping option to determine the fields displayed on the invoice line and how they are grouped.
117
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
8. Select the Customer Invoice check box to use an invoice format for regular contract invoices. Similarly,
select the Internal Invoice check box to use an invoice format for invoices generated by intercompany and
interproject contracts.
Tip: Select both check boxes if you want to use an invoice format for both customer and internal invoices.
However, the list of values for the Field Name field in the Invoice Format Details section only includes values
that are valid for both options.
9. Select the Fixed Format check box to prohibit distributions from being moved to other invoices lines.
Note: You must select this check box if you select the Internal Invoice check box.
Entering Invoice Format Details
Use the Invoice Format Details section to select the fields you want to display.
1. In the Invoice Format Details section, click the Add Row icon.
2. Enter numeric values in the Start Position and End Position columns to specify where the text in the Field
Name appears on an invoice line.
3. Select the Field Name that will appear on the invoice line.
Note: The fields available for selection are determined by your selection of the Customer Invoice and
Internal Invoice check boxes in the Invoice Format Header section.
4. If you want to replace the default field name for a selected field, enter the name you want to display on the
invoice line in the Text column.
5. Select the Right Justify check box to justify the value of a field to the right, for example in the case of numeric
values.
6. Click Save.
7. Repeat this process for each field you want to include on invoice lines.
Project Performance Reporting
Overview of Oracle Project Performance Reporting Setup
In the Define Project Performance Reporting Configuration activity, you configure reporting components for monitoring
project performance.
The following table lists the setup tasks for Oracle Project Performance Reporting:
Task List or Task Name Description
Define Project Performance Reporting
Configuration
Configure Project Performance Reporting to collect and review project data against defined
performance areas.
Manage Project Unit Options: Performance
Reporting Options
Specify settings and default values for project performance reporting and analytics within a project
unit.
118
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Task List or Task Name Description
Define Key Performance Indicators
Manage project performance measures, key performance indicators, KPI categories, and status and
trend indicators to track and view project performance.
Manage Status Indicators
Create indicators to convey the status and severity of performance for a measure and a performance
category.
Manage Trend Indicators
Update the description and sort order of the status trend indicators.
Manage KPI Categories
Create additional categories to group key performance indicators and to track and view the overall
performance of a project.
Manage Performance Measures
Enable predefined performance measures for summarization. Create custom measures to evaluate
project performance using base measures or retrieve from third-party or legacy sources. Specify the
related measures that are displayed with the performance measure in the KPI analysis region.
Manage Key Performance Indicators
Specify thresholds of possible values for a measure and associate them to status indicators.
Define Region Personalization
Configure region layouts and graph types on the project performance reporting dashboard.
Manage Region Layouts
Configure rows and measures within the region layouts.
Manage Cross Project Comparison Graph
Types
Create and update graph types to control the display name, sort order, and contents of the cross-
project comparison graph region.
Define Summarization Options
Configure options for the summarization process.
Specify Number of Parallel Summarization
Extraction Programs
Specify the maximum number of helper programs that can exist at one time. Data summarization
programs can launch helper programs to manage the load on system resources.
Specify Global Start Date for
Summarization
Specify the date that periodic analysis of summarized data starts. You can't analyze project
performance data by period before this date.
Define Project Performance Reporting
Configuration
Configure Project Performance Reporting to collect and review project data against defined
performance areas.
Manage Project Performance Reporting
Messages
Review and manage messages for Project Performance Reporting.
This chapter provides detailed setup steps for the task Manage Key Performance Indicators.
119
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Create Key Performance Indicators
Create key performance indicators (KPI) to measure how well your organization performs an operational, tactical, or
strategic activity that's critical for the current and future success of the organization.
Note: To create KPIs you must enable a project unit to track key performance indicators.
The following sections describe how to create key performance indicators.
Set Up KPI Categories
Create KPI categories for the project unit to use based on organizational requirements. KPIs are grouped into KPI
categories based on performance areas. Examples are, cost, profitability, financial, and schedule. To create a KPI
category:
1. In the Setup and Maintenance work area, go to the Manage KPI Categories task.
2. Use the Manage KPI Categories page to define KPI categories that group KPIs belonging to a specific
performance area.
3. Decide on what KPI categories your organization uses, such as cost, profitability, and financial.
4. Replace the User-defined KPI category 4 KPI Category field with a KPI category name. Optionally add a
description.
5. Select the KPI categories you want to Enable for Use.
6. Enter a Start Date to indicate the date from which the KPI category will be available for use. Optionally specify a
End Date.
7. Click Save and Close.
Entering Basic KPI Information
To create a KPI:
1. In the Setup and Maintenance work area, go to the Manage Key Performance Indicators task.
2. Use the Manage Key Performance Indicators page to search for, create, or edit KPIs.
3. Click the Create icon.
4. Use the Create Key Performance Indicator page to specify KPI details, trending information, and threshold
levels.
5. The following table lists the information you need to provide in the General Information section.
Option Name Decision Notes
KPI Name
What should the KPI name be?
Choose a name for the KPI based on the
measure name you select and the name of
the group or project this KPI will be used.
For example, your organization may use the
same measure to create KPIs for different
groups or projects. In such cases it's
recommended to give a specific meaningful
name to the KPI. If you select the measure
120
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
ITD budget margin (%), you can name the
KPI Group 1 ITD Budget margin (%).
Measure
Which performance measure should you
use?
You're creating a KPI to calculate the
Inception-to-Date margin percentage for a
project.
Measure Format
None
Populated automatically by the application
based on the selected measure, such as
percentage, hours, currency. The measure
format determines how you enter threshold
values for the KPI.
