COST RISK MANAGEMENT
NCHRP 25-25(39): GUIDE TO ENVIRONMENTAL COST ESTIMATING FOR TRANSPORTATION PROJECTS 37
EXHIBIT 1
Common Cost Risk Elements Related to Environmental Costs and Associated Best Practices
Nature of Risk How the Risk Impacts the Project Ways to Control or Avoid Costs
members. The later the discovery, the greater the
impact on project cost.
status for potential historic properties that are not listed, and for which a
Determination of Eligibility is not yet complete. The DOE process should be
completed as soon as possible to avoid late changes.
Project drift When environmental issues are not determined early,
and the progress of the project is not outlined from the
beginning, projects can chase one environmental
issue after another in succession until the project team
is exhausted, the public loses interest, and the political
consensus to do the project is lost.
Some opposition groups deliberately use
environmental regulations to stall projects, hoping that
these factors will in fact occur.
Projects will be attacked at their weakest link, not
necessarily on the aspect related to what the
opposition is interested in. All parts of the study need
to be rigorous to survive an organized opposition.
Environmental processes are the key entry to
opposing a project because they are the only aspects
of the project that by law require public input and
process. Normally, most legal challenges are lost on
procedural issues, not substantive issues, but poor
substance can relate to poor procedures. Both need to
be rigorous.
Projects need to anticipate and identify issues that will develop into major work items
or require a long time frame as early as possible, then plan how to address them,
and carry out the plan.
A decision process with roles and responsibilities should be a part of the initial plan.
The basic agenda of future meetings should be planned from the beginning, with
clear decision points for items such as establishing Purpose and Need, evaluating
concepts, defining the final alternatives to be studied, developing screening or
selection criteria, and the preferred alternative selection process. Extra meetings
should be planned at the beginning for times when it will take more than the
scheduled meetings to reach a decision.
Political decision makers should be made aware from the very beginning if there are
laws governing choices which will be outside their authority or influence such as ESA
and section 4(f).
All contacts with outside agencies should be documented, including a list of people
present at the meeting. All issues, regardless of whether the DOT finds them
relevant should be addressed and agreement reached either through discussion,
research, changes in the design, or mitigation. Acceptance of each agreement
should be documented.
All parts of the DEIS/FEIS or EA/REA/FONSI should be performed at the required
level. Having no weak links in the process or documentation is the best insurance
against legally driven attacks on the project. There is no way to prevent attempts to
sue, but there are ways to make the project process least vulnerable so that the
DOT will prevail in the event of a suit.
Managing the flow of decision making, addressing issues early, anticipating issues
and doing proper research, analysis, avoidance, minimization, mitigation, issue
resolution and design are the strongest methods for avoiding project drift, cost
increases, and potential project cancellation.
Losing the project
purpose to
environmental
To keep the peace with public opposition, agency
representatives, the Project Manager and Project
Development Team allow any requested mitigation or
All of the mentioned add-ons exist today as legitimate aspects of public highway
projects in the US. Any of them are appropriate, in the proper setting. However, none
of them are appropriate for all projects. Controlling environmental cost risk relies on