KPI Category
What category does the KPI you selected fall
into?
You create and enable up to five KPI
categories such as cost, profitability, and
effort on the Manage KPI Categories page.
Currency Type
Which currency type must the KPI use?
You can select either the project currency
or the project ledger currency depending
on what's enabled for the project unit you
selected.
Note:
You can't change the currency type once
a KPI is in use.
Calendar Type
Which calendar type must the KPI use?
You can select either the accounting
calendar or project accounting calendar
depending on what's enabled for the project
unit you selected.
Note:
You can't change the calendar type once
a KPI is in use.
Project Unit
For which project unit would you want this
KPI to be available?
If you don't select a project unit, then you
can attach the KPI to any project irrespective
of which project unit the project belongs to.
121
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
If you select a project unit, then you can
attach the KPI to any project that belongs to
the same project unit.
You can't change the value of the project
unit after the KPI is attached to a project.
6. Optionally enter a description.
7. Enter a From Date to indicate the date from which the KPI to be available for use. Optionally specify a To Date.
8. Use the Trending section to specify if the current KPI values, project progress, and overall project health are
better, worse, or the same as previous values.
9. The following table lists the information you need to provide:
Option Name Decision Notes
Trend Indicator
Does an increase in the KPI value mean the
trend is positive?
Specify if an increase or decrease in the
value of the KPI you're creating is a positive
or a negative thing for the performance of a
project.
For example, an increase in the ITD budget
margin percentage is a positive trend in the
project.
Tolerance Percentage
Should the application tolerate minor
decrease in performance of a KPI when
displaying the trend indicator?
Set a tolerance percentage to define how
much of a change from the previous
KPI value will be tolerated before the
trend indicator changes to indicate worse
performance.
For example, you can specify that the
application can tolerate up to 1 % deviation
for a decrease in ITD Budget Margin
(%) from the previous value, before the
trend indicator changes to depict that
performance of the KPI is decreasing.
122
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
10. Use the Threshold Levels section to specify thresholds to indicate the health status of a KPI. Select one of the
following options:
Multiple threshold levels
Single threshold level value
Single threshold level range
Note: Information you enter in the following sections will vary based on whether the measure format of
the KPI you're creating is percentage, currency, or hours. This procedure is based on a KPI with a currency
measure format.
Specifying Multiple Threshold Level Rules
The Multiple threshold levels option is selected by default. To add or modify multiple threshold levels:
1. Click Add Row.
2. Select a Currency and specify a Decimal Display in the Add Currency and Decimal Display secondary window.
3. Click Save and Close.
4. Click Edit Threshold Levels.
5. Enter the Threshold Start and Threshold End range relevant to the possible KPI values in the Edit Threshold
Levels dialog box.
6. Select a Status Indicator which must be displayed when the KPI value falls in the range you specify.
7. Click Save and Close.
8. Add as many rows as required to set multiple thresholds with different currencies for the KPI.
9. Click Save and Close on the Create Key Performance Indicator page.
Specifying Single Threshold Level Value Rule
To specify a single threshold:
1. Select the Single threshold level value option.
2. Click Add Row.
3. Select a Currency and specify a Decimal Display in the Add Currency and Decimal Display secondary window.
4. Click Save and Close.
5. Click Edit Threshold Levels.
6. Enter the Threshold value.
7. Optionally change the Status Indicator to be displayed for the Greater than or equal to threshold and Less
than threshold rows as relevant to the KPI value.
8. Click Save and Close.
9. Add as many rows as required to set multiple thresholds with different currencies for the KPI.
10. Click Save and Close on the Create Key Performance Indicator page.
Specifying Single Threshold Level Range Rule
To specify a single threshold level range rule:
1. Select the Single threshold level range option.
2. Click Add Row .
3. Select a Currency and specify a Decimal Display in the Add Currency and Decimal Display secondary window.
4. Click Save and Close.
5. Click Edit Threshold Levels.
123
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
6. Enter the Threshold Start and Threshold End range relevant to the possible KPI values in the Edit Threshold
Levels dialog box.
7. Optionally change the Status Indicator to be displayed for the Within threshold range and Outside threshold
range rows as relevant to the KPI value.
8. Click Save and Close.
9. Add as many rows as required to set multiple thresholds with different currencies for the KPI.
10. Click Save and Close on the Create Key Performance Indicator page.
Project Templates
Overview of Project Templates
This table lists the tasks included in the Define Project Templates task list.
Task Name Description
Manage Project Templates
Manage templates to quickly create projects that share common features, attributes, and options.
Create Project Templates
Project templates enable you to quickly create projects that share common features, attributes, and options.
To create a project template:
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Templates task.
2. Click the Manage Project Templates link.
Use the Manage Project Templates page to create project templates and to review or edit existing project
templates. Create a project template based on an existing project template or project, or manually create a
template.
3. To manually create a template, click Create Template.
Use the Create Project Template page to provide basic project template information including the business unit,
project unit, and organization, and to select a project type.
4. Enter a Name and Number for the project template.
5. The following table lists the information you need to provide when creating project templates.
Option Name Decision Notes
Business Unit
What reference data do I want projects to
access?
Selecting a business unit determines which
rate schedules, project types, and invoice
formats projects can use. It also determines
124
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Option Name Decision Notes
the legal entity and which project and task
owning organizations are available for
projects.
Legal Entity
None
Populates automatically based on the
business unit you selected. Change this if
required.
Project Unit
What reference data do I want projects to
access?
Selecting a project unit determines which
class codes, financial and project plan types,
project roles, and statuses projects can use.
It also determines which transaction types
are available for projects.
Organization
Which project and task owning organization
to select?
Selecting a project and task owning
organization are used for reporting, security,
and accounting. It determines the default
organization for the project, quick entry
values, and allows transactions.
Project Type
What is the project type of the project?
Selecting a project type enables you to
control basic project configuration options
for burdening, billing, capitalization, and
project categorization.
Note:
You can't change the project type after
you create a project.
6. Select an Initial Project Status such as Requested.
7. Enter a meaningful Description and click Save and Continue to navigate to the Edit Project Template page.
Use the Edit Project Template page to review basic template information, access project, financial, and
reporting options, and select quick entry fields.
8. In the Edit Project Template page, scroll down to the Quick Entries section.
Use the Quick Entries section to specify the information that users enter when they create a project using this
project template. Quick entry fields allow users to enter certain project information quickly.
9. Click Add Row.
10. Select a value in the Field Name column.
11. If you have selected Classification or Team member as the field name, then select a value in the Specification
column.
Classification: Select the class category to use when creating the classification.
125
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 2
Implement Project Financial Management Applications
Team Member: Select the project role to use when creating the team member.
12. Enter a field label in the Prompt column.
13. Optionally make this a required field.
14. Scroll up to the Setup Options section.
Use the Setup Options section to select which sections, such as basic information, financial options, and
reporting options, are displayed in the project definition after the project is created.
15. Click Save.
126
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
3 Implement Project Execution Management
Applications
Overview of Project Execution Management Offering
Implementation
Implement this offering to configure how project managers, resource managers, and team members execute projects,
track requirements, schedule and collaborate on tasks, and so on.
To implement Project Execution Management offering, you must have the Application Implementation Consultant role
(ORA_ASM_APPLICATION_IMPLEMENTATION_CONSULTANT_JOB) and must have opted in to the offerings applicable
to your business requirements. To manage the opt-in and setup of your offerings, refer to the Oracle Applications Cloud
Using Functional Setup Manager guide.
Here's the list of primary functional areas available in this offering.
Functional Area It Enables You To
Initial Users
Set up users and data roles, import users and roles into application security, import user login history,
and manage applications security preferences.
Users and Security
Set up your initial implementation setup users, hierarchy, and enable users to perform functions
related to their roles.
Project Execution
Configure how you execute projects, manage requirements, schedule and collaborate on tasks, staff
resources, maximize utilization, resolve issues, and complete deliverables. Define and manage project
users, project roles, and calendars.
Project Resource Management
Define attributes required to manage employees and contingent workers. Create and manage
legislative data groups, business units, legal entities, organizations, jobs, resource pools, pool owners,
and pool hierarchies.
Applications Extensions
Manage the common functions that help in maintaining the core application data, establishing
security, maintaining transactional and shared data, and setting the user general preferences.
127
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Common Project Execution Options
Overview of Common Project Execution Options
Tasks that are common across Project Execution Management functional areas are grouped into the Define Common
Project Execution Options task list. You can perform these tasks once and they're applicable in all relevant functional
areas.
Here's the list of tasks in the Define Common Project Execution Options task list along with a brief description.
Task Is This Required? It Enabled You To
Manage Project Implementation Administrator
Yes
Create or identify a project application
administrator to manage and control access to
Project Portfolio Management applications.
Manage Project User Provisioning
Yes
Create and update users and assign enterprise
roles.
Manage Project Roles
No
Create and update roles that are used to control
access to project-level information and for
defining project resource requests.
Manage Project Enterprise Resources
No
Create and update enterprise resources
to assign to projects, tasks, issues, and
deliverables.
Manage Project Shifts
No
Configure shifts to represent a time period that
determines how many hours you work on a day.
Manage Project Workday Patterns
No
Configure workday patterns to represent a
collection of one or more shifts over a number
of days. A pattern repeats for a specific date
range to define the complete schedule.
Manage Project Schedules
No
Configure schedules to define the actual
calendar dates worked, and the pattern shifts to
apply to those dates worked. The date range in
a schedule is defined by a schedule start date
and a schedule end date.
Manage Project Schedule Exceptions
No
Configure schedule exceptions to define
deviations in availability from a schedule.
128
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Create Project Roles
You can set up specific roles and associate qualifications and keywords to each role. When a project manager requests a
resource to fulfill this role on a project, the qualifications and keywords appear on the project resource request.
Note: Project manager and project team member are two predefined project roles that you can't edit or delete as they
have specific functions in a project.
Creating a Role
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Roles task.
2. Click the Manage Project Roles link.
3. On the Manage Project Roles page, click the New icon.
4. Enter a name for the role and click Save.
5. Click the Show More link.
6. In the Default Qualifications and Keywords section, click the New icon to add qualification and keywords for the
role created.
7. Click Save and Close.
Create Calendars for Projects and Resources
You can create the elements that represent project schedules, which are used to define the project and resource
calendars. Project and resource calendars define the standard working and nonworking time for projects and resources.
Working times are the days and total hours in a calendar during which work can occur. Nonworking times in a calendar
are days and total hours for which work should not be scheduled, such as weekends and holidays.
Calendar definition is shared across Oracle Fusion Applications. Project Execution Management provides a predefined
calendar with 8 hours per day, 5 days per week that you can assign to projects and resources. In the predefined
calendar, working days are from Monday to Friday
Note: The standard calendar is predefined and you can't modify it.
In Oracle Fusion Project Execution Management and Oracle Fusion Project Resource Management, only calendars
with the Elapsed schedule type with one workday pattern of 7 days, and one project shift are supported. For example,
available capacity is calculated only for active project and resource calendars with a schedule type of Elapsed. When you
set up calendars for Project Management and Project Resource Management, you can select only the Elapsed schedule
type to use in project and resource calendars.
Schedules are used as a base for project and resource calendars in Project Execution Management applications. The
smallest scheduling unit is a day. For example, you can define the number of hours in a day but, you can't schedule
work for a specific time of the day. The following are the elements of a schedule:
Shifts
Workday patterns
129
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Exceptions
Managing Shifts
A shift is a period of time, typically expressed in hours, that can be defined by a start and end time, or duration. Multiple
shifts per day are not supported in Project Execution Management.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Shifts task.
2. Click the Manage Project Shifts link.
3. On the Manage Shifts page, click the Create Shift list.
4. Select Create Elapsed Shift from the list.
5. Enter name and duration for the selected shift and click Save and Close.
6. Click Done.
Managing Workday Patterns
A workday pattern is a collection of one or more shifts for a specific number of days. A pattern repeats itself for a date
range to define the complete schedule.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Workday Patterns task.
2. Click the Manage Project Workday Patterns link.
3. On the Manage Workday Patterns page, click the Create Workday Pattern list.
4. Select Create Elapsed Workday Pattern from the list.
5. Enter name and days for the pattern. For example, if a workday pattern is a week, define the work pattern as 7
days.
6. In the Workday Pattern Details section, click the Add Row icon and enter the shift details. Note that if work is
carried out on certain days of the week, for instance Monday to Friday, then work day pattern details will only
be from day 1 through day 5.
7. Click Save and Close.
8. Click Done.
Managing Schedule Exceptions
Exceptions are deviations from a schedule. There are two types of exceptions: off period exceptions and work period
exceptions. Off period exceptions convert working days to nonworking days. And, work period exceptions convert
nonworking days to working days. Only full day exceptions are supported.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Schedule Exceptions task.
2. Click the Manage Project Schedule Exceptions link.
3. On the Manage Schedule Exceptions page, click the Create Schedule Exception icon.
4. Enter the details for the exception and click Save and Close.
5. Click Done.
Managing Schedules
Schedules contain workday patterns and exceptions.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Schedules task.
2. Click the Manage Project Schedules link.
3. On the Manage Schedules page, click the Create Schedule list.
4. Select Create Elapsed Schedule from the list.
5. Enter the name and date range for the schedule. The start date of the schedule determines day 1 of the work
pattern. For example, if you pick Monday, December 28, 2015 as the effective from date, then day 1 is a Monday.
If you pick Friday, January 1, 2016 as the effective from date, then day 1 is a Friday.
130
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
6. In the Schedule Details section, enter details in each tab as applicable.
7. Click Save and Close.
8. Click Done.
Set Up Project Management Implementation Options
Specify the default calendar, currency, and full-time equivalent hours. Also, specify the progress exception thresholds
for the project enterprise.
Setting Up the Default Calendars
Calendars determine the standard working and nonworking time, such as weekends and holidays, for resources and
projects. Select the default calendars to assign to resources and new projects.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Management
Implementation Options task.
2. Click the Manage Project Management Implementation Options link.
3. On the Define Project Management Implementation Options page, in the Default Calendars section, select a
value for default project and resource calendars.
4. Click Save and Close.
Entering Progress Exception Thresholds
Progress exceptions are generated when team members enter progress amounts for a proposed start date, finish date,
or planned hours that exceed the defined thresholds. Define the threshold values for task progress in days and hours.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Management
Implementation Options task.
2. Click the Manage Project Management Implementation Options link.
3. On the Define Project Management Implementation Options page, in the Progress Exceptions section, enter the
days and hours.
4. Click Save and Close.
Setting Up a Default Currency
The currency defined is used when a project is created.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Management
Implementation Options task.
2. Click the Manage Project Management Implementation Options link.
3. On the Define Project Management Implementation Options page, in the Default Currency section, select a
currency.
4. Click Save and Close.
Setting Up Common Financial Task Dates
Setting up common financial task dates between work plans and financial plans:
Enables better collaboration between the project manager and the project administrator by providing the same
and consistent task schedule. For example, project administrator's updates in financial tasks are automatically
available for the project manager’s review in the work plan.
131
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Validates the dates in real time in managing project plans. For example, when the transaction and planned
dates are synced, you can only change the task planned dates to the dates valid for the task’s expenditure
items.
To ensure that task dates are the same across work planning and financial planning, regardless of in which of the two
plans the dates are updated, complete the following steps:
1. Click Navigator > My Enterprise > Setup and Maintenance.
2. On the top of the page from the Setup dropdown, select Project Execution Management and then search for
the Manage Project Management Implementation Options task.
3. Click the Manage Project Management Implementation Options link.
4. On the Define Project Management Implementation Options page, in the Define Common Financial Task Dates
section, select Define Common Financial Task Dates Across Work and Financial Planning.
5. Click Save and Close.
Note: For the plans existing at the time of enabling the Define Common Financial Task Dates Across Work and
Financial Planning option, the project manager needs to once sync the dates manually between the two plans. For
more information, see Automatically Sync Dates Between Financial Project Plans and Work Plans in the Using Project
Execution Management guide.
Setting Up Default Full Time Equivalent Hours
Enter the full-time equivalent (FTE) hours for resources that are used to calculate the labor demand FTE hours for
reporting in the Project Hierarchy Dashboard and enterprise project structure. The default value is 520 hours.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Management
Implementation Options task.
2. Click the Manage Project Management Implementation Options link.
3. On the Define Project Management Implementation Options page, in the Default Full Time Equivalent Hours
section, enter hours.
4. Click Save and Close.
Related Topics
Create Project Enterprise Resources
Create project enterprise resources to assign to projects, tasks, issues, or deliverables. You can create labor and expense
type resources to add to projects. You must be a project enterprise resource to access Project Execution Management
applications.
If you manage resource availability and staffing in Oracle Fusion Project Resource Management, you must create
managed project enterprise labor resources to fulfill project resource requests.
This topic describes the manual procedure to create one project enterprise resource. However, you can create multiple
project enterprise resources with Cloud interfaces, processes, or services. Follow this navigation path to open the Create
Project Enterprise Resource window.
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Enterprise Resources task.
2. Click the Manage Project Enterprise Resources link.
132
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Creating a Labor Resource
A project enterprise labor resource is a resource that you can assign to multiple projects. A managed project enterprise
labor resource is a project enterprise labor resource whose availability and staffing are managed in Oracle Fusion Project
Resource Management. You use managed project enterprise labor resources to fulfill project resource requests and
directly assign to one or more projects.
To create a labor resource:
1. Click Create to open the Create Project Enterprise Resource window.
2. Select Labor in the Type field.
3. Select the Create from HCM Person option and select the person name to create the resource from an
employee or contingent worker in Oracle Fusion HCM.
If you create a project enterprise labor resource from an employee in Oracle Fusion HCM, the employee or
contingent worker must have a unique email address in a valid format and an active primary assignment in
HCM.
4. Select the Provision Project Roles option to provision the default role assignments for a resource that you
create from HCM. If you don't create the resource from an employee or contingent worker, then enter the
resource name and a unique e-mail address. Enable the Request User Account option to request a user
account and provision the default role assignments for the user.
Note: If you're implementing Project Resource Management, you don't have to create managed project
enterprise labor resources from HCM persons. The application maintains resource available capacity for
resources that are not HCM employees or contingent workers.
5. Enter the resource's personal details.
The default calendar is from the Define Project Management Implementation Options page.
The default primary project role is Team Member.
6. Upload a resume attachment to include text from the resource's resume in searches for keywords that are
entered on project resource requests.
7. To create a managed project enterprise labor resource, select the Manage resource availability and staffing
option.
Note: Only managed project enterprise labor resources are eligible to fulfill project resource requests in
Project Resource Management.
8. Select a resource pool if you enable this option. The default resource pool is the Resources with No Pool
Membership pool.
9. Enter the cost rate and bill rate for the resource.
The cost rate and bill rate that you enter here are used as the default rates for new resource requests, and for
resources that the project manager or project resource manager adds to the Manage Project Plan page and the
Manage Project Resources page.
10. Click Save and Close.
Creating an Expense Resource
A project enterprise expense resource is a resource that you can assign to projects or tasks to track expenses in Project
Execution Management applications.
133
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
To create an expense resource:
1. Click Create to open the Create Project Enterprise Resource window.
2. Select Expense in the Type field.
3. Select the Create from Expenditure Type option and select the expenditure type to create the resource based
on an expenditure type that is defined in Oracle Fusion Project Foundation.
If you don't create the resource from an existing expenditure type, enter the expense resource name and
description.
4. Click Save and Close.
Related Topics
Project Enterprise Labor Resource
Project Enterprise Expense Resources
Import Project Enterprise Resources
Set up Conditions and Import HCM Person
Project Management Configuration
Overview of Project Management Configuration
In the Define Project Management Configuration activity, you configure Oracle Fusion Project Management to manage
projects, tasks, requirements, deliverables, and resources, and to track and resolve issues. This activity contains
advanced setup tasks that aren't required for a typical implementation of Project Execution Management applications.
This table lists the setup tasks in the Define Project Management Configuration task list.
Task or Task List Description
Manage Project Management
Implementation Options
Specify default attributes for the project enterprise such as calendars, progress exception thresholds,
currency, FTE hours, and the email banner.
Manage Enterprise Project Codes
Create and update enterprise project codes to capture additional details on a project using a
predefined value set, free text, or numeric data type.
Manage Enterprise Task Codes
Create and update enterprise task codes to capture additional details on a project task using a
predefined value set, free text, or numeric data type.
Manage Issue Types
Create and update issue types such as the General issue type.
Manage Deliverable Types
Create and update deliverable types such as the General deliverable type.
Manage Attributes for Issues and
Deliverables
Create and update attributes to capture additional details for issues and deliverables using a
predefined value set, free text, or numeric data type.
134
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Task or Task List Description
Define Project Requirement Configuration
Configure Oracle Fusion Project Management to track requirements, such as features and backlog
items, for products and product families.
Manage Project Management Messages
Review and manage messages for Oracle Fusion Project Management.
Manage Project Management Attachment
Categories
Review and manage attachment categories for Oracle Fusion Project Management.
Set Up the Enterprise Project Structure
Use the enterprise project structure (EPS) to allow summarization of project data to a higher level of categorization.
Project application administrators can group projects in the enterprise, add owners and delegates, for purposes of
reporting to project executives.
To set up the EPS, project application administrators must do the following:
Create elements and arrange them in a hierarchy.
Add participants as owners, delegates, and viewers to each element as appropriate. Participants at parent
elements receive the same role automatically for child elements.
Note: A participant must also be assigned the Project Executive role to access the Project Hierarchy
Dashboard.
Submit the Update EPS Data process.
Creating an Enterprise Project Structure
You can create up to 10 levels in the project structure.
1. Click Navigator > Setup and Maintenance, and search for the Manage Enterprise Project Structure task.
2. Click the Manage Enterprise Project Structure link.
3. In the Enterprise Project Structure section, select a project element.
4. Click the Add Child Element icon.
5. In the Add Child Element window, enter a name and description for the EPS element.
6. Do the following to add participants to an EPS element in the Participants section:
a. Enter a direct owner in the name column.
b. Enter a direct delegate in the name column.
c. Click Add Direct Viewer to add additional viewers for the EPS element.
d. Click Save and Close.
7. To organize projects into your EPS elements, select the Unassigned Projects element to view all unassigned
projects. Newly created projects are automatically assigned to Unassigned Projects element.
8. Perform the following steps to move unassigned projects to the relevant elements:
a. Select an unassigned project.
135
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
b. Click the Move Project button.
c. In the Move Projects window select the element to which you want to move the project.
d. Click Save and Close. Alternatively, you can also drag and drop projects from the Unassigned Project
element to move the unassigned projects to relevant element.
9. Click Done.
Updating EPS Data
1. Navigate to the Scheduled Processes page.
2. On the Scheduled Processes page, click Schedule New Process.
3. In the Schedule New Process window, search and select the Update EPS Data process.
4. Click OK.
5. In the Process Details window, click Submit.
6. Click OK on the confirmation message.
7. Alternatively, a participant can use the Update EPS Data action on the Project Hierarchy Dashboard to update
EPS data.
Manage Oracle Social Network Objects for Project Execution
Management
Use Oracle Social Network objects to share and collaborate on key attribute information from the application with
stakeholders. This helps in making better business decisions based on the information that you obtain and analyze
within your social network.
Managing the Oracle Social Network Objects
Follow these steps to manage Oracle Social Network objects:
1. In the Setup and Maintenance work area, go to the Manage Oracle Social Network Objects for Project
Execution Management task:
Offering: Project Execution Management
Functional Area: Project Execution
2. In the Business Objects section, expand the Oracle Social Network Objects.
3. Expand Project Management and select an object from the list. The attributes for the selected object are
displayed in the Attributes section.
4. In the Attributes section, click Add. The Select Attributes window opens.
5. Enable or disable an attribute and click OK. The changes are reflected in the Attributes section.
6. Select the object and click Enable Object . The Enable Object window opens.
7. The following table lists the options that decide how the business object integrates with Oracle Social Network.
Select an option.
Option Outcome
Manual
User decides whether to share the object instance in the social network. This is the
recommended option.
136
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Option Outcome
Automatic
Shares all instances of the object in the social network.
No
Doesn't share any of the object instance in the social network.
8. Click OK.
9. Click Save.
Project Resource Management Configuration
Project Resource Management Set Up
In the Define Project Resource Management Configuration task list, you configure Oracle Project Resource Management
to manage the availability and staffing of resources, fulfill project resource requests, and monitor resource utilization.
This activity contains advanced setup tasks that aren't required for a typical implementation of Project Execution
Management applications. Here are the tasks and task lists within the Define Project Resource Management
Configuration activity.
Here's a table that lists the task that help you set up tasks for creating and managing resources
These tasks help you create and manage resources. You will also find these tasks in the Define Project Enterprise Labor
Resources task list.
Task or Task List Description
Define Attributes for Employees and
Contingent Workers in Human Capital
Management
Use this Oracle Fusion HCM task list to define attributes that are required for setting up employees and
contingent workers in HCM.
Manage Resource Pools
Configure resource pools to which the resources are assigned.
Manage Project Enterprise Labor Resource
Maintenance Conditions
Configure conditions and import employees and contingent workers from HCM as project enterprise
resources in Project Execution Management.
Manage Target Utilization Percentages
Set up the percentage of hours that the resources are expected to work on project assignments.
Update Resource Utilization Data process
Run the Update Resource Utilization Data process to evaluate the resource utilization.
Submit Process to Maintain Project
Resource Search Index process
Maintain Project Resource Search Index process
Here's a table that lists the task that help you set up tasks for a resource request.
137
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Task or Task List Description
Manage Project Resource Management
Value Sets
Review and manage value sets for Oracle Fusion Project Resource Management.
Manage Project Resource Management
Descriptive Flexfields
Define validation and display properties of descriptive flexfields, which are used to add attributes to
project resource requests.
Manage Resource Staffing Statuses
Create additional staffing statuses to communicate the evaluation of nominated resource.
Here's a table that lists the general tasks resource management.
Task or Task List Description
Manage Project Resource Management
Implementation Options
Specify options used to control workflow notifications.
Manage Standard Lookups
Create and update the project assignment reservation reasons.
Note:
This task is outside of the Project Resource Management functional area of the Setup and
Maintenance work area.
Manage Project Resource Management
Messages
Review and manage messages for Oracle Fusion Project Resource Management.
Manage Project Resource Management
Attachment Categories
Review and manage attachment categories for Oracle Fusion Project Resource Management.
Related Topics
How can I edit the list of valid assignment reservation reasons?
Manage Employees and Contingent Workers
You can create employees or contingent workers as users, update their talent profiles, then enable them as managed
project enterprise labor resources to use in Oracle Fusion Project Resource Management.
Note: If you are using a full implementation of Oracle Fusion Human Capital Management, employees and
contingent workers are already set up and you can skip these steps.
To create an employee, contingent worker, or both as a user:
1. Click Navigator > Setup and Maintenance, and search for the Manager Users task.
138
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
2. Click the Manager Users link.
3. On the Search Person page, click the Create icon.
4. On the Create User page, enter the last name, e-mail, and hire date of the employee or contingent worker.
5. Enter the personal details of the employee or contingent worker.
6. Optionally enter user name.
If you select the option to send the user name and password, the user name and password are sent to the user's
primary e-mail. You can send this information only once.
If you deselect this option, you can send the user name and password to the user later by running the Send
User Name and Password E-Mail Notification process. If the user's e-mail account isn't configured, then the
user name and password are sent to the user's manager.
7. In the Person Type field, select Employee, Contingent Worker, or Employee and Contingent Worker. Enter the
remaining details in the Employment Information section.
8. Select the resource role, reporting manager, and organization.
9. Search for a role, then click Add Role to provision the role manually. Users keep the manually added roles until
all their assignments are terminated or you deprovision the role.
If you autoprovision roles, then users inherit roles that match their assignments and the assignments appear in
the Role Requests table. Similarly, they are removed from roles that don't match their assignments.
10. Click Save and Close. The application immediately sends Oracle Identity Management the request to create the
user account and provision the roles.
Manage Maintenance Conditions for Project Enterprise Labor
Resource
You can create and update project enterprise labor resources from HCM persons by defining a project enterprise labor
resource maintenance condition and submitting the Maintain Project Enterprise Labor Resources process.
The process creates and updates project enterprise labor resources from the employees and contingent workers who
match the maintenance condition. The records are processed in ascending order based on the process order value. If
multiple conditions have the same process order value, then records are processed in ascending alphabetic order based
on the condition name.
The maintenance condition includes:
The person type and optionally, specified jobs.
Attributes that the project enterprise resources are assigned on creation.
To define a project enterprise labor resource maintenance condition:
1. Click Navigator > Setup and Maintenance, and search for the Manage Project Enterprise Labor Resource
Maintenance Conditions task.
2. Click the Manage Project Enterprise Labor Resource Maintenance Conditions link.
3. Click the Create icon.
4. On the Create Condition page, enter a name for the condition in the Name field.
5. Enter a value in the Process Order field.
Note: If a project enterprise labor resource doesn't already exist for that person, then the process creates
a resource for the condition with the process order value of one. The process doesn't create more than one
resource for the same person even if subsequent conditions apply to the person.
139
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
6. Optionally enter a description.
7. Select a person type from the Person Type choice list. The person type can be employee, contingent worker, or
both types.
8. Optionally, select a business unit and an organization.
9. To create resources from HCM persons with specific jobs, select a job from the Jobs choice list. Click Add to add
another job.
10. Select the Manage resource availability and staffing check box to create managed project enterprise
resources.
Managed project enterprise labor resources are managed in Oracle Fusion Project Resource
Management.
If you select this option, then by default the resources are added to the Resources with No Pool
Membership resource pool. You can change this selection to move the resources to another resource
pool.
11. Select the resource calendar from the Calendar choice list. A resource calendar defines the work schedule
for project enterprise labor resources, and includes working days and hours, exceptions, and holidays. This
calendar will be assigned to all resources that match the project enterprise labor resource maintenance
condition.
12. Select the primary project role to assign resources from Primary Project Role. For example, by selecting
Oracle Database Administrator, you can create project enterprise labor resources who are Oracle Database
Administrators.
13. Select the currency and enter the cost rate in the Cost Rate fields.
14. Select the currency and enter the bill rate in the Bill Rate fields.
15. Click Save and Close on the Create Condition page.
16. On the Manage Project Enterprise Labor Resource Maintenance Conditions page, click Maintain Project
Enterprise Labor Resources to submit the process of the same name. Run the process to:
Create resources.
Update resources with HCM changes.
Remove resource availability for staffing.
Maintain the resource search index.
The following table describes the process options that you can select.
Option Description
Create resources
Create project enterprise labor resources from employees or contingent workers based on
selection criteria and attributes defined in maintenance conditions.
Update resources
Apply any of the following changes that were made to HCM resources to existing project
enterprise labor resources:
Name
Image
Email address
Remove resource availability
Disable the manage resource availability and staffing option for resources who are employees
or contingent workers with no active HCM primary assignment.
140
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Option Description
Resources who aren't employees or contingent workers are ignored when determining if a
resource has an active primary assignment in Oracle Fusion HCM.
Resource pool owners receive a notification when resources in their pools are no longer
eligible to fulfill project resource requests.
Note: If you select Remove Resource Availability, then the resources won't be able to fulfill project resource
requests.
17. Click Submit. You can run the Maintain Project Enterprise Labor Resources process from either the Manage
Project Enterprise Labor Resource Maintenance Conditions page or Scheduled Processes page.
Related Topics
Set up Conditions and Import HCM Person
Project Enterprise Labor Resources Report
Manage Resource Pools
Build resource pools to organize managed project enterprise labor resources in hierarchical relationships. You group
resources logically for the purposes of staffing and managing resources, and reporting on utilization.
You can review the resource pool details, change the resource pool hierarchy, and move resources from one resource
pool to another.
1. Click Navigator > Setup and Maintenance, and search for the Manage Resource Pools task.
2. Click the Manage Resource Pools link.
3. On the Manage Resource Pools page, click Expand next to the All Resources folder.
The pools named All Resources and Resources with No Pool Memberships are predefined. The All
Resources pool is always at the top of the resource pool hierarchy.
The Resources with No Pool Memberships pool is the default pool for new resources.
4. To view the details of a resource pool:
a. Place your cursor over a resource pool to view the name of the pool owner.
b. Select the resource pool to view the members of the resource pool in the Resource Pool Members
section.
5. Resource pool hierarchies represent how the organization manages and reports on resources. For example,
resource pools can group resources in a hierarchy by geographic locations, cost centers, skill sets, or primary
project roles. To change the resource pool hierarchy by moving a pool to another hierarchy:
a. Select the resource pool.
b. Click Move Resource Pool. You can also drag and drop a pool from one hierarchy to another.
c. In the Move Resource Pool secondary window, select from the Target Parent Resource Pool choice list.
d. Click Save and Close.
6. To move a resource to another resource pool:
a. Select the resource pool in the Resource Pool section.
141
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
b. In the Resource Pool Members section, select the member.
c. Click Move Resources. You can also drag and drop a member from one pool to another.
d. In the Move Resources secondary window, select the target pool from the Target Resource Pool choice
list.
e. Click Save and Close.
Related Topics
Resource Pools
Who can be a member of a resource pool?
Can I delete a resource from a resource pool?
Update Skills and Qualifications for Project Enterprise Labor
Resources
Resource managers consider resources' skills and qualifications when searching for resources to fulfill open project
resource requests.
Content types are the skills, qualities, and qualifications that you track in talent profiles. Oracle Fusion Project Resource
Management supports the following predefined HCM content types:
Licenses and Certifications
Competencies
Degrees
Honors and Awards
Memberships
Languages
Project enterprise labor resources can update their own skills and qualifications from the My Portrait page. After
completing work on a project or after completing training or receiving certifications, resources may want to update their
competencies and other qualifications to reflect their updated skills.
To update your skills and qualifications:
1. Navigate to My Portrait.
2. Click the Next icon until Experience and Qualifications appears.
3. Click the Experience and Qualifications icon.
4. Click Edit Skills and Qualifications in the Skills and Qualifications section.
5. Select a content type that is supported by Oracle Fusion Project Resource Management from the Content Type
choice list. For example, select Competencies.
6. Click Add.
7. On the Select and Add secondary window, search for and select a competency.
8. Click OK.
9. In the Competencies section, select a proficiency.
10. Click Expand to enter the details.
Note: The attributes for each content type vary. Enter the values required for the content type that you
selected.
142
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
11. Click Submit.
12. Click Yes in the warning message window.
13. Click OK in the confirmation message window.
Submit the Maintain Project Resource Search Index Job Set
Submit the Maintain Project Resource Search Index job set to update the resources that appear on the Search and
Evaluate Resources page when a resource manager searches for resources to fulfill project resource requests.
The job set consists of a set of processes that facilitate efficient and rapid searches for qualified resources.
Resource managers can't search for resources or view resource details if the search index isn't available for a project
resource request with qualifications or keywords. For project resource requests without qualifications and keywords,
resource managers can search for and evaluate resources based on resource availability even if the search index isn't
current or available.
CAUTION: The search index isn't available if the Maintain Project Resource Search Index job set process fails, or while
the process is running.
To submit the job set:
1. Click Navigator > Setup and Maintenance, and search for the Submit Process to Maintain Project Resource
Search Index task.
2. Click the Submit Process to Maintain Project Resource Search Index link.
3. Optionally schedule the job set to run at specific times. Setting up a schedule ensures that the index is updated
on a regular basis, and has the current qualifications and proficiency information for your resources. To define a
schedule:
a. Click the Schedule tab.
b. Select the Using a Schedule option.
c. Select the date and time.
4. Optionally define a notification.
a. Click the Notification tab.
b. Click the Create icon.
c. In the Create Notification secondary window, enter the e-mail address of the recipient.
d. Select a condition from the list. The recipient receives a notification when the condition is true. For
example, you can choose to send an e-mail to the recipient when the job set is executed successfully.
5. Optionally enter submission notes in the Submission Notes field.
6. Click Submit.
7. Click OK in the confirmation message window. The job set runs immediately unless you specified a schedule.
8. Navigate to the Scheduled Processes work area.
9. Review the status of each process in the job set on the Scheduled Processes page.
10. Verify that the status of the following processes is Succeeded on the Scheduled Processes page.
Maintain Project Resource Single Attribute Filters
Maintain Project Resource Qualification Index
Maintain Project Resource Qualification Filters
Maintain Project Resource Search Index Job Set
143
Oracle Fusion Cloud Project Management
Getting Started with Your Project Management
Implementation
Chapter 3
Implement Project Execution Management Applications
Note: When you submit the Maintain Project Enterprise Labor Resources process, you also
automatically submit the Maintain Project Resource Search Index job set.
Manage Target Utilization Percentages
Target utilization is the percentage of hours that project enterprise labor resources are expected to work on project
assignments compared to their available hours. Oracle Fusion Project Resource Management compares the target
utilization percentages with projected and actual utilization for project resources in the
You can define a target utilization percentage for your enterprise and define target utilization percentage overrides for
specific jobs. The override percentage applies to resources with a job title in Oracle Fusion HCM, namely resources who
are employees or contingent workers.
To define target utilization percentage and job specific overrides:
1. Click Navigator > Setup and Maintenance, and search for the Manage Target Utilization Percentages task.
2. Click the Manage Target Utilization Percentages link.
3. Enter the enterprise target utilization percentage in the range of 0 through 100. The default enterprise target
utilization percentage is 100.
4. Click the Add row icon on the Manage Target Utilization Percentages page.
5. Select a job from the Job choice list.
6. Enter a percentage in the range of 0 through 100 in the Target Utilization field. The default target utilization
percentage is 100. If a resource's job doesn't have a target utilization percentage, then the application uses the
enterprise target utilization percentage for that resource.This percentage:
Applies to all project enterprise labor resources with the specified job.
Overrides the enterprise target utilization percentage.
7. Click Save and Close.